Permit GraphShortlistSan Francisco building permits since 2000

How long do bathroom remodel permits take in San Francisco's Inner Sunset neighborhood?

In the Inner Sunset neighborhood of San Francisco, of the 173 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 109 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 215 days of being issued, down from 266 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sInner Sunset neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/inner-sunset/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026173 issued0142 issued0
Permit issued to final sign-offOctober 2023 through September 2024109 finished215106 finished266

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q3635201930too recent
2026-Q2454028712681370too recent
2026-Q13837027231382130too recent
2025-Q44844028281182600too recent
2025-Q3353407222902310too recent
2025-Q23131062241603220too recent
2025-Q14441265341343570too recent
2024-Q43836041271655820too recent
2024-Q340361114262113960yes
2024-Q23432587222024580yes
2024-Q13230151271825510yes
2023-Q442407232342484850yes
2023-Q339381105281864707yes
2023-Q234324125273295413yes
2023-Q1282611212182035566yes
2022-Q443390169332805064yes
2022-Q3434317355343067076yes
2022-Q237337130261805045yes
2022-Q142391109322466497yes
2021-Q44843042402065262yes
2021-Q34138044282725139yes
2021-Q250500109411577776yes
2021-Q1524903303220052016yes
2020-Q4433737230322244848yes
2020-Q3363234290242669855yes
2020-Q2121242091614973yes
2020-Q1282312251183007336yes
2019-Q438325545272498726yes
2019-Q34239595302315798yes
2019-Q24139088291515429yes
2019-Q144446138382857683yes
2018-Q435346130292757903yes
2018-Q33833345282265906yes
2018-Q2575364593724373611yes
2018-Q146432242351898087yes
2017-Q455547280472265804yes
2017-Q359590212482827866yes
2017-Q255504393432259146yes
2017-Q13430294221805197yes
2016-Q438384322312035155yes
2016-Q350497467462469263yes
2016-Q2575442444415459410yes
2016-Q141382583342428903yes
2015-Q437373160322145174yes
2015-Q366626326512461,0378yes
2015-Q255501215471526854yes
2015-Q14140271361745034yes
2014-Q430280285202407365yes
2014-Q350502120412279726yes
2014-Q24242040351326163yes
2014-Q14442035361173955yes
2013-Q452511135421275238yes
2013-Q36159027461103489yes
2013-Q26464011511613585yes
2013-Q13939013311074468yes
2012-Q445451118391123273yes
2012-Q33735273311835121yes
2012-Q23231046291345292yes
2012-Q14343116401183493yes
2011-Q44443024311484146yes
2011-Q34241137381344012yes
2011-Q23431034281273151yes
2011-Q12424123211573022yes
2010-Q43837075361728980yes
2010-Q32929196261505221yes
2010-Q23333041261253734yes
2010-Q13736012291374833yes
2009-Q42828240251693591yes
2009-Q33433123281403310yes
2009-Q22221127162135121yes
2009-Q124220240201813622yes
2008-Q426243261222065310yes
2008-Q346440213371684843yes
2008-Q24846078361443503yes
2008-Q13935033241703448yes
2007-Q432290185192076078yes
2007-Q34140071241945198yes
2007-Q2363500231823827yes
2007-Q148460155312274235yes
2006-Q4313000221673892yes
2006-Q333320330241863393yes
2006-Q237370209271734663yes
2006-Q1313100251532964yes
2005-Q4252400211823143yes
2005-Q33535078251353294yes
2005-Q2282700201743475yes
2005-Q1353500251352658yes
2004-Q4353401901921657310yes
2004-Q3252400171713283yes
2004-Q2181700121523183yes
2004-Q12120049132034933yes
2003-Q428280429211393002yes
2003-Q324240166191422733yes
2003-Q2222100191483311yes
2003-Q12020025161063323yes
2002-Q424240118191034215yes
2002-Q317170167132034913yes
2002-Q220200357101062544yes
2002-Q125250138141503121yes
2001-Q4121108371502530yes
2001-Q3111103882984801yes
2001-Q21210011571417880yes
2001-Q11717024131171710yes
2000-Q42524059161202400yes
2000-Q32118033121404910yes
2000-Q223210204131473420yes
2000-Q124220112121915020yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

407 of the 3,920 bathroom remodel permits filed since 2000 (10%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Inner Sunset neighborhood

Shown apart, with their own page here: bathroom remodel (3,920 filed, 2,888 finished; contractors); kitchen remodel (3,224 filed, 2,313 finished; contractors); stairs (1,621 filed, 1,088 finished; contractors); deck (1,328 filed, 890 finished; contractors); roof deck (157 filed, 91 finished; contractors). Other types: 17,714 permits. All permits in San Francisco's Inner Sunset neighborhood

Nearby neighborhoods

Golden Gate Park, Twin Peaks, Haight Ashbury; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.