How long do building permits take in San Francisco's Inner Richmond neighborhood?

In the Inner Richmond neighborhood of San Francisco, of the 487 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 462 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 84 days of being issued, down from 113 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's InnerRichmond neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/inner-richmond · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026487 issued0558 issued0
Permit issued to final sign-offOctober 2023 through September 2024462 finished84396 finished113

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q47400too recent
2026-Q399760301316750too recent
2026-Q213712905053471220too recent
2026-Q114413104173571590too recent
2025-Q4162151042108692320too recent
2025-Q315114305196772580too recent
2025-Q2178169090131602790too recent
2025-Q112912302995502530too recent
2024-Q4132123073861133750too recent
2024-Q3159145050113693400yes
2024-Q2201192069148703480yes
2024-Q11421310661041083780yes
2023-Q4139129010597914492yes
2023-Q3149141010610410643131yes
2023-Q216315603510912759036yes
2023-Q11341240459812460820yes
2022-Q413712001268511457331yes
2022-Q313913201829512555227yes
2022-Q21381290509915465929yes
2022-Q114413608011624067517yes
2021-Q41049701647617177619yes
2021-Q311710401087918266328yes
2021-Q211811311229118766421yes
2021-Q1120110332088213663326yes
2020-Q41501352819610615362229yes
2020-Q31611404144922061,14257yes
2020-Q25846534289126624yes
2020-Q114612901537825962850yes
2019-Q4238216015012120968699yes
2019-Q3249245085141133685101yes
2019-Q2265245051119137684126yes
2019-Q120218903211111449280yes
2018-Q42282140129106132710101yes
2018-Q3261251043127137665121yes
2018-Q2262249065130164723115yes
2018-Q121420308710712943392yes
2017-Q42122020771119654789yes
2017-Q33052870442176184900108yes
2017-Q2229220022912119665894yes
2017-Q118517601029514669677yes
2016-Q417316401158612273475yes
2016-Q3227216023813018654182yes
2016-Q220519309110511649785yes
2016-Q117716907510514147156yes
2015-Q41851820949414442482yes
2015-Q321420702811110747589yes
2015-Q221220204812814136261yes
2015-Q118717905912411454449yes
2014-Q416215707310316357149yes
2014-Q320720102910617455485yes
2014-Q219819103010411842382yes
2014-Q11781720349714062170yes
2013-Q4155153034958537050yes
2013-Q3161158024888446265yes
2013-Q21581500279710251250yes
2013-Q1138134016628342365yes
2012-Q4142136010799436752yes
2012-Q31851820691119935666yes
2012-Q2164157013858933271yes
2012-Q112711706675624250yes
2011-Q4146145039768850064yes
2011-Q318718202210310247379yes
2011-Q2148146020846225356yes
2011-Q114914408895635755yes
2010-Q4160153042879835763yes
2010-Q3172165012917638667yes
2010-Q21851800131006841377yes
2010-Q11251200216811240851yes
2009-Q4132125046637444257yes
2009-Q317216507959952063yes
2009-Q215814908739965873yes
2009-Q11581490128210242757yes
2008-Q417517005898134072yes
2008-Q3219216031127133491yes
2008-Q223222501010285323108yes
2008-Q1229222038998300121yes
2007-Q42762740710598366149yes
2007-Q3216212051039229996yes
2007-Q219218803929835174yes
2007-Q119719100938625878yes
2006-Q4205201008311126887yes
2006-Q3226221001008032987yes
2006-Q22192150010810633480yes
2006-Q112712200699128235yes
2005-Q41601590377814231145yes
2005-Q3195193009110534956yes
2005-Q2170167039928830033yes
2005-Q117817703010010526945yes
2004-Q4181171014907827944yes
2004-Q3188185008910936244yes
2004-Q2164163063806626946yes
2004-Q115515205659938848yes
2003-Q4163159022709225846yes
2003-Q321120100655528384yes
2003-Q2223214001007217769yes
2003-Q115915800858323727yes
2002-Q41281240178658133124yes
2002-Q3160148007810225439yes
2002-Q21811760451109630312yes
2002-Q115214806282982993yes
2001-Q412812103373912312yes
2001-Q31131080138591343405yes
2001-Q2161158031891013110yes
2001-Q11201150129681003255yes
2000-Q4138133058781604502yes
2000-Q31741700131961184902yes
2000-Q2165160047841155770yes
2000-Q11581530117801624612yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

5,507 of the 18,493 building permits filed since 2000 (30%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Inner Richmond neighborhood

Shown apart, with their own page here: bathroom remodel (2,738 filed, 1,981 finished; contractors); kitchen remodel (2,379 filed, 1,729 finished; contractors); stairs (1,267 filed, 921 finished; contractors); deck (636 filed, 449 finished; contractors); roof deck (131 filed, 82 finished; contractors). Other types: 13,632 permits.

Nearby neighborhoods

Presidio Heights, Presidio, Golden Gate Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.