How long do bathroom remodel permits take in San Francisco's Visitacion Valley neighborhood?

In the Visitacion Valley neighborhood of San Francisco, of the 31 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, up from 0 days a year earlier. Of the 17 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 219 days of being issued, down from 241 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sVisitacion Valley neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/visitacion-valley/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202631 issued222 issued0
Permit issued to final sign-offOctober 2023 through September 202417 finished21926 finished241

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q36681220too recent
2026-Q2990145781190too recent
2026-Q176817820too recent
2025-Q4101022381342870too recent
2025-Q365022330too recent
2025-Q2773414553204300too recent
2025-Q1666695771980too recent
2024-Q44420too recent
2024-Q33330yes
2024-Q27682161663000yes
2024-Q14440yes
2023-Q4651539840yes
2023-Q35573541yes
2023-Q21010010873115333yes
2023-Q19601251181832yes
2022-Q41411789102663742yes
2022-Q31191115091067011yes
2022-Q298046364187263yes
2022-Q18825451403432yes
2021-Q41083215861002193yes
2021-Q386056672781yes
2021-Q26611447241yes
2021-Q12220yes
2020-Q4131116790482887334yes
2020-Q3107189151822301yes
2020-Q15431yes
2019-Q412119318103755401yes
2019-Q310101016992611,0271yes
2019-Q2768813461528401yes
2019-Q11092032472978811yes
2018-Q41413616183271,1553yes
2018-Q314124238101703862yes
2018-Q28864162043082yes
2018-Q114144129132594380yes
2017-Q4761863052321,6551yes
2017-Q365026451413520yes
2017-Q27422yes
2017-Q18797063565452yes
2016-Q4653430131yes
2016-Q377037551968320yes
2016-Q297141254109823yes
2016-Q110108294102267430yes
2015-Q466147541yes
2015-Q3121149392435402yes
2015-Q266215124yes
2015-Q1101001681624262yes
2014-Q488581782941,1250yes
2014-Q3994248983481yes
2014-Q27742371743550yes
2014-Q11514110111422433yes
2013-Q48829553019193yes
2013-Q3141311591262452yes
2013-Q28871681103450yes
2013-Q1121001781503741yes
2012-Q43330yes
2012-Q3990289551870yes
2012-Q21211750111853960yes
2012-Q1660154566940yes
2011-Q43320yes
2011-Q38802081663760yes
2011-Q2101003710934370yes
2011-Q1109037494281yes
2010-Q47713171051910yes
2010-Q39911981242541yes
2010-Q2131113210943031yes
2010-Q1121211010832022yes
2009-Q48824871104451yes
2009-Q310100357702323yes
2009-Q25501641yes
2009-Q188249381203070yes
2008-Q4970461161652yes
2008-Q3111116251103653yes
2008-Q211100381001900yes
2008-Q111100591603482yes
2007-Q411111791345770yes
2007-Q311902761431701yes
2007-Q2880162113411yes
2007-Q1550040yes
2006-Q42201yes
2006-Q399006962000yes
2006-Q28803661563270yes
2006-Q166012330yes
2005-Q411110071051850yes
2005-Q310100061642360yes
2005-Q21111050381742400yes
2005-Q13330yes
2004-Q4111003771342690yes
2004-Q398019461153001yes
2004-Q276023922yes
2004-Q1111100101222720yes
2003-Q48702641yes
2003-Q3660061324760yes
2003-Q2770071271660yes
2003-Q13330yes
2002-Q4101004481223041yes
2002-Q32220yes
2002-Q2121205489863252yes
2002-Q13320yes
2001-Q488024762485201yes
2001-Q36601761443830yes
2001-Q23330yes
2001-Q14440yes
2000-Q4660851351890yes
2000-Q3550020yes
2000-Q22210yes
2000-Q1660410yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

92 of the 859 bathroom remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Visitacion Valley neighborhood

Shown apart, with their own page here: bathroom remodel (859 filed, 628 finished; contractors); kitchen remodel (570 filed, 393 finished; contractors); stairs (237 filed, 147 finished; contractors); deck (213 filed, 141 finished; contractors). Other types: 3,988 permits. All permits in San Francisco's Visitacion Valley neighborhood

Nearby neighborhoods

McLaren Park, Portola, Excelsior; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.