How long do kitchen remodel permits take in San Francisco's Hayes Valley neighborhood?

In the Hayes Valley neighborhood of San Francisco, of the 53 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 1 day a year earlier. Of the 40 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 178 days of being issued, down from 264 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco's HayesValley neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/hayes-valley/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202653 issued066 issued1
Permit issued to final sign-offOctober 2023 through September 202440 finished17844 finished264

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q3191532310too recent
2026-Q2108045851120too recent
2026-Q1161404510791240too recent
2025-Q41716014111052530too recent
2025-Q31313060101683110too recent
2025-Q21413152101662900too recent
2025-Q12625572221413990too recent
2024-Q41615010121001840too recent
2024-Q31613045121924110yes
2024-Q21717091131242760yes
2024-Q112110892084890yes
2023-Q487011561723240yes
2023-Q3111101891903102yes
2023-Q2151535091895932yes
2023-Q11715018142144071yes
2022-Q41818799123696346yes
2022-Q32221276182046123yes
2022-Q22020032151256345yes
2022-Q12121127161846055yes
2021-Q42019027151303053yes
2021-Q34139153351896874yes
2021-Q248450643115744011yes
2021-Q1424101532922956012yes
2020-Q4303001151627646213yes
2020-Q33633276241783647yes
2020-Q2121053510914780yes
2020-Q13128054211764417yes
2019-Q45651143922414235320yes
2019-Q34241040321473156yes
2019-Q2242403020882262yes
2019-Q13532049281183314yes
2018-Q43129775271625842yes
2018-Q33030148241664126yes
2018-Q22928494261483743yes
2018-Q1282802319963837yes
2017-Q421204247171053921yes
2017-Q33939153291333767yes
2017-Q24343046361363446yes
2017-Q1161606912911674yes
2016-Q435321563281583994yes
2016-Q33837472301425595yes
2016-Q22726452251569201yes
2016-Q12826042231104402yes
2015-Q42926650201122284yes
2015-Q334342142281445876yes
2015-Q24544029351543527yes
2015-Q14645137421503973yes
2014-Q43533239241232305yes
2014-Q33938041301543896yes
2014-Q2212104417814643yes
2014-Q13128078191045789yes
2013-Q42727057231014132yes
2013-Q33635019281604396yes
2013-Q22928015241744283yes
2013-Q1282801324813743yes
2012-Q42726044211585614yes
2012-Q32018018181434140yes
2012-Q2222102191394142yes
2012-Q124230816853883yes
2011-Q410100181303822yes
2011-Q33131011241245484yes
2011-Q2101002781815330yes
2011-Q1141402131052761yes
2010-Q4109089701131yes
2010-Q3101018091673911yes
2010-Q21717013151063500yes
2010-Q19901281054430yes
2009-Q41411738101403492yes
2009-Q310100184103224230yes
2009-Q22020012201126780yes
2009-Q116150112852510yes
2008-Q4181802614903080yes
2008-Q3303003161281966yes
2008-Q22626016171544123yes
2008-Q1323003231283633yes
2007-Q4333301201302834yes
2007-Q3282802151283204yes
2007-Q231310147221364762yes
2007-Q1292800181412834yes
2006-Q4242300151975233yes
2006-Q3252500161481,0291yes
2006-Q2252500121252474yes
2006-Q1202002111503014yes
2005-Q4151500111683962yes
2005-Q3161500101422551yes
2005-Q2222200141342522yes
2005-Q113130091252201yes
2004-Q412120091412701yes
2004-Q311110051712614yes
2004-Q2302900151205195yes
2004-Q1171700111272804yes
2003-Q466010822yes
2003-Q3860051482390yes
2003-Q2151500101484334yes
2003-Q112110081062973yes
2002-Q4980251833161yes
2002-Q313120051594402yes
2002-Q21616018111473181yes
2002-Q17701542yes
2001-Q411110040yes
2001-Q3990040yes
2001-Q210100062226260yes
2001-Q112120052843410yes
2000-Q45501830yes
2000-Q3880061221900yes
2000-Q211110073074820yes
2000-Q113120061124041yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

312 of the 2,377 kitchen remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Hayes Valley neighborhood

Shown apart, with their own page here: bathroom remodel (2,515 filed, 1,731 finished; contractors); kitchen remodel (2,377 filed, 1,703 finished; contractors); stairs (1,075 filed, 733 finished; contractors); deck (395 filed, 257 finished; contractors); roof deck (89 filed, 49 finished; contractors). Other types: 13,591 permits. All permits in San Francisco's Hayes Valley neighborhood

Nearby neighborhoods

Western Addition, Japantown, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.