How long do stairs permits take in San Francisco's Noe Valley neighborhood?

In the Noe Valley neighborhood of San Francisco, of the 57 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, down from 17 days a year earlier. Of the 48 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 130 days of being issued, down from 214 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's Noe ValleyneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/noe-valley/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202657 issued065 issued17
Permit issued to final sign-offOctober 2023 through September 202448 finished13040 finished214

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q315702410too recent
2026-Q2141079830too recent
2026-Q1242201714361340too recent
2025-Q4191831638962150too recent
2025-Q318181924782223020too recent
2025-Q2181714116101232580too recent
2025-Q1191618224101922970too recent
2024-Q416143214883544550too recent
2024-Q322212103151043960yes
2024-Q2871656782480yes
2024-Q1171721189151825460yes
2023-Q4201778302122434090yes
2023-Q3181802339782465yes
2023-Q2992541171273330yes
2023-Q1161524119112344393yes
2022-Q4191854860133387432yes
2022-Q3181514357123077584yes
2022-Q2232118427143577385yes
2022-Q1181652336112325123yes
2021-Q41613152647104229182yes
2021-Q3212094639153108804yes
2021-Q2171625095793286955yes
2021-Q1201676326122229664yes
2020-Q4282589335222151,0463yes
2020-Q31813724149578024yes
2020-Q28891976322062yes
2020-Q1231721570134946344yes
2019-Q42322113480133259627yes
2019-Q3272626780174188716yes
2019-Q2211812684134355664yes
2019-Q1161570493113978023yes
2018-Q4231978557144541,4306yes
2018-Q323212253171835215yes
2018-Q2262520728202125393yes
2018-Q1181740469133725734yes
2017-Q4242318436173009045yes
2017-Q3252310165172471,0736yes
2017-Q220162292162798220yes
2017-Q1181712188163166901yes
2016-Q4221921258142476775yes
2016-Q3171754908123101,3714yes
2016-Q232304399252021,2991yes
2016-Q1181873481164511,1341yes
2015-Q424224355181521,0943yes
2015-Q3161628486113025402yes
2015-Q2211963281143841,0443yes
2015-Q1302811343231768023yes
2014-Q4343384343263541,2766yes
2014-Q327277280163188828yes
2014-Q229275478161465905yes
2014-Q1272618381191555505yes
2013-Q4333013368262067294yes
2013-Q3353322363261441,3582yes
2013-Q217166346151767941yes
2013-Q1222216305171286944yes
2012-Q418184308161914742yes
2012-Q3292848023983614yes
2012-Q227244209201804303yes
2012-Q134326249262005095yes
2011-Q421212431720865521yes
2011-Q321204257161153224yes
2011-Q231311311272736373yes
2011-Q12724281231504131yes
2010-Q43230427223726865yes
2010-Q333313118261186464yes
2010-Q242402192351304341yes
2010-Q119168140152083931yes
2009-Q426264292211473752yes
2009-Q3181706815846061yes
2009-Q232305292262273541yes
2009-Q12826138211133582yes
2008-Q433302166192265266yes
2008-Q334320155241054704yes
2008-Q238361143281513823yes
2008-Q133311105231316323yes
2007-Q43731054221764714yes
2007-Q329270127131672946yes
2007-Q236340121201152515yes
2007-Q123220114161323242yes
2006-Q436340249231354215yes
2006-Q335330281221585173yes
2006-Q217170448102045182yes
2006-Q12828017021902902yes
2005-Q429270396171325133yes
2005-Q3353309623925225yes
2005-Q239390437218841110yes
2005-Q123210255121183104yes
2004-Q419170387131222942yes
2004-Q33635036124742998yes
2004-Q226260262181174094yes
2004-Q12524023513852873yes
2003-Q432320148231112284yes
2003-Q32424014810561709yes
2003-Q23434054251162256yes
2003-Q13131019019492287yes
2002-Q4242304714822604yes
2002-Q34443021129633125yes
2002-Q237330191201042403yes
2002-Q1393607525862650yes
2001-Q42423021012901571yes
2001-Q34746010633463740yes
2001-Q23330018615752711yes
2001-Q12019082101243181yes
2000-Q423220100131613020yes
2000-Q327230162171573150yes
2000-Q24340050311525301yes
2000-Q125240223121585620yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

323 of the 2,707 stairs permits filed since 2000 (12%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Noe Valley neighborhood

Shown apart, with their own page here: bathroom remodel (4,669 filed, 3,402 finished; contractors); kitchen remodel (3,842 filed, 2,770 finished; contractors); stairs (2,707 filed, 1,804 finished; contractors); deck (1,767 filed, 1,161 finished; contractors); roof deck (405 filed, 239 finished; contractors). Other types: 22,798 permits. All permits in San Francisco's Noe Valley neighborhood

Nearby neighborhoods

Glen Park, Twin Peaks, Castro/Upper Market; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.