How long do building permits take in each San Francisco neighborhood?

In San Francisco, of the 18,935 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 17,290 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 98 days of being issued, down from 123 days the year before. The city as a whole.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. Each neighborhood’s page has the quarter-by-quarter record, a chart to embed and downloads. How this is calculated.

NeighborhoodPermits issued
filed October 2025 through September 2026
Median days to issueA year earlierReached final
filed October 2023 through September 2024
Median days issue to finalThe year beforeNever finaled
since 2000
San Francisco (all)18,9350017,2909812326%
Bayview Hunters Point477045951278421%
Bernal Heights62700589949425%
Castro/Upper Market6920062110313229%
Excelsior41600502689824%
Glen Park274002747813722%
Haight Ashbury4030040510012933%
Hayes Valley345013079012433%
Inner Richmond487004628411330%
Inner Sunset6850062111011727%
Lone Mountain/USF308002649213328%
Marina7040067411614029%
Mission1,053008629210931%
Nob Hill4590040011215835%
Noe Valley778006809814127%
Oceanview/Merced/Ingleside345003576911221%
Outer Mission296002727412122%
Outer Richmond9160086710312426%
Pacific Heights6780060910612732%
Portola20900213639824%
Presidio100432%
Presidio Heights3870029710918231%
Russian Hill4330040810414232%
Seacliff1250012817215123%
Sunset/Parkside1,493001,5608410823%
Twin Peaks2020021110211821%
Visitacion Valley16700146709923%
West of Twin Peaks1,283001,2339913120%
Western Addition300002321029828%
North Beach3211122910613730%
Potrero Hill4171032310713726%
Tenderloin219122399014731%
South of Market4202636213714728%
Chinatown3295537510115227%
Financial District/South Beach2,182631,6319910719%
Japantown9588639110029%
Mission Bay2059616613913223%
Treasure Island2319262020627031%
Lakeshore16528861958827%
Golden Gate Park111104031%
Lincoln Park20318%
McLaren Park33101278623%

A blank median means fewer than 5 permits in the window. “Reached final” counts the permits filed in those quarters that have a final sign-off; the median is measured from the day the permit was issued. 798 of 801,386 permits since 2000 name no neighborhood and are in the city row only.

How this is calculated

Approved means the city issued the permit; the first stage counts days from filing to issue over the permits filed in the last four complete quarters, against the four before them. Final sign-off means the city’s own status is “complete”; the second stage counts days from issue to completion over permits filed in the last four quarters that ended two or more years ago, so that most have had time to finish. Inspection records are not yet included. A median needs at least 5 permits. Never finaled is no final sign-off three years after issue (or filing, if never issued), for a permit not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended; those permits are in the counts and not in the medians, which therefore understate the real wait. A permit’s neighborhood is the Analysis Neighborhood the city writes on it. Each neighborhood’s page carries the full note. How to read these records.