How long do deck permits take in San Francisco's Marina neighborhood?

In the Marina neighborhood of San Francisco, of the 27 deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 5 days, up from 0 days a year earlier. Of the 23 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 100 days of being issued, up from 95 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long deck permits take in San Francisco's MarinaneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/marina/deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202627 issued524 issued0
Permit issued to final sign-offOctober 2023 through September 202423 finished10019 finished95

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 164 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q37771610too recent
2026-Q2131142040too recent
2026-Q176106130too recent
2025-Q44320too recent
2025-Q34430too recent
2025-Q2991536982680too recent
2025-Q1882415631130too recent
2024-Q44330too recent
2024-Q388109171004960yes
2024-Q2977411762646810yes
2024-Q15440yes
2023-Q488986206685030yes
2023-Q34440yes
2023-Q29701776943762yes
2023-Q13220yes
2022-Q4109143471347542yes
2022-Q33221yes
2022-Q2951556525yes
2022-Q12210yes
2021-Q465016023yes
2021-Q36322yes
2021-Q2983043023yes
2021-Q1556351,00631yes
2020-Q498624761698201yes
2020-Q311101416761606612yes
2020-Q21110yes
2020-Q176836643yes
2019-Q4554940yes
2019-Q399058861064473yes
2019-Q2761277151857761yes
2019-Q1961340542yes
2018-Q4161176419101688613yes
2018-Q3101081028605692yes
2018-Q2109515691539760yes
2018-Q16412yes
2017-Q4131201210696113yes
2017-Q316111513863508405yes
2017-Q2101012733761741,0191yes
2017-Q16431yes
2016-Q466157053621,3311yes
2016-Q3554241652096960yes
2016-Q210903148724792yes
2016-Q11081635956378872yes
2015-Q44220yes
2015-Q316142400121416922yes
2015-Q210101024892948241yes
2015-Q110103255974107552yes
2014-Q41510226271187192yes
2014-Q39801341yes
2014-Q2971717742yes
2014-Q1761823042yes
2013-Q4873887974730yes
2013-Q3171614490131977002yes
2013-Q2111061,3097961,0572yes
2013-Q1109135681742421yes
2012-Q41085317881442780yes
2012-Q31111511181695651yes
2012-Q24430yes
2012-Q177132462215501yes
2011-Q415120133121124880yes
2011-Q311101014992249681yes
2011-Q211102226481975402yes
2011-Q15440yes
2010-Q4768833163124870yes
2010-Q33330yes
2010-Q288503055626411yes
2010-Q166293286952670yes
2009-Q477013532yes
2009-Q34220yes
2009-Q2108733971913182yes
2009-Q1101001177531910yes
2008-Q4119014881964211yes
2008-Q31614433873233741yes
2008-Q213122717171073333yes
2008-Q1851440yes
2007-Q41311417691192581yes
2007-Q31312417091423080yes
2007-Q2101001045411641yes
2007-Q199015351362841yes
2006-Q410904156901761yes
2006-Q31716016014852400yes
2006-Q213110254101793310yes
2006-Q1667420440yes
2005-Q45528446220yes
2005-Q3109031181165340yes
2005-Q299021871142260yes
2005-Q165031510yes
2004-Q4111104429591650yes
2004-Q37610266240yes
2004-Q2111100101321930yes
2004-Q198030681053130yes
2003-Q477013031yes
2003-Q3111103417638020yes
2003-Q299643156984050yes
2003-Q166021130yes
2002-Q499025930yes
2002-Q314120071688400yes
2002-Q212126732110983850yes
2002-Q115140408132613250yes
2001-Q43320yes
2001-Q37602965571020yes
2001-Q2111002598982650yes
2001-Q1105014530yes
2000-Q4775618440yes
2000-Q37701997893990yes
2000-Q2161448399121054240yes
2000-Q155813940yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

90 of the 939 deck permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Marina neighborhood

Shown apart, with their own page here: bathroom remodel (4,620 filed, 3,379 finished; contractors); kitchen remodel (4,226 filed, 3,107 finished; contractors); stairs (1,549 filed, 1,069 finished; contractors); deck (939 filed, 610 finished; contractors); roof deck (573 filed, 329 finished; contractors). Other types: 23,123 permits. All permits in San Francisco's Marina neighborhood

Nearby neighborhoods

Pacific Heights, Russian Hill, Japantown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.