How long do bathroom remodel permits take in San Francisco's Tenderloin neighborhood?

In the Tenderloin neighborhood of San Francisco, of the 27 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 11 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 90 days of being issued, down from 118 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sTenderloin neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/tenderloin/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202627 issued035 issued0
Permit issued to final sign-offOctober 2023 through September 202411 finished9032 finished118

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q31080810too recent
2026-Q210100385991470too recent
2026-Q15420too recent
2025-Q4550595922020too recent
2025-Q3550040too recent
2025-Q27501840too recent
2025-Q1141405412901900too recent
2024-Q413110610981360too recent
2024-Q3970930yes
2024-Q25517520yes
2024-Q16537440yes
2023-Q42220yes
2023-Q36531941yes
2023-Q210100661162263yes
2023-Q1161617151351881yes
2022-Q4111103271462024yes
2022-Q31212105491713693yes
2022-Q21817128111271706yes
2022-Q1302907824941705yes
2021-Q420192147171642650yes
2021-Q3343303425942617yes
2021-Q2414002321262967yes
2021-Q127260305161132489yes
2020-Q417134112781262867yes
2020-Q32319001012120410yes
2020-Q2151464314611240yes
2020-Q1413809286220110yes
2019-Q445420853110126511yes
2019-Q35150036315633818yes
2019-Q23939058226426417yes
2019-Q1393803030642768yes
2018-Q4414003830961688yes
2018-Q3414103333581738yes
2018-Q2302904525744474yes
2018-Q13938011286624410yes
2017-Q4272503115781509yes
2017-Q3282702520942198yes
2017-Q2353202921581549yes
2017-Q131290124641212yes
2016-Q435350629571706yes
2016-Q3525006240841205yes
2016-Q2444312531991978yes
2016-Q144430142611137615yes
2015-Q4403901026723568yes
2015-Q343410833793068yes
2015-Q24948020288015117yes
2015-Q158560364411461611yes
2014-Q4302902624773715yes
2014-Q337360531711027015yes
2014-Q25554070328638218yes
2014-Q1414101029733109yes
2013-Q430290824903044yes
2013-Q3373601027561978yes
2013-Q2454501638994937yes
2013-Q1343201177177012yes
2012-Q4232308121321,3714yes
2012-Q311828462881,4622yes
2012-Q2119016781403yes
2012-Q1660135867831yes
2011-Q4770441yes
2011-Q31313049111803291yes
2011-Q2141402312581191yes
2011-Q1990408722521yes
2010-Q44440yes
2010-Q311100408762691yes
2010-Q29911729402370yes
2010-Q188475881600yes
2009-Q44411yes
2009-Q388037631511yes
2009-Q24440yes
2009-Q11212019514021yes
2008-Q4151501349625721yes
2008-Q334340026782562yes
2008-Q241410024982037yes
2008-Q141410119673067yes
2007-Q449490227902867yes
2007-Q357560142213303yes
2007-Q2414100171652287yes
2007-Q135340021782352yes
2006-Q4383800221516332yes
2006-Q316160127562522yes
2006-Q21111005791242yes
2006-Q11312008641631yes
2005-Q4191803145yes
2005-Q36601023yes
2005-Q255013130yes
2005-Q11100yes
2004-Q4550030yes
2004-Q34430yes
2004-Q288015440yes
2004-Q14411yes
2003-Q43320yes
2003-Q33320yes
2003-Q22202yes
2003-Q11101yes
2002-Q44431yes
2002-Q34421yes
2002-Q22211yes
2002-Q155013110yes
2001-Q44440yes
2001-Q34400yes
2001-Q277015120yes
2001-Q16602200yes
2000-Q477034331yes
2000-Q32210yes
2000-Q22210yes
2000-Q176014230yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

418 of the 2,192 bathroom remodel permits filed since 2000 (19%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Tenderloin neighborhood

Shown apart, with their own page here: kitchen remodel (2,385 filed, 1,598 finished; contractors); bathroom remodel (2,192 filed, 1,438 finished; contractors); stairs (312 filed, 173 finished; contractors). Other types: 14,026 permits. All permits in San Francisco's Tenderloin neighborhood

Nearby neighborhoods

Nob Hill, South of Market, Chinatown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.