How long do building permits take in San Francisco's Marina neighborhood?

In the Marina neighborhood of San Francisco, of the 704 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 674 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 116 days of being issued, down from 140 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's MarinaneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/marina · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026704 issued0801 issued0
Permit issued to final sign-offOctober 2023 through September 2024674 finished116715 finished140

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41290300too recent
2026-Q31761360212712610too recent
2026-Q220618702883431210too recent
2026-Q118917618498561690too recent
2025-Q4222205075146602060too recent
2025-Q3215200077139662190too recent
2025-Q22382280541611062760too recent
2025-Q1205193039136833400too recent
2024-Q41861800851371063620too recent
2024-Q3232216040173992960yes
2024-Q22422270591871153740yes
2024-Q12041950701571344270yes
2023-Q421120201841571184752yes
2023-Q322920807617511054933yes
2023-Q2251224114918313156534yes
2023-Q122219607017115956027yes
2022-Q4248228114818614452236yes
2022-Q3207189010315011855937yes
2022-Q220918508013314755156yes
2022-Q1193184013315116448025yes
2021-Q4197183011014315162134yes
2021-Q322420706515618146651yes
2021-Q2207198315715221169639yes
2021-Q1238227327917417060848yes
2020-Q42652453216318817876859yes
2020-Q32872604150157156791106yes
2020-Q21311165535611054264yes
2020-Q13202870188154178789131yes
2019-Q4364346048166176750177yes
2019-Q3458438060187140884240yes
2019-Q2410389033183127620209yes
2019-Q1370349033151148699199yes
2018-Q4405381056183146885195yes
2018-Q3470444089231149658210yes
2018-Q2446433055214136783213yes
2018-Q1407374062187118575183yes
2017-Q44133950111194166765198yes
2017-Q34814580204242174672206yes
2017-Q2416396092214136828163yes
2017-Q1348337077175134611153yes
2016-Q43793550224188152706150yes
2016-Q34103980249219176652167yes
2016-Q23903750127213133509157yes
2016-Q1346324074193150705123yes
2015-Q42982900175153174732122yes
2015-Q33463300110189175644138yes
2015-Q2345338057204143537126yes
2015-Q1334323072200156818113yes
2014-Q4338324042181120515128yes
2014-Q333732003417790425133yes
2014-Q2359346066217122542123yes
2014-Q1312306046199106504100yes
2013-Q4331312072176102421132yes
2013-Q3344328040175119534143yes
2013-Q2366355040191103464139yes
2013-Q129528601318311343791yes
2012-Q4273261024153111439100yes
2012-Q3363348033199135583133yes
2012-Q22592490401359850398yes
2012-Q12552410361409848593yes
2011-Q4272255019146104521102yes
2011-Q335234402320197462108yes
2011-Q225625101914113943697yes
2011-Q12442310171508438770yes
2010-Q42312240912211734292yes
2010-Q325224203413910846892yes
2010-Q22952890301887248878yes
2010-Q12442360121548637570yes
2009-Q43032890201809935999yes
2009-Q329328201316097449104yes
2009-Q23132960261836034993yes
2009-Q12242150261179935965yes
2008-Q43683640314795316187yes
2008-Q33443330614991370137yes
2008-Q23263170813599451129yes
2008-Q12902800512980318111yes
2007-Q433232308142108314143yes
2007-Q34153980418268291164yes
2007-Q23713630015997285136yes
2007-Q133433002815578324123yes
2006-Q42822770513410632495yes
2006-Q33453410015379257133yes
2006-Q230930003514311135389yes
2006-Q126926402513610631864yes
2005-Q42292250389714935661yes
2005-Q33143080015511134581yes
2005-Q2302299001409730986yes
2005-Q12492410281039037369yes
2004-Q4243237021129238071yes
2004-Q3331325057153106384100yes
2004-Q22992920616410630156yes
2004-Q1300296001627231470yes
2003-Q4274270001519027953yes
2003-Q33323270151669429961yes
2003-Q23002920471648436848yes
2003-Q1265260001477024926yes
2002-Q42632540411337521420yes
2002-Q33133030221668628634yes
2002-Q22612490381356630419yes
2002-Q1245234021131922836yes
2001-Q418518005684632271yes
2001-Q3236230071114843091yes
2001-Q22262170381181023242yes
2001-Q1231219056120963603yes
2000-Q42232090921001483921yes
2000-Q32872810381431484420yes
2000-Q23143040431741084251yes
2000-Q12602480481191435466yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

9,094 of the 31,380 building permits filed since 2000 (29%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Marina neighborhood

Shown apart, with their own page here: bathroom remodel (4,620 filed, 3,379 finished; contractors); kitchen remodel (4,226 filed, 3,107 finished; contractors); stairs (1,549 filed, 1,069 finished; contractors); deck (939 filed, 610 finished; contractors); roof deck (573 filed, 329 finished; contractors). Other types: 23,123 permits.

Nearby neighborhoods

Pacific Heights, Russian Hill, Japantown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.