Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Bernal Heights neighborhood?

In the Bernal Heights neighborhood of San Francisco, of the 627 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 589 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 94 days of being issued, the same as the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's BernalHeights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/bernal-heights · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026627 issued0728 issued0
Permit issued to final sign-offOctober 2023 through September 2024589 finished94528 finished94

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q46200too recent
2026-Q31511070152222550too recent
2026-Q218115604070281000too recent
2026-Q1192172046107331230too recent
2025-Q4212192076116431680too recent
2025-Q3192181044133592290too recent
2025-Q2183173072128642940too recent
2025-Q1216205055153812660too recent
2024-Q4177169025127893520too recent
2024-Q31991880571511093870yes
2024-Q2195180034153953180yes
2024-Q1190176031144863840yes
2023-Q42081940108141874334yes
2023-Q32242040411485241156yes
2023-Q221619816315512648143yes
2023-Q116715303711511351136yes
2022-Q418315813791109037041yes
2022-Q318117501291259258342yes
2022-Q218117007912212263838yes
2022-Q1216188014014911041841yes
2021-Q4179166014212714854537yes
2021-Q321119706615815155934yes
2021-Q2205183011014212954933yes
2021-Q1195177027212714769147yes
2020-Q42061741220313613263536yes
2020-Q3229203420514015471769yes
2020-Q2101916765210843541yes
2020-Q122520509612013968285yes
2019-Q42932730286144210800120yes
2019-Q33273060118154163702143yes
2019-Q2317301084176132613124yes
2019-Q1271257057152115636105yes
2018-Q42752580137149175807102yes
2018-Q3338321069192168682122yes
2018-Q2281266050150149495107yes
2018-Q13012760114146142553129yes
2017-Q4268252013015017166992yes
2017-Q3320299052189160530104yes
2017-Q2297283056175111544100yes
2017-Q123422707912014849895yes
2016-Q4289272018716717659697yes
2016-Q3311299059174158607119yes
2016-Q2304289053173148510104yes
2016-Q128026601591711421,08791yes
2015-Q425624609715112948287yes
2015-Q327426203115191368107yes
2015-Q2298283023517511950199yes
2015-Q125624804916710537278yes
2014-Q4253238020115713673179yes
2014-Q3263244010314714560093yes
2014-Q224223508614412248382yes
2014-Q125424406316513053774yes
2013-Q423422606214110350581yes
2013-Q32332260161319433589yes
2013-Q22462370431589056270yes
2013-Q12132050161376835655yes
2012-Q416115301610410231445yes
2012-Q32342220151389838679yes
2012-Q22252160761336940280yes
2012-Q118818106312111544855yes
2011-Q41841770291249241149yes
2011-Q32031960201227323562yes
2011-Q2228217071395235771yes
2011-Q12001860141319136347yes
2010-Q422821602615711234652yes
2010-Q32372280301529341464yes
2010-Q22142070451386542261yes
2010-Q1181175091149637041yes
2009-Q42142060161446837549yes
2009-Q32342300181407035873yes
2009-Q2226221051495637253yes
2009-Q119519001510910739470yes
2008-Q4266259071537734779yes
2008-Q3261252051586635570yes
2008-Q22802670121497736483yes
2008-Q1238227071219133577yes
2007-Q427826801612711538480yes
2007-Q3248238051128233593yes
2007-Q2231226011079127677yes
2007-Q12542480151209826971yes
2006-Q4251248001308433772yes
2006-Q330028902614010431761yes
2006-Q226926404613312343474yes
2006-Q124524204312210835763yes
2005-Q422722204110212035253yes
2005-Q32752700011510936575yes
2005-Q2235225010111010436751yes
2005-Q12292210221109040942yes
2004-Q4235227001129427955yes
2004-Q3305297001698430158yes
2004-Q22232200541359734650yes
2004-Q12402390291049641956yes
2003-Q428828408311090365110yes
2003-Q32552520013810626639yes
2003-Q2246244011277434055yes
2003-Q123623203210510048046yes
2002-Q4300295041117106387100yes
2002-Q333132404717211934746yes
2002-Q22692520811439844917yes
2002-Q12112050501101262907yes
2001-Q419819107385673056yes
2001-Q3198191021921084361yes
2001-Q223422601497973224yes
2001-Q12202110118112804125yes
2000-Q4208201053871013564yes
2000-Q3211206038951493660yes
2000-Q22192090951071834665yes
2000-Q12041860558411352912yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

6,179 of the 25,219 building permits filed since 2000 (25%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Bernal Heights neighborhood

Shown apart, with their own page here: bathroom remodel (3,696 filed, 2,606 finished; contractors); kitchen remodel (2,991 filed, 2,081 finished; contractors); stairs (2,249 filed, 1,508 finished; contractors); deck (1,270 filed, 821 finished; contractors); roof deck (214 filed, 133 finished; contractors). Other types: 17,957 permits.

Nearby neighborhoods

Glen Park, Noe Valley, Portola; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.