How long do kitchen remodel permits take in San Francisco's Bayview Hunters Point neighborhood?

In the Bayview Hunters Point neighborhood of San Francisco, of the 37 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 4 days a year earlier. Of the 104 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 438 days of being issued, up from 155 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco'sBayview Hunters Point neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/bayview-hunters-point/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202637 issued052 issued4
Permit issued to final sign-offOctober 2023 through September 2024104 finished43835 finished155

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42200too recent
2026-Q39410too recent
2026-Q2141403440too recent
2026-Q11110049589950too recent
2025-Q49913362002670too recent
2025-Q3151404581803070too recent
2025-Q21514092101272600too recent
2025-Q1211915175161362970too recent
2024-Q475130730too recent
2024-Q32120229191204400yes
2024-Q271706078675055730yes
2024-Q114140377101121750yes
2023-Q41110811481464990yes
2023-Q31110022561253183yes
2023-Q2131263670101563542yes
2023-Q1161534691775113yes
2022-Q4161410160101625134yes
2022-Q316155220122324454yes
2022-Q216121122881883175yes
2022-Q118164265132563333yes
2021-Q419196124152023524yes
2021-Q31818032141165712yes
2021-Q224200468172347324yes
2021-Q11811056551463067yes
2020-Q4242076731173838735yes
2020-Q3191729413112581,0506yes
2020-Q21212213396982804yes
2020-Q11714439991844495yes
2019-Q41716301,03092474365yes
2019-Q3262228278152515435yes
2019-Q226220260173516615yes
2019-Q13027033151563377yes
2018-Q417170188142684902yes
2018-Q323221094181244523yes
2018-Q237344321311905662yes
2018-Q138344395282767115yes
2017-Q4353501752233672413yes
2017-Q329260388191553817yes
2017-Q22222092131464909yes
2017-Q118180225152114051yes
2016-Q421200136162368023yes
2016-Q31515079121443602yes
2016-Q22321083172586101yes
2016-Q12118194161573123yes
2015-Q431244440191966379yes
2015-Q32524086182467395yes
2015-Q230250103182245176yes
2015-Q11514032101823133yes
2014-Q42120065152691,0802yes
2014-Q32221043171213593yes
2014-Q23230040261784023yes
2014-Q11717031121683031yes
2013-Q423225152181525143yes
2013-Q327250128221143181yes
2013-Q2282509201033246yes
2013-Q12323045191033092yes
2012-Q420202265151193953yes
2012-Q31313113111775352yes
2012-Q2171701113712373yes
2012-Q11515014121402920yes
2011-Q4272703231093762yes
2011-Q32321027141402825yes
2011-Q29901461349322yes
2011-Q19902742yes
2010-Q41817068121063374yes
2010-Q37522145911410yes
2010-Q2131206461494391yes
2010-Q12219223161202281yes
2009-Q4131301010802611yes
2009-Q32019075161407044yes
2009-Q21515029922462yes
2009-Q11918014141843562yes
2008-Q41110011381948961yes
2008-Q311113444971552621yes
2008-Q2131322591392551yes
2008-Q1171606611981433yes
2007-Q4252405151462593yes
2007-Q31615018642893yes
2007-Q214140161663263yes
2007-Q1151500131653891yes
2006-Q410100081212890yes
2006-Q316160010901971yes
2006-Q2242300131242980yes
2006-Q116160071111733yes
2005-Q41212006942482yes
2005-Q3181804561884221yes
2005-Q2161600101473500yes
2005-Q1880022yes
2004-Q4550021yes
2004-Q31313006811201yes
2004-Q21111029671753061yes
2004-Q19901805491292yes
2003-Q45505140yes
2003-Q31515046101592690yes
2003-Q2171603481823950yes
2003-Q11515111891051962yes
2002-Q41515018121022620yes
2002-Q31514007821533yes
2002-Q2151500121243051yes
2002-Q1202002013582760yes
2001-Q423220018921270yes
2001-Q316150110681540yes
2001-Q26602045858340yes
2001-Q177025061172410yes
2000-Q49902910yes
2000-Q3990451702490yes
2000-Q2980020yes
2000-Q16601220yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

248 of the 1,911 kitchen remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Bayview Hunters Point neighborhood

Shown apart, with their own page here: bathroom remodel (2,453 filed, 1,694 finished; contractors); kitchen remodel (1,911 filed, 1,279 finished; contractors); stairs (1,180 filed, 748 finished; contractors); deck (707 filed, 429 finished; contractors). Other types: 18,226 permits. All permits in San Francisco's Bayview Hunters Point neighborhood

Nearby neighborhoods

Portola, Bernal Heights, Visitacion Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.