Permit GraphShortlistSan Francisco building permits since 2000

How long do building permits take in San Francisco's Hayes Valley neighborhood?

In the Hayes Valley neighborhood of San Francisco, of the 345 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 1 day a year earlier. Of the 307 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 90 days of being issued, down from 124 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's Hayes ValleyneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/hayes-valley · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026345 issued0408 issued1
Permit issued to final sign-offOctober 2023 through September 2024307 finished90314 finished124

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q46310too recent
2026-Q396690222713670too recent
2026-Q2918402142501240too recent
2026-Q1969006657601450too recent
2025-Q411010205463711870too recent
2025-Q312611006983973060too recent
2025-Q21079906473843300too recent
2025-Q110696056761103080too recent
2024-Q4109103128891252520too recent
2024-Q311911008491843740yes
2024-Q210293112270782280yes
2024-Q19890057711463590yes
2023-Q41129807075953680yes
2023-Q3142131111110312139429yes
2023-Q2119102182769243328yes
2023-Q185780496213842317yes
2022-Q411110022457314764027yes
2022-Q31029431627312551320yes
2022-Q210910103836711351133yes
2022-Q1108980447914157521yes
2021-Q4102880756415059825yes
2021-Q31201100459217171019yes
2021-Q213112411828717345234yes
2021-Q1133123231508017254845yes
2020-Q4155143261217524772165yes
2020-Q31701564879114085368yes
2020-Q268596472610538038yes
2020-Q1209197023387160419110yes
2019-Q42842720114105127606158yes
2019-Q32922730124119139452146yes
2019-Q2256244047102136732138yes
2019-Q1251234056116118584121yes
2018-Q4243231099116160720110yes
2018-Q3227220012698155575115yes
2018-Q2244228075128100426102yes
2018-Q1263250056122113456125yes
2017-Q4234223081116135598107yes
2017-Q32812730364158134715102yes
2017-Q2287280061168127460106yes
2017-Q1211203028011614650583yes
2016-Q42412240205118166582107yes
2016-Q32742591320117179734128yes
2016-Q2256242014713520493599yes
2016-Q1215203014812113265871yes
2015-Q423021407511514062496yes
2015-Q3227214090112159782101yes
2015-Q2231220016513713955777yes
2015-Q123922804914011645984yes
2014-Q421820807310212038997yes
2014-Q324122904813310647387yes
2014-Q22072020611049149089yes
2014-Q120819407810611356085yes
2013-Q419619105010310140079yes
2013-Q321720305410713955092yes
2013-Q2199191016211813269566yes
2013-Q1173165020978062162yes
2012-Q41381320498514755946yes
2012-Q317616301609015667162yes
2012-Q2170159037857041271yes
2012-Q1146137032809647650yes
2011-Q41141070736310166240yes
2011-Q3160159037869065063yes
2011-Q2144139087710643054yes
2011-Q114413706738946554yes
2010-Q41181120456410549647yes
2010-Q3154148027809730260yes
2010-Q2158155027938036656yes
2010-Q1140137097711037652yes
2009-Q4138131019708443658yes
2009-Q3139136018835746044yes
2009-Q21661590181008035658yes
2009-Q1168166061006035648yes
2008-Q418418109979132167yes
2008-Q32342280510491298100yes
2008-Q2207204023928444390yes
2008-Q121921209977730798yes
2007-Q4225221081089036478yes
2007-Q321920408928030777yes
2007-Q222322001711211030680yes
2007-Q123022500886732394yes
2006-Q4235230008186420116yes
2006-Q3213207009611430082yes
2006-Q2195192027898629861yes
2006-Q118017800818337859yes
2005-Q4149146004813433574yes
2005-Q3173169014729224750yes
2005-Q21481440397210842449yes
2005-Q1138133015648523341yes
2004-Q4136136014658823543yes
2004-Q315615200596028072yes
2004-Q2195186036856029862yes
2004-Q11351320225110023048yes
2003-Q4138135079627037146yes
2003-Q3116111026618923239yes
2003-Q21321300896710759946yes
2003-Q1138132042717337845yes
2002-Q41081070634512038238yes
2002-Q31571480157410844952yes
2002-Q21611550508612034322yes
2002-Q1130126010460782425yes
2001-Q41281200100631073676yes
2001-Q3123117024451117312yes
2001-Q2124122025621483101yes
2001-Q1120116036621153682yes
2000-Q49997078501484501yes
2000-Q3149145046831275080yes
2000-Q2152140045671514661yes
2000-Q1141133054582446973yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

6,025 of the 18,070 building permits filed since 2000 (33%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Hayes Valley neighborhood

Shown apart, with their own page here: bathroom remodel (2,515 filed, 1,731 finished; contractors); kitchen remodel (2,377 filed, 1,703 finished; contractors); stairs (1,075 filed, 733 finished; contractors); deck (395 filed, 257 finished; contractors); roof deck (89 filed, 49 finished; contractors). Other types: 13,591 permits.

Nearby neighborhoods

Western Addition, Japantown, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.