How long do bathroom remodel permits take in San Francisco's Nob Hill neighborhood?

In the Nob Hill neighborhood of San Francisco, of the 116 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 65 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 158 days of being issued, down from 162 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco's NobHill neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002502017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/nob-hill/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026116 issued0104 issued0
Permit issued to final sign-offOctober 2023 through September 202465 finished158103 finished162

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q325251520too recent
2026-Q2343224217811170too recent
2026-Q1282703415891600too recent
2025-Q43232064231401730too recent
2025-Q33332017211053700too recent
2025-Q23030223271522980too recent
2025-Q12019055121463540too recent
2024-Q4242303191442670too recent
2024-Q3202009171603250yes
2024-Q22323018181503820yes
2024-Q1171706121102360yes
2023-Q4222108181825590yes
2023-Q32725025201224595yes
2023-Q24340067331313075yes
2023-Q13029015211985946yes
2022-Q43838246292024546yes
2022-Q34139031341594405yes
2022-Q23535233291784636yes
2022-Q15755126491463586yes
2021-Q44947025411673586yes
2021-Q33737155331694812yes
2021-Q274730555716344915yes
2021-Q1737221395619242615yes
2020-Q4615401123818763115yes
2020-Q362560403218037322yes
2020-Q224184159131904104yes
2020-Q156520323919622711yes
2019-Q482791686323036513yes
2019-Q347470473613841110yes
2019-Q264520703716771518yes
2019-Q160580424414529611yes
2018-Q450451753516347010yes
2018-Q350491683415840211yes
2018-Q249471683712029710yes
2018-Q168620684217837619yes
2017-Q46462087421694689yes
2017-Q35451396401847238yes
2017-Q256530973720566214yes
2017-Q14645093341294178yes
2016-Q454490114371553108yes
2016-Q354522213514427112yes
2016-Q24847030371444147yes
2016-Q14034039261173287yes
2015-Q451490493716441910yes
2015-Q34948037391405379yes
2015-Q26058029481284228yes
2015-Q154531633716038314yes
2014-Q4454411117331455477yes
2014-Q352500233214023716yes
2014-Q25656034431379738yes
2014-Q155520143614336014yes
2013-Q4444307331334377yes
2013-Q3585302642963509yes
2013-Q268630214613838111yes
2013-Q1444206341563467yes
2012-Q451490703316864011yes
2012-Q346460143515943711yes
2012-Q2312905221445446yes
2012-Q1313106211923646yes
2011-Q4313101224883155yes
2011-Q34139025301172884yes
2011-Q225250621822372yes
2011-Q12121013191686490yes
2010-Q4252207171403224yes
2010-Q3272508191443983yes
2010-Q2222108191273823yes
2010-Q12121054171474203yes
2009-Q4151507131982942yes
2009-Q32727027241543021yes
2009-Q224240140211676542yes
2009-Q112120181693621yes
2008-Q4282800191614190yes
2008-Q3393800271283262yes
2008-Q2534900271583822yes
2008-Q1676405351652547yes
2007-Q4515101281513657yes
2007-Q35655012916339010yes
2007-Q26262013615428013yes
2007-Q1615902321506669yes
2006-Q4494801301504332yes
2006-Q3414100161452428yes
2006-Q223230091743144yes
2006-Q1202000131753255yes
2005-Q4272700142045074yes
2005-Q3353500201662574yes
2005-Q215150091773561yes
2005-Q1171700141483131yes
2004-Q4151507131542772yes
2004-Q318180091444735yes
2004-Q2202000131402661yes
2004-Q110100071792660yes
2003-Q4121203271112190yes
2003-Q314130071813143yes
2003-Q2181800121423433yes
2003-Q19901451272201yes
2002-Q41717054111522241yes
2002-Q3161500101572521yes
2002-Q2990061662580yes
2002-Q19802151562050yes
2001-Q4770051133600yes
2001-Q310100440yes
2001-Q2171700131332710yes
2001-Q19905371532700yes
2000-Q413130181724410yes
2000-Q313130082211,1920yes
2000-Q218180091042500yes
2000-Q117170081161780yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

584 of the 3,903 bathroom remodel permits filed since 2000 (15%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Nob Hill neighborhood

Shown apart, with their own page here: kitchen remodel (3,967 filed, 2,708 finished; contractors); bathroom remodel (3,903 filed, 2,669 finished; contractors); stairs (623 filed, 413 finished; contractors); deck (165 filed, 107 finished; contractors); roof deck (134 filed, 76 finished; contractors). Other types: 16,235 permits. All permits in San Francisco's Nob Hill neighborhood

Nearby neighborhoods

Tenderloin, Chinatown, Russian Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.