How long do deck permits take in San Francisco's Pacific Heights neighborhood?

In the Pacific Heights neighborhood of San Francisco, of the 22 deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 8 days, down from 14 days a year earlier. Of the 16 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 206 days of being issued, up from 71 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long deck permits take in San Francisco's Pacific HeightsneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/pacific-heights/deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202622 issued827 issued14
Permit issued to final sign-offOctober 2023 through September 202416 finished20613 finished71

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 164 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q310552810too recent
2026-Q266208310too recent
2026-Q1765115020too recent
2025-Q46511530too recent
2025-Q37573630too recent
2025-Q2662840720too recent
2025-Q15563020too recent
2024-Q412111119961523700too recent
2024-Q386256551884770yes
2024-Q2774334130yes
2024-Q1877615673380yes
2023-Q44430yes
2023-Q34430yes
2023-Q275134930yes
2023-Q186108442yes
2022-Q43330yes
2022-Q399217871454590yes
2022-Q213110390112106030yes
2022-Q13330yes
2021-Q4111016692251843691yes
2021-Q34440yes
2021-Q21194432781754680yes
2021-Q1873351,19443yes
2020-Q44422yes
2020-Q313131788122025061yes
2020-Q26667261504770yes
2020-Q13320yes
2019-Q41210147591205841yes
2019-Q365937352031,3600yes
2019-Q212117092873875954yes
2019-Q187185341yes
2018-Q41083742166488502yes
2018-Q3886217442781yes
2018-Q25421yes
2018-Q1883670571434021yes
2017-Q4863445056448421yes
2017-Q33330yes
2017-Q2882010271631,4291yes
2017-Q1108169271406280yes
2016-Q465163441yes
2016-Q3990538874091yes
2016-Q23302yes
2016-Q11313120392159072yes
2015-Q46620254251324721yes
2015-Q31194640674246842yes
2015-Q2111123860103406100yes
2015-Q1992932384179830yes
2014-Q46511751493790yes
2014-Q31111333673711,6662yes
2014-Q27772797568020yes
2014-Q14312yes
2013-Q41084940772207411yes
2013-Q315150944141529190yes
2013-Q29923845663741,5203yes
2013-Q15440yes
2012-Q4771371063190yes
2012-Q3131213210813901yes
2012-Q265292775504390yes
2012-Q1151310165101967561yes
2011-Q499422764161,4161yes
2011-Q312128211112844501yes
2011-Q214141177111073443yes
2011-Q19917851292357470yes
2010-Q4141472299122089862yes
2010-Q3151455228679602yes
2010-Q2990681144011yes
2010-Q1119120761202221yes
2009-Q41010224381213292yes
2009-Q377018471684560yes
2009-Q211114308765742yes
2009-Q18713226533600yes
2008-Q43330yes
2008-Q311902681613410yes
2008-Q21513725081844461yes
2008-Q1109411571384922yes
2007-Q415144174101503123yes
2007-Q35504235681320yes
2007-Q2111001567613601yes
2007-Q1667636651562770yes
2006-Q411113933562212820yes
2006-Q31515058131504361yes
2006-Q21111018843yes
2006-Q177022761945110yes
2005-Q41616029892003050yes
2005-Q366016051292740yes
2005-Q298049271235850yes
2005-Q15440yes
2004-Q477050761483420yes
2004-Q312120232101042350yes
2004-Q21311056461803170yes
2004-Q155021541yes
2003-Q4151307482023491yes
2003-Q3121203547672792yes
2003-Q21412025471302060yes
2003-Q166015630yes
2002-Q4121201476342701yes
2002-Q3101005852002321yes
2002-Q21010024361363601yes
2002-Q188025020yes
2001-Q49903171306280yes
2001-Q38801485412010yes
2001-Q2990426482340yes
2001-Q11091211571133450yes
2000-Q487029240yes
2000-Q3111101498862370yes
2000-Q25502730yes
2000-Q1129025852756630yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

74 of the 949 deck permits filed since 2000 (8%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Pacific Heights neighborhood

Shown apart, with their own page here: bathroom remodel (4,845 filed, 3,523 finished; contractors); kitchen remodel (4,365 filed, 3,192 finished; contractors); stairs (1,514 filed, 952 finished; contractors); deck (949 filed, 637 finished; contractors); roof deck (336 filed, 200 finished; contractors). Other types: 24,826 permits. All permits in San Francisco's Pacific Heights neighborhood

Nearby neighborhoods

Japantown, Marina, Western Addition; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.