How long do building permits take in San Francisco's Golden Gate Park neighborhood?

In the Golden Gate Park neighborhood of San Francisco, only 1 of the building permits filed from October 2025 through September 2026 has been issued, too few for a reliable figure. Of the 10 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 40 days of being issued.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's Golden GatePark neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/golden-gate-park · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20261 issuedunder 56 issued11
Permit issued to final sign-offOctober 2023 through September 202410 finished403 finishedunder 5

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q31000too recent
2026-Q22100too recent
2025-Q41000too recent
2025-Q31110too recent
2025-Q22210too recent
2025-Q12210too recent
2024-Q43110too recent
2024-Q366161465561820yes
2024-Q12220yes
2023-Q44430yes
2023-Q22211yes
2023-Q11110yes
2022-Q41110yes
2022-Q33303yes
2022-Q24431yes
2022-Q14431yes
2021-Q44422yes
2021-Q34431yes
2021-Q23330yes
2021-Q17721254843yes
2020-Q41000yes
2020-Q32211yes
2020-Q14422yes
2019-Q45502441yes
2019-Q35423yes
2019-Q24413yes
2019-Q14330yes
2018-Q4769620664507200yes
2018-Q32220yes
2018-Q25515437141yes
2018-Q14404yes
2017-Q43220yes
2017-Q33211yes
2017-Q26601233yes
2017-Q13312yes
2016-Q42220yes
2016-Q23321yes
2015-Q23321yes
2015-Q1870186554301yes
2014-Q42100yes
2014-Q32211yes
2014-Q2775795331152yes
2014-Q13330yes
2013-Q43312yes
2013-Q32211yes
2013-Q2551432yes
2013-Q166817232yes
2012-Q42211yes
2012-Q33330yes
2012-Q28645942yes
2012-Q16606742yes
2011-Q43312yes
2011-Q35504623yes
2011-Q22211yes
2011-Q13321yes
2010-Q41000yes
2010-Q34321yes
2010-Q22101yes
2010-Q13312yes
2009-Q44422yes
2009-Q31000yes
2009-Q22220yes
2009-Q14440yes
2008-Q42211yes
2008-Q34303yes
2008-Q2121207852152797yes
2008-Q17778262183061yes
2007-Q49902583684341yes
2007-Q32211yes
2007-Q24413yes
2007-Q12110yes
2006-Q43330yes
2006-Q21110yes
2006-Q13311yes
2005-Q41110yes
2005-Q31101yes
2005-Q24413yes
2005-Q1553417223yes
2004-Q41101yes
2004-Q34440yes
2004-Q25412yes
2004-Q16613753461,8542,8540yes
2003-Q41110yes
2003-Q31101yes
2003-Q24412yes
2003-Q13330yes
2002-Q43310yes
2002-Q32202yes
2002-Q2550630yes
2002-Q176105001yes
2001-Q45507031yes
2001-Q3872219306yes
2001-Q24410yes
2001-Q14431yes
2000-Q41110yes
2000-Q21110yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

106 of the 339 building permits filed since 2000 (31%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Golden Gate Park neighborhood

No project type has 30 or more finished permits here, so the types are not shown apart. Citywide, by type: roof deck, pergola or trellis, deck, stairs, kitchen remodel, bathroom remodel.

Nearby neighborhoods

Inner Sunset, Inner Richmond, Outer Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.