Permit GraphShortlistSan Francisco building permits since 2000

How long do bathroom remodel permits take in San Francisco's Bernal Heights neighborhood?

In the Bernal Heights neighborhood of San Francisco, of the 120 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, the same as a year earlier. Of the 91 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 171 days of being issued, down from 184 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sBernal Heights neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/bernal-heights/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026120 issued2135 issued2
Permit issued to final sign-offOctober 2023 through September 202491 finished17183 finished184

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q3301602220too recent
2026-Q246396548951430too recent
2026-Q139311145121261800too recent
2025-Q43634597161222120too recent
2025-Q34040183251342990too recent
2025-Q229281490181322520too recent
2025-Q145430110301602940too recent
2024-Q42524626221324280too recent
2024-Q33533139252174870yes
2024-Q232307215251724340yes
2024-Q12623029191165090yes
2023-Q43029064221214761yes
2023-Q33026064182105597yes
2023-Q2292516297192386095yes
2023-Q125251133212085101yes
2022-Q43937144725903203yes
2022-Q336340105252985706yes
2022-Q227246375171685976yes
2022-Q146451342381856898yes
2021-Q439384180292465697yes
2021-Q341380227331946234yes
2021-Q248430200352756665yes
2021-Q15752505223926467610yes
2020-Q4514141171331846077yes
2020-Q344411144342346927yes
2020-Q21814666141805460yes
2020-Q133295315241546875yes
2019-Q44944123833140086111yes
2019-Q35351105773225070217yes
2019-Q2575310595433127538yes
2019-Q14845158382088365yes
2018-Q452496275382401,0016yes
2018-Q348461236382089466yes
2018-Q247403105382606780yes
2018-Q142393285292369888yes
2017-Q447447352423268950yes
2017-Q34137165342466093yes
2017-Q266591337461766669yes
2017-Q144422280342374605yes
2016-Q4585619313482485715yes
2016-Q352491418422986756yes
2016-Q254536103423046615yes
2016-Q14339297341694694yes
2015-Q448468262372815506yes
2015-Q340401174341184635yes
2015-Q259563234531763442yes
2015-Q13838064351814063yes
2014-Q451488599373781,1529yes
2014-Q350464170342035159yes
2014-Q243424243302091,1318yes
2014-Q146453117392405716yes
2013-Q44846583382115267yes
2013-Q33129337251904991yes
2013-Q248477321393557215yes
2013-Q137361108321103371yes
2012-Q436361116331375883yes
2012-Q343422120361804686yes
2012-Q235350205281394124yes
2012-Q13434373301534282yes
2011-Q428273312241786851yes
2011-Q32826264221442423yes
2011-Q225230123191195193yes
2011-Q1252217201322862yes
2010-Q443404100372065011yes
2010-Q34542164352125764yes
2010-Q23332294292154762yes
2010-Q12928120242005340yes
2009-Q437352193262225663yes
2009-Q329294101252143652yes
2009-Q236340113281543751yes
2009-Q11919142171464621yes
2008-Q43027016191332792yes
2008-Q33331192252394260yes
2008-Q233321345232664151yes
2008-Q124220172181414400yes
2007-Q443390274231913915yes
2007-Q3383704201523007yes
2007-Q2222003121283082yes
2007-Q13433074191402832yes
2006-Q4323100191273803yes
2006-Q332300138161192361yes
2006-Q227270162151833822yes
2006-Q133330108242143722yes
2005-Q431300476162003325yes
2005-Q329290264171402317yes
2005-Q222190571121986082yes
2005-Q1202000111052100yes
2004-Q4252400161534482yes
2004-Q323230111171112832yes
2004-Q223220385151284541yes
2004-Q11919014291112891yes
2003-Q41918070132103742yes
2003-Q32322023161804722yes
2003-Q222220159102003851yes
2003-Q121180212101744942yes
2002-Q413120091243341yes
2002-Q327270120162704681yes
2002-Q220190174132811,5630yes
2002-Q117161019171402442yes
2001-Q41412022362173490yes
2001-Q31312027681863060yes
2001-Q224220231112303320yes
2001-Q11919035910731720yes
2000-Q4131101361531930yes
2000-Q31313013971834750yes
2000-Q21211011282564970yes
2000-Q110909972457260yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

338 of the 3,696 bathroom remodel permits filed since 2000 (9%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Bernal Heights neighborhood

Shown apart, with their own page here: bathroom remodel (3,696 filed, 2,606 finished; contractors); kitchen remodel (2,991 filed, 2,081 finished; contractors); stairs (2,249 filed, 1,508 finished; contractors); deck (1,270 filed, 821 finished; contractors); roof deck (214 filed, 133 finished; contractors). Other types: 17,957 permits. All permits in San Francisco's Bernal Heights neighborhood

Nearby neighborhoods

Glen Park, Noe Valley, Portola; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.