Permit GraphShortlistSan Francisco building permits since 2000

How long do kitchen remodel permits take in San Francisco's Sunset/Parkside neighborhood?

In the Sunset/Parkside neighborhood of San Francisco, of the 287 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, up from 1 day a year earlier. Of the 252 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 202 days of being issued, up from 194 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco'sSunset/Parkside neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/sunset-parkside/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026287 issued2281 issued1
Permit issued to final sign-offOctober 2023 through September 2024252 finished202230 finished194

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q47100too recent
2026-Q3815313110too recent
2026-Q2908245916801380too recent
2026-Q18476044301082000too recent
2025-Q48676280531402570too recent
2025-Q389813106561612720too recent
2025-Q28078259581923230too recent
2025-Q15453089361633210too recent
2024-Q471691124561723460too recent
2024-Q39390479692104550yes
2024-Q27673183612015160yes
2024-Q16767153602034350yes
2023-Q46867243621766281yes
2023-Q38275453702647069yes
2023-Q2746811595819243711yes
2023-Q15046042401584006yes
2022-Q480737126621944829yes
2022-Q3101100199851755749yes
2022-Q291871290832726654yes
2022-Q191826856652577368yes
2021-Q4101966200852705339yes
2021-Q392900377924660911yes
2021-Q2908401386721373014yes
2021-Q1968602147335770013yes
2020-Q410087493077327462016yes
2020-Q37370103105521956712yes
2020-Q221201028171417803yes
2020-Q145390292342746373yes
2019-Q41028844277220767614yes
2019-Q3878351547031468511yes
2019-Q28076198642056399yes
2019-Q11049572108422561912yes
2018-Q41029511228220865911yes
2018-Q379771131651891,12210yes
2018-Q2817401876220473411yes
2018-Q1807441985822166313yes
2017-Q4898901507720663310yes
2017-Q3848152816520755313yes
2017-Q29693093801704128yes
2017-Q18786057751764307yes
2016-Q476731846015737612yes
2016-Q3848201266816034412yes
2016-Q27271074621524446yes
2016-Q192880567615435810yes
2015-Q4787712206118737711yes
2015-Q384810169691694238yes
2015-Q2938824566815948215yes
2015-Q1888711136522641214yes
2014-Q4918912866427971723yes
2014-Q384792806319552514yes
2014-Q282800132731435467yes
2014-Q15252012431204185yes
2013-Q45754042441453638yes
2013-Q393920167712536413yes
2013-Q2747101965933125yes
2013-Q1666508531103358yes
2012-Q46059016501523778yes
2012-Q387850227415642010yes
2012-Q260570264215258112yes
2012-Q14645011381605245yes
2011-Q4444303331272597yes
2011-Q35555013521083401yes
2011-Q26257010491123627yes
2011-Q1504806411163134yes
2010-Q4525206451193333yes
2010-Q34544010391113575yes
2010-Q25858011461473547yes
2010-Q1484506391203325yes
2009-Q4504904421293426yes
2009-Q35049018411423344yes
2009-Q2565509461303445yes
2009-Q165650354942864yes
2008-Q4686709511183226yes
2008-Q3666604571412284yes
2008-Q28684066513431313yes
2008-Q1676604581192715yes
2007-Q4646302481223358yes
2007-Q39090017015636914yes
2007-Q27470005514226311yes
2007-Q16060004315733710yes
2006-Q4676500491373089yes
2006-Q3595800481363014yes
2006-Q26666004912326912yes
2006-Q16363004613234012yes
2005-Q46161004414733710yes
2005-Q36161003912236212yes
2005-Q27372005513433210yes
2005-Q1505006321083399yes
2004-Q4565600391031984yes
2004-Q371690051912956yes
2004-Q2606000461173348yes
2004-Q1535300401324117yes
2003-Q4494900401122186yes
2003-Q34644002717124711yes
2003-Q24141019321052207yes
2003-Q153530437972127yes
2002-Q44241031331333614yes
2002-Q35757003910938612yes
2002-Q24141041251192395yes
2002-Q1333200241022461yes
2001-Q43939014261582650yes
2001-Q3454500301002420yes
2001-Q22828010171253130yes
2001-Q1373600261174410yes
2000-Q424240166171793350yes
2000-Q3404000251112741yes
2000-Q23535022251203100yes
2000-Q13029046131584881yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

760 of the 7,313 kitchen remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Sunset/Parkside neighborhood

Shown apart, with their own page here: bathroom remodel (10,452 filed, 8,088 finished; contractors); kitchen remodel (7,313 filed, 5,521 finished; contractors); stairs (2,879 filed, 2,023 finished; contractors); deck (1,899 filed, 1,354 finished; contractors); roof deck (201 filed, 116 finished; contractors). Other types: 33,821 permits. All permits in San Francisco's Sunset/Parkside neighborhood

Nearby neighborhoods

Inner Sunset, Golden Gate Park, Lakeshore; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.