How long do pergola or trellis permits take in San Francisco?

In San Francisco, of the 24 pergola or trellis permits filed from October 2025 through September 2026 that have been issued, half were issued within 11 days, down from 17 days a year earlier. Of the 21 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 222 days of being issued, down from 225 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long pergola or trellis permits take in San FranciscoMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005006002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/san-francisco/pergola · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202624 issued1127 issued17
Permit issued to final sign-offOctober 2023 through September 202421 finished22219 finished225

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q314575620too recent
2026-Q2106325640too recent
2026-Q15310too recent
2025-Q411101112653023160too recent
2025-Q375812430too recent
2025-Q2657119720too recent
2025-Q112112010371433770too recent
2024-Q4663414220too recent
2024-Q386387251022420yes
2024-Q24330yes
2024-Q114101226792223700yes
2023-Q46440yes
2023-Q33321yes
2023-Q21168042424yes
2023-Q1101012255102354340yes
2022-Q4873212052946502yes
2022-Q3874527665166261yes
2022-Q25431yes
2022-Q15441yes
2021-Q4872038561825482yes
2021-Q35212yes
2021-Q26324yes
2021-Q15431yes
2020-Q43330yes
2020-Q31101yes
2020-Q21000yes
2020-Q13221yes
2019-Q47422yes
2019-Q34422yes
2019-Q21095967651435305yes
2019-Q11292538463506863yes
2018-Q4653111231yes
2018-Q34440yes
2018-Q22220yes
2018-Q11052028041yes
2017-Q43220yes
2017-Q3771114916587861yes
2017-Q25526843723yes
2017-Q13330yes
2016-Q465218032yes
2016-Q355205722yes
2016-Q23320yes
2016-Q155127414yes
2015-Q46610742823yes
2015-Q39710517952246273yes
2015-Q297031054176652yes
2015-Q175014041yes
2014-Q4656215023yes
2014-Q34330yes
2014-Q2109210871333941yes
2014-Q1652521922yes
2013-Q4655611442yes
2013-Q31010027771304882yes
2013-Q25551441yes
2013-Q13321yes
2012-Q4657125941yes
2012-Q3556414941yes
2012-Q23220yes
2012-Q1867141965712,4481yes
2011-Q47723516727261yes
2011-Q377114961663100yes
2011-Q255104131yes
2011-Q12220yes
2010-Q4871356502581yes
2010-Q3651928232yes
2010-Q28834961563141yes
2010-Q166411240yes
2009-Q477729653193532yes
2009-Q3551430440yes
2009-Q26514626141yes
2009-Q13201yes
2008-Q45422yes
2008-Q377424071405530yes
2008-Q21185811533yes
2008-Q11081117244yes
2007-Q41111119472415642yes
2007-Q3664217841yes
2007-Q21010020641yes
2007-Q199030952304441yes
2006-Q43320yes
2006-Q398027751782682yes
2006-Q23330yes
2006-Q1883431040yes
2005-Q46601062365980yes
2005-Q34440yes
2005-Q24431yes
2005-Q13320yes
2004-Q44440yes
2004-Q355021221yes
2004-Q255021530yes
2004-Q11100yes
2003-Q43321yes
2003-Q34421yes
2003-Q25504013yes
2003-Q12220yes
2002-Q466010451132740yes
2002-Q3990071442901yes
2002-Q21110yes
2002-Q13200yes
2001-Q4770146992590yes
2001-Q33320yes
2001-Q25504120yes
2001-Q14322yes
2000-Q44440yes
2000-Q3651814320yes
2000-Q2552315730yes
2000-Q13200yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

107 of the 645 pergola or trellis permits filed since 2000 (17%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco

Shown apart, with their own page here: bathroom remodel (104,357 filed, 75,687 finished; contractors); kitchen remodel (88,742 filed, 63,705 finished; contractors); stairs (42,896 filed, 29,067 finished; contractors); deck (24,218 filed, 16,266 finished; contractors); roof deck (5,264 filed, 3,106 finished; contractors); pergola or trellis (645 filed, 372 finished; contractors). Other types: 613,041 permits. All permits in San Francisco

Every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.