How long do deck permits take in San Francisco's Bayview Hunters Point neighborhood?

In the Bayview Hunters Point neighborhood of San Francisco, of the 9 deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, down from 50 days a year earlier. Of the 18 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 196 days of being issued, up from 192 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long deck permits take in San Francisco's Bayview HuntersPoint neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/bayview-hunters-point/deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 20269 issued228 issued50
Permit issued to final sign-offOctober 2023 through September 202418 finished19620 finished192

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 164 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q36501830too recent
2026-Q25200too recent
2026-Q12000too recent
2025-Q43210too recent
2025-Q33310too recent
2025-Q24310too recent
2025-Q1171750181151401540too recent
2024-Q4658814240too recent
2024-Q31899418861962350yes
2024-Q23220yes
2024-Q18807761212740yes
2023-Q4755720041yes
2023-Q33211yes
2023-Q28784771852630yes
2023-Q15431yes
2022-Q41412169892183953yes
2022-Q333220yes
2022-Q25441yes
2022-Q14440yes
2021-Q44440yes
2021-Q34321yes
2021-Q2555824952777730yes
2021-Q16516447042yes
2020-Q49723188344yes
2020-Q37534372432yes
2020-Q21110yes
2020-Q16311yes
2019-Q465425542yes
2019-Q3119730484887871yes
2019-Q275106342yes
2019-Q15431yes
2018-Q41111723783181,0192yes
2018-Q3873432741yes
2018-Q21311716491414761yes
2018-Q1991120762674963yes
2017-Q4873619273648081yes
2017-Q3981835782224110yes
2017-Q29931898932131yes
2017-Q15440yes
2016-Q43321yes
2016-Q3773121943yes
2016-Q26323yes
2016-Q1662441,98033yes
2015-Q499108261704963yes
2015-Q34320yes
2015-Q23111yes
2015-Q14220yes
2014-Q46677661001,4140yes
2014-Q3555025822yes
2014-Q276824352926270yes
2014-Q166012652784240yes
2013-Q44312yes
2013-Q3118655141yes
2013-Q27621851121320yes
2013-Q1654831241yes
2012-Q487102047561180yes
2012-Q34420yes
2012-Q23220yes
2012-Q155047932yes
2011-Q43301yes
2011-Q355275951210yes
2011-Q2550341yes
2011-Q12220yes
2010-Q42211yes
2010-Q31000yes
2010-Q23210yes
2010-Q13330yes
2009-Q4550351193420yes
2009-Q3771396182100yes
2009-Q25431yes
2009-Q188717861843390yes
2008-Q44440yes
2008-Q355327140yes
2008-Q26611946691590yes
2008-Q15220yes
2007-Q48440yes
2007-Q37706731yes
2007-Q21110007621631yes
2007-Q11100yes
2006-Q476025240yes
2006-Q355076230yes
2006-Q2886030071112890yes
2006-Q165034922yes
2005-Q455055840yes
2005-Q34430yes
2005-Q22210yes
2005-Q11100yes
2004-Q34430yes
2004-Q25502240yes
2004-Q176018830yes
2003-Q4962937321yes
2003-Q34412yes
2003-Q213131626101685440yes
2003-Q1121261540yes
2002-Q42220yes
2002-Q314142933710761421yes
2002-Q238383649261121325yes
2002-Q1660134555980yes
2001-Q41212061240810yes
2001-Q3770030yes
2001-Q26610032031yes
2001-Q155019151071840yes
2000-Q44310yes
2000-Q34410yes
2000-Q21110yes
2000-Q18804351383260yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

72 of the 707 deck permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Bayview Hunters Point neighborhood

Shown apart, with their own page here: bathroom remodel (2,453 filed, 1,694 finished; contractors); kitchen remodel (1,911 filed, 1,279 finished; contractors); stairs (1,180 filed, 748 finished; contractors); deck (707 filed, 429 finished; contractors). Other types: 18,226 permits. All permits in San Francisco's Bayview Hunters Point neighborhood

Nearby neighborhoods

Portola, Bernal Heights, Visitacion Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.