How long do deck permits take in San Francisco's Outer Mission neighborhood?

In the Outer Mission neighborhood of San Francisco, of the 12 deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 8 days, down from 46 days a year earlier. Only 3 of the permits filed from October 2023 through September 2024 have reached final sign-off, too few for a reliable figure.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long deck permits take in San Francisco's Outer MissionneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge05101520252017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/outer-mission/deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202612 issued89 issued46
Permit issued to final sign-offOctober 2023 through September 20243 finishedunder 55 finished226

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 164 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q33300too recent
2026-Q22210too recent
2026-Q15310too recent
2025-Q44430too recent
2025-Q33310too recent
2025-Q21000too recent
2025-Q12220too recent
2024-Q44420too recent
2024-Q33320yes
2024-Q22200yes
2024-Q12100yes
2023-Q41110yes
2023-Q31110yes
2023-Q25422yes
2023-Q11101yes
2022-Q42220yes
2022-Q355198531yes
2022-Q22220yes
2022-Q15331yes
2021-Q46431yes
2021-Q355105141yes
2021-Q24331yes
2021-Q14440yes
2020-Q42211yes
2020-Q32220yes
2020-Q21001yes
2020-Q11110yes
2019-Q465189022yes
2019-Q34321yes
2019-Q2982440445yes
2019-Q13330yes
2018-Q43330yes
2018-Q33210yes
2018-Q22220yes
2018-Q13321yes
2017-Q43330yes
2017-Q35431yes
2017-Q265020632yes
2017-Q14330yes
2016-Q4553430422yes
2016-Q365419242yes
2016-Q266462533yes
2016-Q166162252332,1770yes
2015-Q44422yes
2015-Q32211yes
2015-Q25522631yes
2015-Q13330yes
2014-Q4662321653176081yes
2014-Q32220yes
2014-Q23210yes
2014-Q11110yes
2013-Q4889822772107221yes
2013-Q3874429650771yes
2013-Q24431yes
2013-Q13330yes
2012-Q44330yes
2012-Q25508351001510yes
2012-Q11110yes
2011-Q22220yes
2011-Q155817051704600yes
2010-Q42211yes
2010-Q35431yes
2010-Q25431yes
2010-Q12220yes
2009-Q4990137782542yes
2009-Q38841338773950yes
2009-Q2986807843530yes
2009-Q11110yes
2008-Q487113762352660yes
2008-Q34440yes
2008-Q21110yes
2008-Q13330yes
2007-Q43330yes
2007-Q310824661602520yes
2007-Q24440yes
2007-Q1760766501040yes
2006-Q43330yes
2006-Q34430yes
2006-Q22200yes
2006-Q1550041yes
2005-Q42210yes
2005-Q36603355831520yes
2005-Q24430yes
2005-Q155019741yes
2004-Q4980917812910yes
2004-Q355015921yes
2004-Q23320yes
2004-Q13330yes
2003-Q43310yes
2003-Q33320yes
2003-Q24420yes
2003-Q13321yes
2002-Q44430yes
2002-Q35440yes
2002-Q265019440yes
2002-Q13320yes
2001-Q455428130yes
2001-Q32210yes
2001-Q255052630yes
2001-Q12220yes
2000-Q43320yes
2000-Q21100yes
2000-Q14430yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

46 of the 403 deck permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Outer Mission neighborhood

Shown apart, with their own page here: bathroom remodel (2,084 filed, 1,559 finished; contractors); kitchen remodel (1,307 filed, 942 finished; contractors); stairs (749 filed, 512 finished; contractors); deck (403 filed, 278 finished; contractors). Other types: 8,343 permits. All permits in San Francisco's Outer Mission neighborhood

Nearby neighborhoods

Excelsior, Oceanview/Merced/Ingleside, Glen Park; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.