How long do roof deck permits take in San Francisco?

In San Francisco, of the 100 roof deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 32 days, down from 55 days a year earlier. Of the 93 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 250 days of being issued, down from 310 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long roof deck permits take in San FranciscoMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/san-francisco/roof-deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026100 issued32141 issued55
Permit issued to final sign-offOctober 2023 through September 202493 finished250106 finished310

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q410100too recent
2026-Q3602503640too recent
2026-Q2512936128826850too recent
2026-Q120147415320too recent
2025-Q449329824930too recent
2025-Q3474240216201833080too recent
2025-Q2444088232181563430too recent
2025-Q1343098224142444050too recent
2024-Q4352942147172584640too recent
2024-Q3453828214252664390yes
2024-Q2423224323221863850yes
2024-Q1322623460182666560yes
2023-Q4504138513282635582yes
2023-Q3443584425252936729yes
2023-Q25843576132737762112yes
2023-Q1393343373223807105yes
2022-Q45547159830322707737yes
2022-Q350402245542836462412yes
2022-Q269522286563248187118yes
2022-Q165522348933533290312yes
2021-Q45540876822535280717yes
2021-Q361502299162533591818yes
2021-Q255421261,0232935580314yes
2021-Q17461337864456301,00712yes
2020-Q465521484254237391912yes
2020-Q359501791,1602934584617yes
2020-Q29622130243yes
2020-Q14732146883244741,0319yes
2019-Q4786479664443161,07917yes
2019-Q38265113859444831,19416yes
2019-Q26953841,038343841,21218yes
2019-Q17362847664248697913yes
2018-Q46152126744404121,2768yes
2018-Q38067388575341899613yes
2018-Q26653141577373451,07510yes
2018-Q17462818723929798217yes
2017-Q48363947285126786110yes
2017-Q3675883474473159378yes
2017-Q2645796650442721,13611yes
2017-Q1514096556293851,05310yes
2016-Q47870156706513841,07714yes
2016-Q37661676554136488116yes
2016-Q27967666605033888312yes
2016-Q16149119624423961,1099yes
2015-Q48368186614524301,0179yes
2015-Q37975184825564361,64513yes
2015-Q28573176646524121,22414yes
2015-Q18676140679584341,18513yes
2014-Q48371163643564621,68211yes
2014-Q3827444572583101,17212yes
2014-Q28780200597614211,00313yes
2014-Q16664105416524521,2628yes
2013-Q47467141559473261,08915yes
2013-Q3857941556683521,0035yes
2013-Q2655741496462608627yes
2013-Q1534953399413329947yes
2012-Q44437170484313606992yes
2012-Q3656037441442821,33110yes
2012-Q23834114426273209673yes
2012-Q14843106401343881,1996yes
2011-Q44038100623303046906yes
2011-Q3403830466323189465yes
2011-Q2535317334402787077yes
2011-Q1383448243302278151yes
2010-Q4363265403262807765yes
2010-Q3434121287332364924yes
2010-Q255501384763632464411yes
2010-Q14038112308312969862yes
2009-Q4423586407293495643yes
2009-Q3423812363242184145yes
2009-Q2565336580453017522yes
2009-Q1302447199211996231yes
2008-Q45952152510402444988yes
2008-Q3484338402282447558yes
2008-Q2806555419482627598yes
2008-Q1444113476262384944yes
2007-Q45447137439303047455yes
2007-Q343425291261964906yes
2007-Q237320296231795352yes
2007-Q1333129426172382,2318yes
2006-Q443400275272374735yes
2006-Q3363248348252124812yes
2006-Q238354380232244635yes
2006-Q1313150419202724433yes
2005-Q4353359702193234862yes
2005-Q342360487201642984yes
2005-Q2302867473182221,1574yes
2005-Q11716100545121143981yes
2004-Q417130232111333791yes
2004-Q336300600191673692yes
2004-Q227250417192326100yes
2004-Q1242478699102985601yes
2003-Q4333159804191973669yes
2003-Q338360390171556064yes
2003-Q2252066476112605135yes
2003-Q1151317143771818775yes
2002-Q42017024881433692yes
2002-Q3332814330171573993yes
2002-Q22321113385123694973yes
2002-Q1141313141582166370yes
2001-Q4232379516151327381yes
2001-Q3262448386141764221yes
2001-Q2191666230122625102yes
2001-Q1242013137121143590yes
2000-Q4282517223102408372yes
2000-Q315152329853474250yes
2000-Q2262451290162003960yes
2000-Q1242316286112726350yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

697 of the 5,264 roof deck permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco

Shown apart, with their own page here: bathroom remodel (104,357 filed, 75,687 finished; contractors); kitchen remodel (88,742 filed, 63,705 finished; contractors); stairs (42,896 filed, 29,067 finished; contractors); deck (24,218 filed, 16,266 finished; contractors); roof deck (5,264 filed, 3,106 finished; contractors); pergola or trellis (645 filed, 372 finished; contractors). Other types: 613,041 permits. All permits in San Francisco

Every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.