Permit GraphShortlistSan Francisco building permits since 2000

How long do stairs permits take in San Francisco's South of Market neighborhood?

In the South of Market neighborhood of San Francisco, of the 16 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 19 days, up from 16 days a year earlier. Of the 13 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 159 days of being issued, down from 308 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's South ofMarket neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/south-of-market/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202616 issued1916 issued16
Permit issued to final sign-offOctober 2023 through September 202413 finished15916 finished308

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q314742520too recent
2026-Q24310too recent
2026-Q14310too recent
2025-Q44310too recent
2025-Q37711030620too recent
2025-Q166022830too recent
2024-Q43320too recent
2024-Q35430yes
2024-Q24430yes
2024-Q16541051322470yes
2023-Q43220yes
2023-Q34440yes
2023-Q21084337361833964yes
2023-Q19810632164225561yes
2022-Q42101yes
2022-Q32220yes
2022-Q21110yes
2022-Q13321yes
2021-Q42220yes
2021-Q34331yes
2021-Q2553812351061590yes
2021-Q16613878763698400yes
2020-Q47612646241yes
2020-Q32210yes
2020-Q14312yes
2019-Q46422yes
2019-Q3662933841yes
2019-Q23311yes
2019-Q111112229965289004yes
2018-Q46534935848090yes
2018-Q3661011853701,8231yes
2018-Q2994425482468761yes
2018-Q1887736354577663yes
2017-Q43330yes
2017-Q3108265773946581yes
2017-Q21091525784701,4431yes
2017-Q1111003073751,7142yes
2016-Q411106893693005911yes
2016-Q3882415373487540yes
2016-Q21111278382567773yes
2016-Q11413814091907093yes
2015-Q4992221172124552yes
2015-Q3171426121111586303yes
2015-Q216122032592901,3773yes
2015-Q11312320092809641yes
2014-Q4181612126102141,1406yes
2014-Q3985335052181,7691yes
2014-Q2119497575256812yes
2014-Q1874823862526721yes
2013-Q413107011694098281yes
2013-Q31212456101643092yes
2013-Q21715774122545693yes
2013-Q116161274132413442yes
2012-Q4141319191103705432yes
2012-Q31010918381601,2531yes
2012-Q210106158101966110yes
2012-Q115152118791586444yes
2011-Q46605261356380yes
2011-Q3871606563221yes
2011-Q2151335512822651yes
2011-Q1181701916804041yes
2010-Q487196272194321yes
2010-Q310610546601760yes
2010-Q211110320101463460yes
2010-Q1981621162207221yes
2009-Q41095778641480yes
2009-Q34430yes
2009-Q28758351824080yes
2009-Q14412yes
2008-Q41311221881473694yes
2008-Q31110196969193yes
2008-Q2131201963891,7003yes
2008-Q11290575764393yes
2007-Q422210155102324144yes
2007-Q39804842yes
2007-Q21413016072767142yes
2007-Q13320yes
2006-Q42110yes
2006-Q38701453063461yes
2006-Q27609041yes
2006-Q14421yes
2005-Q4556511322yes
2005-Q377014522yes
2005-Q25503640yes
2005-Q18801727733870yes
2004-Q42201yes
2004-Q34431yes
2004-Q255130040yes
2004-Q1990106582100yes
2003-Q466019526671yes
2003-Q310101112552052930yes
2003-Q266345230yes
2003-Q14430yes
2002-Q44430yes
2002-Q32210yes
2002-Q24430yes
2002-Q116166154101384880yes
2001-Q4666524040yes
2001-Q35501720yes
2001-Q26502910yes
2001-Q177012541yes
2000-Q476135251222300yes
2000-Q35440yes
2000-Q266187530yes
2000-Q1776314120yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

108 of the 837 stairs permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's South of Market neighborhood

Shown apart, with their own page here: bathroom remodel (1,159 filed, 750 finished; contractors); kitchen remodel (1,156 filed, 762 finished; contractors); stairs (837 filed, 539 finished; contractors); deck (168 filed, 116 finished; contractors); roof deck (103 filed, 63 finished; contractors). Other types: 23,340 permits. All permits in San Francisco's South of Market neighborhood

Nearby neighborhoods

Tenderloin, Mission Bay, Financial District/South Beach; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.