Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Glen Park neighborhood?

In the Glen Park neighborhood of San Francisco, of the 274 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 274 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 78 days of being issued, down from 137 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's Glen ParkneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/glen-park · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026274 issued0376 issued0
Permit issued to final sign-offOctober 2023 through September 2024274 finished78234 finished137

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q424190000too recent
2026-Q36141023840670too recent
2026-Q273670453140690too recent
2026-Q1878206454641650too recent
2025-Q41008402757811940too recent
2025-Q310710307271842440too recent
2025-Q2989404064642290too recent
2025-Q1909002169902410too recent
2024-Q49489037621243450too recent
2024-Q31009704681773620yes
2024-Q2959301870682080yes
2024-Q1817903768672610yes
2023-Q47970099551184130yes
2023-Q388780506210448116yes
2023-Q2888721306714754518yes
2023-Q174700655015054318yes
2022-Q477730905515753413yes
2022-Q3837601305310558918yes
2022-Q28375092609242013yes
2022-Q195880557012437118yes
2021-Q4645411764119339111yes
2021-Q3776802675016062516yes
2021-Q290790966512247410yes
2021-Q1797002116013073111yes
2020-Q4767501235815845915yes
2020-Q39689375589558332yes
2020-Q23428448188631112yes
2020-Q1868102084820650431yes
2019-Q411610803186419661244yes
2019-Q31181150148708080441yes
2019-Q2115110048709962836yes
2019-Q188870575624063329yes
2018-Q41019701044916673846yes
2018-Q31191140905816659852yes
2018-Q212512201087111168849yes
2018-Q112411701557117373346yes
2017-Q41231190616513455553yes
2017-Q316915901009620254759yes
2017-Q21191140956410662049yes
2017-Q192890195311344137yes
2016-Q41009501415312565441yes
2016-Q31471420898211547954yes
2016-Q21151110285812652248yes
2016-Q112211701947213070543yes
2015-Q412512401558014456943yes
2015-Q3135129095769550050yes
2015-Q212312201167912451236yes
2015-Q1102950141708862627yes
2014-Q4101970258678755826yes
2014-Q31351330329415266735yes
2014-Q213613401109011855844yes
2014-Q1111109079739651935yes
2013-Q410610202076617557935yes
2013-Q3131125020808639042yes
2013-Q29492022667637924yes
2013-Q170700135310343417yes
2012-Q48281034507853427yes
2012-Q3114113025739941238yes
2012-Q2113111014706330935yes
2012-Q18179025597025917yes
2011-Q468670565510135610yes
2011-Q3135128032856635239yes
2011-Q27574026524636322yes
2011-Q19089028588649122yes
2010-Q4868206486627530yes
2010-Q3122118030846634031yes
2010-Q210399020695729724yes
2010-Q1949001547624628yes
2009-Q412111902715327238yes
2009-Q3107106010787935722yes
2009-Q212011800826737131yes
2009-Q11029604487234540yes
2008-Q4102101076910434627yes
2008-Q313613507829047940yes
2008-Q213112606798831433yes
2008-Q11271230156413943643yes
2007-Q498930189497143723yes
2007-Q314814603787629448yes
2007-Q214514402777124047yes
2007-Q111911806629336528yes
2006-Q4112109039498042330yes
2006-Q3136135016649028627yes
2006-Q2162160019513841546yes
2006-Q110310106549429422yes
2005-Q41141130455411851123yes
2005-Q31111070586611250915yes
2005-Q294910156408837220yes
2005-Q110810501675817452924yes
2004-Q4898900556451913yes
2004-Q31331310428110251922yes
2004-Q2121119045716426022yes
2004-Q11121080646111833912yes
2003-Q4121117051688128322yes
2003-Q3124123056838635314yes
2003-Q21331270437411638220yes
2003-Q19288024557804387yes
2002-Q4104102059537136617yes
2002-Q31351330136678724919yes
2002-Q2150147082828425411yes
2002-Q1107106069591023673yes
2001-Q4989705467833271yes
2001-Q311210906156853260yes
2001-Q2969003545611881yes
2001-Q18380015045773651yes
2000-Q49897055551144230yes
2000-Q397960232411103280yes
2000-Q21091070104561163381yes
2000-Q188840165331504490yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

2,529 of the 11,302 building permits filed since 2000 (22%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Glen Park neighborhood

Shown apart, with their own page here: bathroom remodel (1,601 filed, 1,164 finished; contractors); kitchen remodel (1,308 filed, 929 finished; contractors); deck (818 filed, 553 finished; contractors); stairs (805 filed, 522 finished; contractors); roof deck (122 filed, 75 finished; contractors). Other types: 7,929 permits.

Nearby neighborhoods

Noe Valley, Bernal Heights, Twin Peaks; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.