How long do building permits take in San Francisco's Excelsior neighborhood?

In the Excelsior neighborhood of San Francisco, of the 416 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 502 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 68 days of being issued, down from 98 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's ExcelsiorneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02550751001251502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/excelsior · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026416 issued0616 issued0
Permit issued to final sign-offOctober 2023 through September 2024502 finished68386 finished98

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q46000too recent
2026-Q3106730211321770too recent
2026-Q213711002465281060too recent
2026-Q111510205654501210too recent
2025-Q415213108198662170too recent
2025-Q3178171084129542720too recent
2025-Q2152141025104562760too recent
2025-Q1143136038107462530too recent
2024-Q4176168034130933490too recent
2024-Q3184178030140573330yes
2024-Q2168161017129562790yes
2024-Q1132126010110693550yes
2023-Q41671570221231193506yes
2023-Q31661550421118632138yes
2023-Q21641510451118533441yes
2023-Q1112990497410834527yes
2022-Q413212102249013641732yes
2022-Q31061000736914042729yes
2022-Q21161020105758438822yes
2022-Q11391270719713950133yes
2021-Q412111301628714849825yes
2021-Q3124114043839848230yes
2021-Q21079402666511942628yes
2021-Q110910301317510951229yes
2020-Q414814001781109246129yes
2020-Q31221013887612648532yes
2020-Q26053470307736623yes
2020-Q112612302738111356936yes
2019-Q4194182011411514568364yes
2019-Q31801710359710758869yes
2019-Q2174157011410912655248yes
2019-Q115214002010210448239yes
2018-Q419818202610814639772yes
2018-Q3187169017810713374056yes
2018-Q22071960241119746172yes
2018-Q1140132032899937945yes
2017-Q41621550219613256557yes
2017-Q31761690611198452144yes
2017-Q216915904810811847148yes
2017-Q1115110029808436932yes
2016-Q41431350558011043449yes
2016-Q31681600251016937151yes
2016-Q21221180457011333040yes
2016-Q11401340182908256843yes
2015-Q41551510207412738262yes
2015-Q31761710381109252058yes
2015-Q2154141022878260952yes
2015-Q11331290848010675338yes
2014-Q41551500579511542845yes
2014-Q3159151030979737545yes
2014-Q2131125011817731441yes
2014-Q11321280238011445242yes
2013-Q41281250113709931945yes
2013-Q31381360237711437954yes
2013-Q2140137013858834342yes
2013-Q1131125037846432239yes
2012-Q411911209746031435yes
2012-Q31531490131038332938yes
2012-Q21601530131116236535yes
2012-Q1113106014755022429yes
2011-Q411811404837332622yes
2011-Q311510606816624826yes
2011-Q2138133011847635642yes
2011-Q111911208827522029yes
2010-Q4137132011877738339yes
2010-Q31591560301126435039yes
2010-Q217116806917528471yes
2010-Q118517801734218799yes
2009-Q4223216041405432673yes
2009-Q317116706948029065yes
2009-Q216615908935732451yes
2009-Q114013706726136454yes
2008-Q414013605779333954yes
2008-Q3176173051027234763yes
2008-Q215915602856824461yes
2008-Q112812202648025347yes
2007-Q4200194041049844378yes
2007-Q318217902898426870yes
2007-Q217517001976423250yes
2007-Q1167164001046225826yes
2006-Q415215000816628747yes
2006-Q318217600956822641yes
2006-Q22162140010810431778yes
2006-Q115715300857030230yes
2005-Q418217900948822448yes
2005-Q3202195001069429248yes
2005-Q218118000955633557yes
2005-Q116916600909527654yes
2004-Q417216800848431347yes
2004-Q32052020551106430556yes
2004-Q21851820541158235536yes
2004-Q12072030491148334969yes
2003-Q4187182026996437552yes
2003-Q32302250312510931676yes
2003-Q2187185009310731259yes
2003-Q118417301321118439638yes
2002-Q41621590268810634649yes
2002-Q322421802431348231955yes
2002-Q2205202011299833815yes
2002-Q11831780571091043421yes
2001-Q4206199022106883382yes
2001-Q318718101116903760yes
2001-Q21661630138921224493yes
2001-Q115415106280924781yes
2000-Q417416802098893521yes
2000-Q317817403479853220yes
2000-Q2191187036991114433yes
2000-Q1157152038551204752yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

4,016 of the 16,926 building permits filed since 2000 (24%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Excelsior neighborhood

Shown apart, with their own page here: bathroom remodel (2,869 filed, 2,106 finished; contractors); kitchen remodel (1,940 filed, 1,370 finished; contractors); stairs (1,120 filed, 785 finished; contractors); deck (780 filed, 535 finished; contractors). Other types: 12,100 permits.

Nearby neighborhoods

Outer Mission, McLaren Park, Glen Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.