How long do stairs permits take in San Francisco's Marina neighborhood?

In the Marina neighborhood of San Francisco, of the 41 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 4 days, down from 10 days a year earlier. Of the 25 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 235 days of being issued, up from 147 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's MarinaneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/marina/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202641 issued441 issued10
Permit issued to final sign-offOctober 2023 through September 202425 finished23544 finished147

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q3131022140too recent
2026-Q222185597371540too recent
2026-Q19828540too recent
2025-Q4752010120too recent
2025-Q311112721740too recent
2025-Q21713110251021950too recent
2025-Q1982447981560too recent
2024-Q4109298382805180too recent
2024-Q3111142581084770yes
2024-Q211111714072354690yes
2024-Q16610818230yes
2023-Q410913622972936980yes
2023-Q31010045101245710yes
2023-Q2141418321122836761yes
2023-Q1151412167101786582yes
2022-Q418177567121045162yes
2022-Q3863645544yes
2022-Q2886034642yes
2022-Q1765622853416170yes
2021-Q46510620941yes
2021-Q3131110060691777084yes
2021-Q212123245582294932yes
2021-Q1131320858293959204yes
2020-Q4882613475041,0700yes
2020-Q312113966881747430yes
2020-Q22220yes
2020-Q1109636991185590yes
2019-Q4131310145114309081yes
2019-Q3141486752103309002yes
2019-Q218131295112611,0215yes
2019-Q1872015363808731yes
2018-Q4201822343132948923yes
2018-Q31212669101736652yes
2018-Q2109981881545791yes
2018-Q111802332yes
2017-Q41715773112261,0244yes
2017-Q3161658214104861,3684yes
2017-Q2232212403162701,1744yes
2017-Q115111073481328011yes
2016-Q4171471729103361,5063yes
2016-Q319187222142336513yes
2016-Q223222427201076273yes
2016-Q120171112616984271yes
2015-Q412113368672568442yes
2015-Q3181821300164237042yes
2015-Q214143653893835754yes
2015-Q1151512560142808641yes
2014-Q419168236131754651yes
2014-Q321186348161487750yes
2014-Q2141322580115851,1841yes
2014-Q1171726550162157781yes
2013-Q4221916309162727661yes
2013-Q3191716271162316530yes
2013-Q217156598121586802yes
2013-Q112125014481567393yes
2012-Q4202028255182476770yes
2012-Q33027580152107217yes
2012-Q2121112582405461yes
2012-Q118181168161103921yes
2011-Q4231910117172216853yes
2011-Q31614478122144541yes
2011-Q21716218121904483yes
2011-Q1131249157111456031yes
2010-Q498426371542760yes
2010-Q319182176172494980yes
2010-Q212120149491002yes
2010-Q1121210411101687172yes
2009-Q413134315111025182yes
2009-Q31717090161023980yes
2009-Q219180339152456441yes
2009-Q11414496131923520yes
2008-Q41614431491636683yes
2008-Q319162242113044401yes
2008-Q227256198161033411yes
2008-Q11413115812683571yes
2007-Q421201217141742951yes
2007-Q32523014517602582yes
2007-Q218170120101923591yes
2007-Q11312035042yes
2006-Q418170146141554620yes
2006-Q3201902114561743yes
2006-Q218160200141242980yes
2006-Q11313021091035240yes
2005-Q421210192171483370yes
2005-Q3181806715972450yes
2005-Q2151501606911821yes
2005-Q1108030141yes
2004-Q4111003708605090yes
2004-Q31010010681123690yes
2004-Q21413028891343350yes
2004-Q1980071202180yes
2003-Q4131300111092630yes
2003-Q3191900121041890yes
2003-Q21312015472903820yes
2003-Q110100051024250yes
2002-Q4141401739291550yes
2002-Q3121102181071720yes
2002-Q2111002419952130yes
2002-Q11515017412782810yes
2001-Q4131302118462430yes
2001-Q314140010653020yes
2001-Q27701437495710yes
2001-Q1108039231yes
2000-Q4141301509923200yes
2000-Q3161603711513470yes
2000-Q21514841982406441yes
2000-Q110106525774970yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

123 of the 1,549 stairs permits filed since 2000 (8%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Marina neighborhood

Shown apart, with their own page here: bathroom remodel (4,620 filed, 3,379 finished; contractors); kitchen remodel (4,226 filed, 3,107 finished; contractors); stairs (1,549 filed, 1,069 finished; contractors); deck (939 filed, 610 finished; contractors); roof deck (573 filed, 329 finished; contractors). Other types: 23,123 permits. All permits in San Francisco's Marina neighborhood

Nearby neighborhoods

Pacific Heights, Russian Hill, Japantown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.