How long do building permits take in San Francisco's Japantown neighborhood?

In the Japantown neighborhood of San Francisco, of the 95 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 8 days, the same as a year earlier. Of the 63 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 91 days of being issued, down from 100 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's JapantownneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/japantown · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202695 issued893 issued8
Permit issued to final sign-offOctober 2023 through September 202463 finished9159 finished100

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q32815928626640too recent
2026-Q2312862721711040too recent
2026-Q126241213615651240too recent
2025-Q4292858719751400too recent
2025-Q336341113425762160too recent
2025-Q2272323118841150too recent
2025-Q121201817712721890too recent
2024-Q41716824911692180too recent
2024-Q31513830111004960yes
2024-Q2282620244201203660yes
2024-Q1232004317635150yes
2023-Q4252224115703942yes
2023-Q32719612016815199yes
2023-Q2181610234112326072yes
2023-Q1191805916985142yes
2022-Q4211918299161013923yes
2022-Q3191510118121563144yes
2022-Q238292135198926911yes
2022-Q11916010215743502yes
2021-Q41211135710911,1732yes
2021-Q31816718013703384yes
2021-Q28885062664002yes
2021-Q199602377717412yes
2020-Q413135211410841683yes
2020-Q314133315392005674yes
2020-Q2875615943yes
2020-Q116150297867118yes
2019-Q423206135151794745yes
2019-Q3312901081710593112yes
2019-Q22323083137837610yes
2019-Q12020042151614245yes
2018-Q42417012295114310yes
2018-Q32926059136527014yes
2018-Q242380163247637215yes
2018-Q13634028206420614yes
2017-Q43127036159127712yes
2017-Q3403605462115740616yes
2017-Q230281124181223519yes
2017-Q12626042145819612yes
2016-Q439370642413639714yes
2016-Q33231113205823211yes
2016-Q228250427161795588yes
2016-Q1474671283310139213yes
2015-Q4444413223261461,03718yes
2015-Q3242301471021339113yes
2015-Q236330121813352017yes
2015-Q127250306158436210yes
2014-Q430290591412945714yes
2014-Q335320330202551,1038yes
2014-Q232310491710232412yes
2014-Q1181703010268816yes
2013-Q42220095119245910yes
2013-Q31717021101592886yes
2013-Q221210511576448yes
2013-Q11919037131042636yes
2012-Q4262407105446313yes
2012-Q33232417221993089yes
2012-Q22827038139849213yes
2012-Q1212001291903189yes
2011-Q42524411017844807yes
2011-Q324230315141084135yes
2011-Q22221028141663105yes
2011-Q1181804612343365yes
2010-Q41513096582116yes
2010-Q3222217121711738yes
2010-Q23230221161541848yes
2010-Q1201909381964068yes
2009-Q42424033917970313yes
2009-Q32828010171453208yes
2009-Q245350112311118712yes
2009-Q142390632421037515yes
2008-Q445430433130071512yes
2008-Q33535019221163019yes
2008-Q231310241617626215yes
2008-Q129280331322335811yes
2007-Q43331021724940720yes
2007-Q349470231413751622yes
2007-Q2393708157149915yes
2007-Q1302902157639211yes
2006-Q42424098171222506yes
2006-Q33129042147821311yes
2006-Q2201905481512556yes
2006-Q1272601581120956811yes
2005-Q42323017121534046yes
2005-Q32525035111122339yes
2005-Q234320831115629212yes
2005-Q14039002110931414yes
2004-Q42121017181985619yes
2004-Q3151409561682687yes
2004-Q23232041812841419yes
2004-Q124240158111144288yes
2003-Q4212007661805967yes
2003-Q31919051681704585yes
2003-Q21515062101623173yes
2003-Q11312611648yes
2002-Q41313008741762yes
2002-Q31190226yes
2002-Q2212100101271764yes
2002-Q11312027972381,1410yes
2001-Q41818009831560yes
2001-Q3181709710441682yes
2001-Q21616011062465020yes
2001-Q1111101271965880yes
2000-Q415150686181240yes
2000-Q31514009584760yes
2000-Q2131213887674970yes
2000-Q131300275165087241yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

786 of the 2,687 building permits filed since 2000 (29%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Japantown neighborhood

Shown apart, with their own page here: kitchen remodel (288 filed, 205 finished; contractors); bathroom remodel (207 filed, 147 finished; contractors); stairs (79 filed, 44 finished; contractors). Other types: 2,244 permits.

Nearby neighborhoods

Western Addition, Pacific Heights, Hayes Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.