How long do building permits take in San Francisco's Lone Mountain/USF neighborhood?

In the Lone Mountain/USF neighborhood of San Francisco, of the 308 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 264 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 92 days of being issued, down from 133 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's LoneMountain/USF neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/lone-mountain-usf · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026308 issued0334 issued0
Permit issued to final sign-offOctober 2023 through September 2024264 finished92275 finished133

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q46100too recent
2026-Q377592211126410too recent
2026-Q2807201643321120too recent
2026-Q1857902844621580too recent
2025-Q41079803668701740too recent
2025-Q31059704971622020too recent
2025-Q2109104043761322840too recent
2025-Q18278150581423860too recent
2024-Q46455116940983320too recent
2024-Q3959101971873130yes
2024-Q2110104041801044080yes
2024-Q1726501554883430yes
2023-Q48782031591084302yes
2023-Q31141080407811847030yes
2023-Q297910130699539315yes
2023-Q191830606515141421yes
2022-Q4887811446313339615yes
2022-Q31091020637411037427yes
2022-Q211810801968719561926yes
2022-Q111110701078313450021yes
2021-Q4857701136117463314yes
2021-Q31381240959312552630yes
2021-Q291860906914151317yes
2021-Q11018401167114555515yes
2020-Q4118109242129119078416yes
2020-Q315614361339414456250yes
2020-Q2574981083311956522yes
2020-Q113011801436419256455yes
2019-Q414113302486026267467yes
2019-Q31841690128812069079yes
2019-Q21741570638113347278yes
2019-Q11621530297719170972yes
2018-Q415014201447214884770yes
2018-Q316715601018313449771yes
2018-Q216115701028718178469yes
2018-Q11471340597614769060yes
2017-Q413713402336116361866yes
2017-Q3220205051012314887579yes
2017-Q2180170013710512271061yes
2017-Q11361310628011864548yes
2016-Q412912502127912869945yes
2016-Q314313801668313856053yes
2016-Q211811301256818764042yes
2016-Q110395052637842934yes
2015-Q411211001616016265344yes
2015-Q312912101187510143345yes
2015-Q21401390979214240541yes
2015-Q11291250138849070437yes
2014-Q41381330348011036751yes
2014-Q31681600231029134458yes
2014-Q216816106210112248855yes
2014-Q11341290217410341350yes
2013-Q4137133017899332241yes
2013-Q3127122021838434635yes
2013-Q2116114058769036637yes
2013-Q11111060426510230938yes
2012-Q4113111014705425940yes
2012-Q3137131058847949844yes
2012-Q21271250269110533933yes
2012-Q184830514410154937yes
2011-Q49794019506421641yes
2011-Q3123119014687025148yes
2011-Q2117115028808465932yes
2011-Q18279014486478729yes
2010-Q4107105014728632930yes
2010-Q312712605777526649yes
2010-Q21281250209012035133yes
2010-Q19691014499442039yes
2009-Q4999307448227643yes
2009-Q312512401635927657yes
2009-Q2115113026629265347yes
2009-Q1116114076711347739yes
2008-Q411210904495934655yes
2008-Q3139138010796229642yes
2008-Q213112702646825856yes
2008-Q115114504826217754yes
2007-Q4139134090659642558yes
2007-Q3161159026831101,23865yes
2007-Q2146145006110137972yes
2007-Q1120119076510444049yes
2006-Q4116116005311076654yes
2006-Q3182180039111230868yes
2006-Q215515202899648350yes
2006-Q1129127071757824937yes
2005-Q4128128007112449035yes
2005-Q3154151007212939438yes
2005-Q21671660768012234952yes
2005-Q1989400607831718yes
2004-Q4115113005410236032yes
2004-Q3129128022689928741yes
2004-Q2136133010756725124yes
2004-Q111110600606418724yes
2003-Q410710404574118227yes
2003-Q3130130039697021832yes
2003-Q21101090124639024625yes
2003-Q1103101026518820227yes
2002-Q4105104018517928736yes
2002-Q3122119029719922522yes
2002-Q2128119026678724215yes
2002-Q19793057471162546yes
2001-Q410610302554882280yes
2001-Q380740123461053121yes
2001-Q2959303250462464yes
2001-Q110299030671173660yes
2000-Q48583042491713920yes
2000-Q3105103069681024271yes
2000-Q2108105068591576231yes
2000-Q19791080381924860yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

3,664 of the 12,936 building permits filed since 2000 (28%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Lone Mountain/USF neighborhood

Shown apart, with their own page here: bathroom remodel (1,836 filed, 1,363 finished; contractors); kitchen remodel (1,645 filed, 1,201 finished; contractors); stairs (790 filed, 562 finished; contractors); deck (406 filed, 276 finished; contractors); roof deck (100 filed, 63 finished; contractors). Other types: 9,544 permits.

Nearby neighborhoods

Haight Ashbury, Presidio Heights, Inner Richmond; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.