How long do kitchen remodel permits take in San Francisco's Nob Hill neighborhood?

In the Nob Hill neighborhood of San Francisco, of the 107 kitchen remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, up from 0 days a year earlier. Of the 67 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 123 days of being issued, down from 151 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long kitchen remodel permits take in San Francisco's NobHill neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/nob-hill/kitchen · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026107 issued1101 issued0
Permit issued to final sign-offOctober 2023 through September 202467 finished12396 finished151

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 176 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q326241520too recent
2026-Q2353222120781130too recent
2026-Q13028163141161630too recent
2025-Q42323061171452020too recent
2025-Q33129021181483140too recent
2025-Q23636114321472520too recent
2025-Q11818012111073260too recent
2024-Q4181802161282530too recent
2024-Q3161606141402760yes
2024-Q22121040161352960yes
2024-Q1232301217981900yes
2023-Q42323032201645190yes
2023-Q32623010201102934yes
2023-Q23535098281223125yes
2023-Q12726031202016114yes
2022-Q43634137282164594yes
2022-Q33737033301624406yes
2022-Q23938228291784409yes
2022-Q15958126511393576yes
2021-Q44443026371692585yes
2021-Q342400542916948710yes
2021-Q272710635616840614yes
2021-Q1676711335518433811yes
2020-Q4545101113616637113yes
2020-Q362570313422038622yes
2020-Q223175161121624184yes
2020-Q160570154519122610yes
2019-Q47875369652243489yes
2019-Q357571824213541213yes
2019-Q262491653315775817yes
2019-Q158551433913630613yes
2018-Q44437041301622485yes
2018-Q346460463215427211yes
2018-Q244420663111825311yes
2018-Q166610374412831217yes
2017-Q45251087371744608yes
2017-Q35755181421926887yes
2017-Q258550664012663812yes
2017-Q141410913013041810yes
2016-Q4504601163115831210yes
2016-Q34646240331442979yes
2016-Q255540443916946112yes
2016-Q13834045281173865yes
2015-Q460591574515937611yes
2015-Q359580344614654912yes
2015-Q25957021461463918yes
2015-Q160595624215032415yes
2014-Q44039467301143086yes
2014-Q357560143814632017yes
2014-Q26159016461438739yes
2014-Q160600114613138312yes
2013-Q44545026351594226yes
2013-Q3575202639833269yes
2013-Q247430222419742813yes
2013-Q1474506401343574yes
2012-Q448461403018248812yes
2012-Q3444406351134019yes
2012-Q2414007281334576yes
2012-Q1343203261783674yes
2011-Q428280721793244yes
2011-Q33837013311223142yes
2011-Q2262607221002761yes
2011-Q1292901127986130yes
2010-Q429260418982834yes
2010-Q3282502181042214yes
2010-Q2272602221263635yes
2010-Q11918045161343762yes
2009-Q42020012162385024yes
2009-Q3191806141043022yes
2009-Q22524022221666411yes
2009-Q11716049762393yes
2008-Q4303009211685690yes
2008-Q3444301291063254yes
2008-Q2524900271583694yes
2008-Q1626001351492267yes
2007-Q4404000231372685yes
2007-Q34645002518434210yes
2007-Q25353003414626110yes
2007-Q1605802331936669yes
2006-Q4585701341504136yes
2006-Q3454500151572459yes
2006-Q2313100111063018yes
2006-Q1262600151653195yes
2005-Q4353500182073583yes
2005-Q3353400191572924yes
2005-Q2222100122043862yes
2005-Q1232300161202804yes
2004-Q4171705101262954yes
2004-Q3242400111062085yes
2004-Q2222200141342622yes
2004-Q1151500101142942yes
2003-Q413130091112260yes
2003-Q3252300102002488yes
2003-Q2181800142013501yes
2003-Q116160249881131yes
2002-Q422220112121622813yes
2002-Q312110081843280yes
2002-Q2141400121232421yes
2002-Q11414056101502821yes
2001-Q411100051352371yes
2001-Q37701530yes
2001-Q21515009774110yes
2001-Q114140081202360yes
2000-Q4161600101722590yes
2000-Q3252508141363630yes
2000-Q2212000141443310yes
2000-Q1242400141745520yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

600 of the 3,967 kitchen remodel permits filed since 2000 (15%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Nob Hill neighborhood

Shown apart, with their own page here: kitchen remodel (3,967 filed, 2,708 finished; contractors); bathroom remodel (3,903 filed, 2,669 finished; contractors); stairs (623 filed, 413 finished; contractors); deck (165 filed, 107 finished; contractors); roof deck (134 filed, 76 finished; contractors). Other types: 16,235 permits. All permits in San Francisco's Nob Hill neighborhood

Nearby neighborhoods

Tenderloin, Chinatown, Russian Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.