How long do deck permits take in San Francisco's Haight Ashbury neighborhood?

In the Haight Ashbury neighborhood of San Francisco, of the 15 deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 9 days, up from 2 days a year earlier. Of the 11 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 150 days of being issued, down from 265 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long deck permits take in San Francisco's Haight AshburyneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/haight-ashbury/deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202615 issued910 issued2
Permit issued to final sign-offOctober 2023 through September 202411 finished15012 finished265

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 164 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q35210too recent
2026-Q276129840too recent
2026-Q12210too recent
2025-Q45505820too recent
2025-Q35430too recent
2025-Q21110too recent
2025-Q13210too recent
2024-Q43320too recent
2024-Q33320yes
2024-Q23330yes
2024-Q15430yes
2023-Q4555246930yes
2023-Q35441yes
2023-Q26321yes
2023-Q16511621040yes
2022-Q43320yes
2022-Q3763055053005911yes
2022-Q23112yes
2022-Q17613679832yes
2021-Q4109211,38052615103yes
2021-Q34431yes
2021-Q277128243yes
2021-Q12110yes
2020-Q47732471666821,1710yes
2020-Q33220yes
2020-Q21110yes
2020-Q12210yes
2019-Q45440yes
2019-Q34212yes
2019-Q28706862876201yes
2019-Q14440yes
2018-Q43320yes
2018-Q38783292784920yes
2018-Q25532454817050yes
2018-Q13330yes
2017-Q47626694065027920yes
2017-Q376417061645670yes
2017-Q26603454025061yes
2017-Q16611634941yes
2016-Q43330yes
2016-Q31194168435yes
2016-Q27509569760yes
2016-Q155638954659500yes
2015-Q47412yes
2015-Q31210450082104182yes
2015-Q26652861726820yes
2015-Q1108321253295341yes
2014-Q465620022yes
2014-Q34330yes
2014-Q2882884572439120yes
2014-Q110105432862444943yes
2013-Q45512741yes
2013-Q37601661241940yes
2013-Q2766919851885071yes
2013-Q1985239571251,0151yes
2012-Q466121875594071yes
2012-Q33211yes
2012-Q27505440yes
2012-Q15441yes
2011-Q498054861151460yes
2011-Q31211182101186590yes
2011-Q266252440yes
2011-Q1983621282189640yes
2010-Q49905681383181yes
2010-Q398311582967331yes
2010-Q213137236102408801yes
2010-Q1777621961646521yes
2009-Q4111002187682793yes
2009-Q314131109113214652yes
2009-Q288216051024890yes
2009-Q16621041451793021yes
2008-Q45440yes
2008-Q398024261395901yes
2008-Q21091041842yes
2008-Q177117662403201yes
2007-Q414137292101207662yes
2007-Q399024661433103yes
2007-Q29901327867321yes
2007-Q11212011061502912yes
2006-Q477029241yes
2006-Q31313017492234282yes
2006-Q2131302468492030yes
2006-Q1101001565221252yes
2005-Q46606632yes
2005-Q3111003881222852yes
2005-Q27705021yes
2005-Q166918851392280yes
2004-Q44420yes
2004-Q34422yes
2004-Q299030461142143yes
2004-Q1653038641yes
2003-Q4151404247601503yes
2003-Q355010431yes
2003-Q21313036481643335yes
2003-Q19902447482301yes
2002-Q466023340yes
2002-Q37602386773040yes
2002-Q21082422740yes
2002-Q18801256621411yes
2001-Q455020911yes
2001-Q31414142287872361yes
2001-Q2770915511220yes
2001-Q1776025840yes
2000-Q4884613351943850yes
2000-Q3982019071814410yes
2000-Q24320yes
2000-Q116169232101425220yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

91 of the 751 deck permits filed since 2000 (12%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Haight Ashbury neighborhood

Shown apart, with their own page here: bathroom remodel (3,075 filed, 2,147 finished; contractors); kitchen remodel (2,766 filed, 1,877 finished; contractors); stairs (1,550 filed, 1,064 finished; contractors); deck (751 filed, 494 finished; contractors); roof deck (170 filed, 96 finished; contractors). Other types: 15,744 permits. All permits in San Francisco's Haight Ashbury neighborhood

Nearby neighborhoods

Lone Mountain/USF, Castro/Upper Market, Hayes Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.