How long do kitchen remodel permits take in San Francisco's Marina neighborhood?

In the Marina neighborhood of San Francisco, of the 143 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, up from 0 days a year earlier. Of the 113 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 203 days of being issued, up from 156 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco'sMarina neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/marina/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026143 issued1141 issued0
Permit issued to final sign-offOctober 2023 through September 2024113 finished203126 finished156

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42100too recent
2026-Q3413203510too recent
2026-Q2383601711821240too recent
2026-Q14240274211112070too recent
2025-Q4363527722902380too recent
2025-Q33636030251242220too recent
2025-Q24545046321773140too recent
2025-Q13029149211303650too recent
2024-Q431310101211493640too recent
2024-Q34037070282044220yes
2024-Q24038041361543720yes
2024-Q134330107262104350yes
2023-Q430281113233375950yes
2023-Q33333034302066532yes
2023-Q232310271251687073yes
2023-Q13331024301698500yes
2022-Q44948165411434906yes
2022-Q34939072351693893yes
2022-Q23330143242254236yes
2022-Q14949024461603543yes
2021-Q443390129291966039yes
2021-Q35656044501984125yes
2021-Q25656048491967037yes
2021-Q161610140462545529yes
2020-Q48683362006419049518yes
2020-Q3696531164519054315yes
2020-Q23027315211172934yes
2020-Q153480187421925208yes
2019-Q44040230312104709yes
2019-Q35554096421609229yes
2019-Q25047031391536086yes
2019-Q13331172251274765yes
2018-Q44946038391627207yes
2018-Q34945068371695785yes
2018-Q255531534116462110yes
2018-Q14542039351313367yes
2017-Q443421332341768916yes
2017-Q347460168371377479yes
2017-Q260592210461708146yes
2017-Q14442033371766283yes
2016-Q44441051341504565yes
2016-Q34847091431603774yes
2016-Q256541894214953110yes
2016-Q14645041402205353yes
2015-Q436340198261816425yes
2015-Q34039094352026324yes
2015-Q24342066361664715yes
2015-Q15554041432106379yes
2014-Q43634031281466516yes
2014-Q34242086299943010yes
2014-Q26059068541598564yes
2014-Q14242073351322965yes
2013-Q44542033341443905yes
2013-Q330300156232025807yes
2013-Q25150064431523813yes
2013-Q1454505361123724yes
2012-Q42725057232056142yes
2012-Q33736018311545783yes
2012-Q244430132911745111yes
2012-Q1242405191264224yes
2011-Q44542083381354963yes
2011-Q359580112401474224yes
2011-Q23838014301714642yes
2011-Q13835016301664951yes
2010-Q4292808201502326yes
2010-Q33434068291464773yes
2010-Q2333204311333490yes
2010-Q1514805381132783yes
2009-Q43834020291214501yes
2009-Q3333109211433125yes
2009-Q2343101261163642yes
2009-Q12827095201583971yes
2008-Q42727014161223001yes
2008-Q3454407311603843yes
2008-Q2515106331533641yes
2008-Q1353308251343384yes
2007-Q44242011321273392yes
2007-Q33937011241123191yes
2007-Q2434200281593351yes
2007-Q14544053301073883yes
2006-Q42727039241183462yes
2006-Q3292900191863164yes
2006-Q252510146362233433yes
2006-Q1252500191313130yes
2005-Q4252500152314142yes
2005-Q3353500251894742yes
2005-Q2282800162074341yes
2005-Q1333100201404720yes
2004-Q42222077171795131yes
2004-Q3292907261824701yes
2004-Q2303000251563731yes
2004-Q1232300171443891yes
2003-Q422220015932800yes
2003-Q3292900191704681yes
2003-Q2333200231513631yes
2003-Q132320026932840yes
2002-Q42322009926230yes
2002-Q32928010201263412yes
2002-Q2373700241273422yes
2002-Q13232018241092961yes
2001-Q4282800181272370yes
2001-Q3252503817832020yes
2001-Q220200145101805030yes
2001-Q12825055161203620yes
2000-Q42727095171483360yes
2000-Q34140011232175610yes
2000-Q245440128301414260yes
2000-Q13231036161313420yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

361 of the 4,226 kitchen remodel permits filed since 2000 (9%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Marina neighborhood

Shown apart, with their own page here: bathroom remodel (4,620 filed, 3,379 finished; contractors); kitchen remodel (4,226 filed, 3,107 finished; contractors); stairs (1,549 filed, 1,069 finished; contractors); deck (939 filed, 610 finished; contractors); roof deck (573 filed, 329 finished; contractors). Other types: 23,123 permits. All permits in San Francisco's Marina neighborhood

Nearby neighborhoods

Pacific Heights, Russian Hill, Japantown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.