How long do bathroom remodel permits take in San Francisco's Sunset/Parkside neighborhood?

In the Sunset/Parkside neighborhood of San Francisco, of the 372 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 4 days, the same as a year earlier. Of the 322 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 194 days of being issued, down from 217 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sSunset/Parkside neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/sunset-parkside/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026372 issued4376 issued4
Permit issued to final sign-offOctober 2023 through September 2024322 finished194271 finished217

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q49200too recent
2026-Q311575129541710too recent
2026-Q212410666326901280too recent
2026-Q11019206046861800too recent
2025-Q4107998109691462610too recent
2025-Q3104984124651823170too recent
2025-Q21181124101761923180too recent
2025-Q18784069641583700too recent
2024-Q485822154612103600too recent
2024-Q3113108389912024160yes
2024-Q29998595822064750yes
2024-Q18988257801804670yes
2023-Q48379264691756341yes
2023-Q398902658123270511yes
2023-Q2838021686519455310yes
2023-Q1605211154222853810yes
2022-Q4111967237832195259yes
2022-Q31019641108121354811yes
2022-Q212111771371051817018yes
2022-Q111310245348221959810yes
2021-Q412311352749728255017yes
2021-Q311711616310224668310yes
2021-Q211810811298921858318yes
2021-Q112311001599829569513yes
2020-Q4123110602659726259515yes
2020-Q310193203457719361112yes
2020-Q2222114108191828101yes
2020-Q170584229502225367yes
2019-Q4126112124329426770517yes
2019-Q311511361609224566316yes
2019-Q21049911218422670714yes
2019-Q11241181221810521763712yes
2018-Q4130118611610620064915yes
2018-Q310410042668522583210yes
2018-Q2999262028120450910yes
2018-Q112711541989820058511yes
2017-Q412011551729320566919yes
2017-Q3128125836110919252512yes
2017-Q212811841519618652116yes
2017-Q11071034978817647210yes
2016-Q41079961908416442213yes
2016-Q3139132217711117542619yes
2016-Q2134123721910618644814yes
2016-Q1129122312510616038412yes
2015-Q412211881401051905117yes
2015-Q3124121319410120954114yes
2015-Q210810622329119648110yes
2015-Q111911662489122862918yes
2014-Q412311933029318360924yes
2014-Q31211173489618551818yes
2014-Q2127124213111115243910yes
2014-Q18683393721584558yes
2013-Q410510031848414738413yes
2013-Q313512922811016236615yes
2013-Q21131061508516058413yes
2013-Q187840267013835610yes
2012-Q4101991288416240112yes
2012-Q31031011258614837215yes
2012-Q29187275751474069yes
2012-Q17372039581543937yes
2011-Q4858101016814246711yes
2011-Q38985126781403366yes
2011-Q28077131701293494yes
2011-Q18883164731463586yes
2010-Q46666030601423723yes
2010-Q37977125731553301yes
2010-Q28179122661513837yes
2010-Q166621127551483746yes
2009-Q481780156612939610yes
2009-Q38888018781483382yes
2009-Q289851146713830113yes
2009-Q17371022631372896yes
2008-Q48482046691282953yes
2008-Q31161160269414434514yes
2008-Q21201140710114335810yes
2008-Q11009706811262649yes
2007-Q41151110199116834111yes
2007-Q31381340310115736321yes
2007-Q210097007914840011yes
2007-Q1107106008616731611yes
2006-Q48583006115335215yes
2006-Q310510300901413706yes
2006-Q299990808115735611yes
2006-Q19797008313634910yes
2005-Q49393007015429616yes
2005-Q39695036715936116yes
2005-Q2107106008615435011yes
2005-Q1545300401602947yes
2004-Q4757400611203337yes
2004-Q3898700691413307yes
2004-Q29695006913342014yes
2004-Q1787700641544079yes
2003-Q494930113751513418yes
2003-Q39291016616625814yes
2003-Q27171031581262829yes
2003-Q17473014601182708yes
2002-Q4888301785913330812yes
2002-Q38988006312337210yes
2002-Q27473021581282357yes
2002-Q16059049511122741yes
2001-Q48484038661002100yes
2001-Q37472025501282310yes
2001-Q26160012481302680yes
2001-Q17372019621092800yes
2000-Q45652081401443580yes
2000-Q35755042431042520yes
2000-Q25857047431313540yes
2000-Q15148049341565053yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

952 of the 10,452 bathroom remodel permits filed since 2000 (9%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Sunset/Parkside neighborhood

Shown apart, with their own page here: bathroom remodel (10,452 filed, 8,088 finished; contractors); kitchen remodel (7,313 filed, 5,521 finished; contractors); stairs (2,879 filed, 2,023 finished; contractors); deck (1,899 filed, 1,354 finished; contractors); roof deck (201 filed, 116 finished; contractors). Other types: 33,821 permits. All permits in San Francisco's Sunset/Parkside neighborhood

Nearby neighborhoods

Inner Sunset, Golden Gate Park, Lakeshore; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.