How long do building permits take in San Francisco's South of Market neighborhood?

In the South of Market neighborhood of San Francisco, of the 420 building permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, down from 6 days a year earlier. Of the 362 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 137 days of being issued, down from 147 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long building permits take in San Francisco's South ofMarket neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/south-of-market · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026420 issued2389 issued6
Permit issued to final sign-offOctober 2023 through September 2024362 finished137371 finished147

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 98 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q45200too recent
2026-Q3116862301830660too recent
2026-Q21251081634560950too recent
2026-Q111910239357371280too recent
2025-Q4142124611980732250too recent
2025-Q312511787969963380too recent
2025-Q2928010112541003050too recent
2025-Q110497417957662520too recent
2024-Q410395545681053850too recent
2024-Q313012316391962770yes
2024-Q2131113689851883840yes
2024-Q11511392451101463910yes
2023-Q410696059761286101yes
2023-Q312911531458613451427yes
2023-Q2162141919610917664429yes
2023-Q111510511348012663022yes
2022-Q415213541179615053639yes
2022-Q3155139516010614061231yes
2022-Q2149123518910311658630yes
2022-Q1154138318010510262937yes
2021-Q4162145313011310840133yes
2021-Q3155141212811519056225yes
2021-Q21931802618313611248944yes
2021-Q1134112362468011241234yes
2020-Q41721464415911018265241yes
2020-Q3133116262187612269648yes
2020-Q25954441743217552725yes
2020-Q119916802239516955480yes
2019-Q4289241091132204688122yes
2019-Q3294265192155217622114yes
2019-Q2337300085157126836152yes
2019-Q13523270100179140827146yes
2018-Q43503200122179130709146yes
2018-Q33573230260171175811146yes
2018-Q2415384110622791562163yes
2018-Q13282980103164111581128yes
2017-Q4305283093153106393124yes
2017-Q3345312090185140627127yes
2017-Q23012830120164173688110yes
2017-Q12872631169159172717103yes
2016-Q43042800111154137561127yes
2016-Q3340329096202130618119yes
2016-Q2332313055194127577115yes
2016-Q1334305085195139763109yes
2015-Q4302284077179111727100yes
2015-Q33963671102210135828151yes
2015-Q2353326277218179672104yes
2015-Q1377348173213132533131yes
2014-Q4343320196180120620139yes
2014-Q3342317084201113699113yes
2014-Q2433413115627694720135yes
2014-Q1368349056220104436126yes
2013-Q43493251108193127566119yes
2013-Q3333313053192116565118yes
2013-Q2414393063242126606141yes
2013-Q1407388052242158834134yes
2012-Q4362344062230133676109yes
2012-Q3316300036194119669103yes
2012-Q2338325180205112520112yes
2012-Q125724518614812278991yes
2011-Q420618908112813068356yes
2011-Q32672530641677173871yes
2011-Q228126505819610248061yes
2011-Q11991850381329343442yes
2010-Q42071890681287741449yes
2010-Q32141990981177631860yes
2010-Q220619404712410435464yes
2010-Q11881780591049435860yes
2009-Q42162080421267029867yes
2009-Q323422202112012331681yes
2009-Q223522505812812233282yes
2009-Q1256241021118106362111yes
2008-Q422820903871158737280yes
2008-Q325424002511891372106yes
2008-Q2298281037126125404122yes
2008-Q124922502510113043288yes
2007-Q4310293053118162448120yes
2007-Q325623401810116041791yes
2007-Q228927906014414862686yes
2007-Q123222801168711867396yes
2006-Q421020401268714348461yes
2006-Q3525512647313141418127yes
2006-Q23513341312519619643064yes
2006-Q1232224015511113381354yes
2005-Q42051930797112044779yes
2005-Q323922601539314965086yes
2005-Q22452350741087851977yes
2005-Q121621201139811847963yes
2004-Q42011970789512649060yes
2004-Q325024206911512946770yes
2004-Q221020501188411448259yes
2004-Q12021970839510533258yes
2003-Q4213204092968432452yes
2003-Q318418301128812245048yes
2003-Q217216801329313453533yes
2003-Q11731660769811938431yes
2002-Q41801680938712436235yes
2002-Q31901810969912644329yes
2002-Q22542400691539931121yes
2002-Q1207197089107774607yes
2001-Q41811670130911173996yes
2001-Q318217807684923752yes
2001-Q22462370741021783431yes
2001-Q12502340691141424331yes
2000-Q4242226088991774093yes
2000-Q32992680631041774306yes
2000-Q22762660631301995911yes
2000-Q13643460651201956864yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

7,254 of the 26,156 building permits filed since 2000 (28%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Citywide, 798 of 801,386 permits since 2000 (0%) name no neighborhood and count in the city's figures only. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's South of Market neighborhood

Shown apart, with their own page here: bathroom remodel (1,159 filed, 750 finished; contractors); kitchen remodel (1,156 filed, 762 finished; contractors); stairs (837 filed, 539 finished; contractors); deck (168 filed, 116 finished; contractors); roof deck (103 filed, 63 finished; contractors). Other types: 23,340 permits.

Nearby neighborhoods

Tenderloin, Mission Bay, Financial District/South Beach; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.