Shawn M Anderson
- Listed as
- architect, authorized agent-others, designer, engineer
- Firm
- Msa Architecture+Design
- Based in
- Oakland
- On San Francisco permits
- Apr 2001 to Apr 2026
112 permits since 2000 (architect on 104 permits, engineer on 4 permits, designer on 3 permits, authorized agent-others on 1 permit): 69 completed, 8 in progress, 15 never finaled, 20 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 112.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 23, 2026 | Completed final sign-off Jul 2026 | 201 Spear St | Hathaway Dinwiddie Co. | 13th fl - ti of (e) space - relocate (e) pre-fabricated phone booths and install seismic strappingDetails
13th fl - ti of (e) space - relocate (e) pre-fabricated phone booths and install seismic strapping | $20,000 |
| Dec 10, 2025 | Completed final sign-off Dec 2025 | 201 Spear St | Novo Construction Inc | revision to pa # 202509104944: to eliminate scope of work on 13th fl. addition of the 3 phone booth on the 5th fl. provide seismic strapping.Details
revision to pa # 202509104944: to eliminate scope of work on 13th fl. addition of the 3 phone booth on the 5th fl. provide seismic strapping. | $1,500 |
| Dec 5, 2025 | In progress filed Dec 2025, not yet issued | 6100 Geary Bl | voluntary seismic upgrade of (e) retail banking space,requiring full removal & reconstruction of (e) ti conditions, including mep, (e) tenant to remain, no change in use, no change in building area.Details
voluntary seismic upgrade of (e) retail banking space,requiring full removal & reconstruction of (e) ti conditions, including mep, (e) tenant to remain, no change in use, no change in building area. | $2,000,000 | |
| Oct 7, 2025 | Completed final sign-off Dec 2025 | 44 Montgomery St | 2nd, 3rd, 4th, 17th, 21st & 22nd floor - interior ti relocate (e) pre-frabricated nstall ismic trapping. all booths less than 48" apart shall have sprinklers . re-install pre-fabricated phone boothsDetails
2nd, 3rd, 4th, 17th, 21st & 22nd floor - interior ti relocate (e) pre-frabricated nstall ismic trapping. all booths less than 48" apart shall have sprinklers . re-install pre-fabricated phone booths | $100,000 | |
| Sep 10, 2025 | Completed final sign-off Dec 2025 | 201 Spear St | Novo Construction Inc | t.i of (e) space. relocate (e) pre-fabricated phone booths. install strapping. all booth less than 48" apart shall have sprinklers, re-install pre-fabricate phone booth for floor 4,5,6,13 only.Details
t.i of (e) space. relocate (e) pre-fabricated phone booths. install strapping. all booth less than 48" apart shall have sprinklers, re-install pre-fabricate phone booth for floor 4,5,6,13 only. | $62,500 |
| Aug 18, 2025 | In progress filed Aug 2025, not yet issued | 415 Mission St | 36/fl:tenant improvement of (e) space.no exterior work conference room , new storefront and dodor. no change of use. executive office new door/hardware demo of millwork and shelving interior finished. install millwork with acess door,signage around (e) electrical panel. install hinged acoustic andDetails
36/fl:tenant improvement of (e) space.no exterior work conference room , new storefront and dodor. no change of use. executive office new door/hardware demo of millwork and shelving interior finished. install millwork with acess door,signage around (e) electrical panel. install hinged acoustic and | $75,000 | |
| Jul 16, 2025 | In progress issued Jul 2025 | 500 Treat Av | Brothers Energy Incorporated | tenant improvement of an existing space. work to include to replace roof top hvac. all exterior work only.Details
tenant improvement of an existing space. work to include to replace roof top hvac. all exterior work only. | $45,000 |
| May 28, 2025 | Completed final sign-off Jan 2026 | 1 California St | Clune Construction Company L P | deferred submittal for permit 2024-0611-4142. revision to approved permit 2025-0206-9815 to show head detail changes and curb shown around the building.Details
deferred submittal for permit 2024-0611-4142. revision to approved permit 2025-0206-9815 to show head detail changes and curb shown around the building. | |
| Apr 4, 2025 | In progress filed Apr 2025, not yet issued | 1 California St | revision to pa 2024-0611-4142 added scope to include repair of damaged existing shaftwall per inspector commentsDetails
revision to pa 2024-0611-4142 added scope to include repair of damaged existing shaftwall per inspector comments | $2,500 | |
| Feb 27, 2025 | In progress issued May 2025 | 1 California St | Clune Construction Company L P | deferred submittal of permit # 202406114142: replacement of the exterior curtainwall system.Details
deferred submittal of permit # 202406114142: replacement of the exterior curtainwall system. | $750,000 |
| Dec 6, 2024 | Completed final sign-off Jan 2026 | 1 California St | Clune Construction Company L P | revision to permit 202406114142 revised restroom layout on ground and second floors. additional floor cores for low voltage stub-upsDetails
revision to permit 202406114142 revised restroom layout on ground and second floors. additional floor cores for low voltage stub-ups | $75,000 |
| Oct 16, 2024 | In progress issued Mar 2025 | 600 California St | Dome Construction Corp | 2/f & 3/f: relocate (e) pre-fabricated telephone booths. install seismic strapping.Details
2/f & 3/f: relocate (e) pre-fabricated telephone booths. install seismic strapping. | $40,000 |
| Oct 9, 2024 | Completed final sign-off Oct 2025 | 2025 Van Ness Av | Clune Construction Company L P | structural revision to 202311130657: revision to architectural equipment, lighting, revising demo work. revision to structural framing of roof unit, show new stepped concrete, remove detail where new footing on north wall (new footing is built under wall). revise shoring post due to damaged sill plDetails
structural revision to 202311130657: revision to architectural equipment, lighting, revising demo work. revision to structural framing of roof unit, show new stepped concrete, remove detail where new footing on north wall (new footing is built under wall). revise shoring post due to damaged sill pl | |
| Aug 7, 2024 | In progress issued Oct 2024 | 150 Stockton St | Trainor Commercial Construction Inc. | 2/f: ti for (e) retail space, scope of work includes millwork, light mechanical work, ceiling lighting is (e) to remain. fitting rooms and cash wrap are (e) to remain. light partition (demo) work. no change in use, occupancy, or zoning. (905 sf total)Details
2/f: ti for (e) retail space, scope of work includes millwork, light mechanical work, ceiling lighting is (e) to remain. fitting rooms and cash wrap are (e) to remain. light partition (demo) work. no change in use, occupancy, or zoning. (905 sf total) | $135,800 |
| Apr 9, 2024 | In progress issued Jun 2024 | 150 Stockton St | Trainor Commercial Construction Inc. | interior tenant improvement of existing retail space for new vendor, work to include built in millwork, lighting and electrical. no change in use, occupancy, egress or zoning. no exterior work and no sf addition.Details
interior tenant improvement of existing retail space for new vendor, work to include built in millwork, lighting and electrical. no change in use, occupancy, egress or zoning. no exterior work and no sf addition. | $45,000 |
| Nov 30, 2023 | Completed final sign-off May 2024 | 2025 Van Ness Av | Clune Construction Company L P | demo of (e) ti, including interior non bearing partitions, suspended ceilings, mep fixtures, wall finishes. no exterior work.Details
demo of (e) ti, including interior non bearing partitions, suspended ceilings, mep fixtures, wall finishes. no exterior work. | $38,500 |
| Nov 13, 2023 | Completed final sign-off Oct 2025 | 2025 Van Ness Av | Clune Construction Company L P | tenant improvement of an existing commerical retail space, including: 1. exterior storefront and finishes 2. structural framing/bracing 3. interior non-bearing partitions 4. millwork and interior finishes 5. mep 6. civil - ada path of travel and parking complianceDetails
tenant improvement of an existing commerical retail space, including: 1. exterior storefront and finishes 2. structural framing/bracing 3. interior non-bearing partitions 4. millwork and interior finishes 5. mep 6. civil - ada path of travel and parking compliance | $3,400,000 |
| Oct 3, 2023 | Expired or cancelled withdrawn Nov 2023 | 2025 Van Ness Av | demo of (e) partitions and millwork in (e) building. no bearing wall to be removed or structural components to be modified.Details
demo of (e) partitions and millwork in (e) building. no bearing wall to be removed or structural components to be modified. | $37,500 | |
| Sep 28, 2023 | Completed final sign-off Feb 2024 | 49 Stevenson St | abate planning code violation# 2023-001179: to accurately document square footage & location of publicly accessible 2,660 sq ft open space (arcade) per motion #10162. provide seating w/in arcade, affix signage per section 138. restaurant encroach no more than 25% (up to 665 s.f.) in arcade.Details
abate planning code violation# 2023-001179: to accurately document square footage & location of publicly accessible 2,660 sq ft open space (arcade) per motion #10162. provide seating w/in arcade, affix signage per section 138. restaurant encroach no more than 25% (up to 665 s.f.) in arcade. | ||
| Sep 26, 2023 | Completed final sign-off Jun 2024 | 425 Market St | Gci, Inc | 14/f: demolition of interior non-load bearing partitions, ceiling, lighting, millwork, plumbing fixtures and flooring. construction of new non-load bearing partitions, restroom upgrades of fixtures, eqmt and interior finishes. new lighting and limited electrical. limited mechanical andDetails
14/f: demolition of interior non-load bearing partitions, ceiling, lighting, millwork, plumbing fixtures and flooring. construction of new non-load bearing partitions, restroom upgrades of fixtures, eqmt and interior finishes. new lighting and limited electrical. limited mechanical and | $918,839 |
| Mar 16, 2023 | Expired or cancelled cancelled Jan 2026 | 2 Embarcadero Center | install 8 prefab phone booths on floors 17 & 30Details
install 8 prefab phone booths on floors 17 & 30 | $21,000 | |
| Mar 10, 2023 | Completed final sign-off Jul 2023 | 425 Market St | Richlen Construction | 11th fl - demolition of interior non-load bearing partitions, ceilings, lighting millwork, plumbing, fixtures and flooring in preparation for future tenant. occupancy group to remain b business. sprinklers/life safety under separate permit. ab-017Details
11th fl - demolition of interior non-load bearing partitions, ceilings, lighting millwork, plumbing, fixtures and flooring in preparation for future tenant. occupancy group to remain b business. sprinklers/life safety under separate permit. ab-017 | $160,000 |
| Jan 3, 2023 | Expired or cancelled withdrawn Oct 2023 | 49 Stevenson St | ste 1500: ti of a flr office space to include- partial demo of partitions, suspended ceilings and flr covering, installation of new partitions, new finishes throughout, paint & flr covering, ada upgrade to restrooms.Details
ste 1500: ti of a flr office space to include- partial demo of partitions, suspended ceilings and flr covering, installation of new partitions, new finishes throughout, paint & flr covering, ada upgrade to restrooms. | ||
| Nov 16, 2022 | Never finaled issued Jan 2023, no final | 150 Stockton St | Trainor Commercial Construction Inc. | 1/flr: tenant improvement of retail space for new vendors, work to include demo and installation of partitions, finishes, loose fixtures and ceiling and lighting remodel. mech and elec work as req. no change of use, occupancy, egress, or zoning in the app. no exterior work.Details
1/flr: tenant improvement of retail space for new vendors, work to include demo and installation of partitions, finishes, loose fixtures and ceiling and lighting remodel. mech and elec work as req. no change of use, occupancy, egress, or zoning in the app. no exterior work. | $90,000 |
| Sep 28, 2022 | Never finaled issued Mar 2023, no final | 201 Spear St | Rudolph Commercial Interiors Inc, Rci | demolition of existing partitions and act ceiling for reinforcement of window washing system on roof above.Details
demolition of existing partitions and act ceiling for reinforcement of window washing system on roof above. | $245,000 |
| Sep 20, 2022 | Expired or cancelled withdrawn Nov 2022 | 150 Stockton St | 1/f: t.i. of (e) retail including floor, finishes, millwork, partitions, merchanical, electricalDetails
1/f: t.i. of (e) retail including floor, finishes, millwork, partitions, merchanical, electrical | $200,000 | |
| Sep 16, 2022 | Completed final sign-off Mar 2024 | 1712 Taraval St | abe# 202001301488 for compliance w/s.f. mandatory abe program. install ada door operator.Details
abe# 202001301488 for compliance w/s.f. mandatory abe program. install ada door operator. | $5,000 | |
| Aug 17, 2022 | Never finaled issued Sep 2022, no final | 150 Stockton St | Trainor Commercial Construction Inc. | 2/f ti of (e) retail, new vendor, work to include millwork, flooring, finishes and electrical fixtures.Details
2/f ti of (e) retail, new vendor, work to include millwork, flooring, finishes and electrical fixtures. | $150,000 |
| Mar 3, 2022 | Completed final sign-off Sep 2023 | 680 Folsom St | Novo Construction Inc | 12th fl: tenant improvement of an (e) space. removal of interior non-load bearing partitions, millwork, & flooring. new millwork, minor electrical & lighting changer, new finishes & furniture.Details
12th fl: tenant improvement of an (e) space. removal of interior non-load bearing partitions, millwork, & flooring. new millwork, minor electrical & lighting changer, new finishes & furniture. | $300,000 |
| Mar 3, 2022 | Completed final sign-off Sep 2023 | 680 Folsom St | Novo Construction Inc | 11th fl: tenant improvement of an (e) space. removal of millwork, minor electrical & lighting changer, new finishes & furniture.Details
11th fl: tenant improvement of an (e) space. removal of millwork, minor electrical & lighting changer, new finishes & furniture. | $250,000 |
| Jan 31, 2022 | Completed final sign-off Apr 2023 | 3251 20th Av | Deb Construction Llc | op190: change occupancy from restaurant to lending institution. t.i. including exterior storefront with structural columns & headers, interior non-bearing partitions, millwork, & interior finishes. mechanical, electrical power & lighting. plumbing fixtures. deferred fire & signage.Details
op190: change occupancy from restaurant to lending institution. t.i. including exterior storefront with structural columns & headers, interior non-bearing partitions, millwork, & interior finishes. mechanical, electrical power & lighting. plumbing fixtures. deferred fire & signage. | $812,000 |
| Dec 1, 2021 | Expired or cancelled withdrawn Jan 2022 | 3251 20th Av | suite# op109: change occupancy from restraurant to lending institution. t.i. including: exterior storefront w/ structural columns & headers, interior non-bearing partitions, millwork & interior finishes, electrical power & lighting, mechanical distribution, plumbing fixtures.Details
suite# op109: change occupancy from restraurant to lending institution. t.i. including: exterior storefront w/ structural columns & headers, interior non-bearing partitions, millwork & interior finishes, electrical power & lighting, mechanical distribution, plumbing fixtures. | $812,000 | |
| Nov 3, 2021 | Completed final sign-off Dec 2021 | 2117 Fillmore St | Trainor Commercial Construction Inc. | ground floor, beauty shop: new wall and floor finish, new furniture. electrical for new fixtures. walls ceiling lighting to remain existing, restrooms existing. basement no work.Details
ground floor, beauty shop: new wall and floor finish, new furniture. electrical for new fixtures. walls ceiling lighting to remain existing, restrooms existing. basement no work. | $45,000 |
| Oct 18, 2021 | Never finaled issued Oct 2021, no final | 150 Stockton St | Trainor Commercial Construction Inc. | 3/f: tenant improvement: architectural walls, doors, finishes, fixtures and ceiling/lighting remodel (e) hvac systems to remainDetails
3/f: tenant improvement: architectural walls, doors, finishes, fixtures and ceiling/lighting remodel (e) hvac systems to remain | $120,000 |
| Dec 18, 2020 | Completed final sign-off Sep 2021 | 415 Mission St | Dome Construction Corp | revision to pa #2018-0625-2845: update to the smoke control narrative per pre-application meeting confirmation.Details
revision to pa #2018-0625-2845: update to the smoke control narrative per pre-application meeting confirmation. | |
| Dec 4, 2020 | Completed final sign-off Jun 2022 | 201 Spear St | Sc Builders, Inc | 3rd fl: installation of card readers and two-way communication devices at the elevator lobby. installation of panic hardware at the exist stairs doors.Details
3rd fl: installation of card readers and two-way communication devices at the elevator lobby. installation of panic hardware at the exist stairs doors. | $5,000 |
| Dec 4, 2020 | Completed final sign-off Jun 2022 | 201 Spear St | Sc Builders, Inc | 13th fl: installation of card readers and two-way communication devices at at the 13th fl elevator lobby. installation of panic hardware at the doors of exit stairs.Details
13th fl: installation of card readers and two-way communication devices at at the 13th fl elevator lobby. installation of panic hardware at the doors of exit stairs. | $5,000 |
| Nov 13, 2020 | Expired or cancelled withdrawn Sep 2023 | 4972 Mission St | to comply with be ord 51-16 new door landing and threshold to be ada complaint to comply with accessible business entrance program.Details
to comply with be ord 51-16 new door landing and threshold to be ada complaint to comply with accessible business entrance program. | $12,000 | |
| Sep 21, 2020 | Never finaled filed Sep 2020, never issued | 425 Mission St | tjpa-ti. suite# 222/224. t.i of an (e) space. work to include office. no change of use. interior non-bearing partitions. millwork & interior finishes. mep as required. card readers. ** maher: n/a **Details
tjpa-ti. suite# 222/224. t.i of an (e) space. work to include office. no change of use. interior non-bearing partitions. millwork & interior finishes. mep as required. card readers. ** maher: n/a ** | $325,000 | |
| Jan 10, 2020 | Completed final sign-off Jan 2021 | 475 Sansome St | Dome Construction Corp | 18 & 19/f -t.i. improvement of (e) vacant office space on floors 18 & 19 new non-bearning partitions, and suspended ceilings, new millork, countertops, and fixtures, new finishes mep included n/a maherDetails
18 & 19/f -t.i. improvement of (e) vacant office space on floors 18 & 19 new non-bearning partitions, and suspended ceilings, new millork, countertops, and fixtures, new finishes mep included n/a maher | $5,000,000 |
| Jan 6, 2020 | Completed final sign-off Mar 2020 | 71 Stevenson St | Sc Builders, Inc | demolition only. non-structural no mep's for existing permit 2019-1206-8955Details
demolition only. non-structural no mep's for existing permit 2019-1206-8955 | |
| Dec 26, 2019 | Expired or cancelled cancelled Jan 2026 | 201 Spear St | Bcci Construction Company | 15/f: revision to pa #201905312147 & 201905080088. adding detail to showe new door frame attaches to ceiling.Details
15/f: revision to pa #201905312147 & 201905080088. adding detail to showe new door frame attaches to ceiling. | |
| Dec 6, 2019 | Completed final sign-off Nov 2020 | 71 Stevenson St | Sc Builders, Inc | 5th floor: t.i. of office suite spaces. install new partitions and gyp bd ceiling. install new millwork, countertops and fixtures. new finishes and installtion of light fixtures.Details
5th floor: t.i. of office suite spaces. install new partitions and gyp bd ceiling. install new millwork, countertops and fixtures. new finishes and installtion of light fixtures. | $1,000,000 |
| Dec 3, 2019 | Expired or cancelled cancelled Jan 2026 | 170 Ofarrell St | 5th fl: upgrade existing ceiling & clights. patch & repair and paint gypsum as required.Details
5th fl: upgrade existing ceiling & clights. patch & repair and paint gypsum as required. | $75,000 | |
| Nov 8, 2019 | Completed final sign-off Dec 2020 | 166 Geary St | Derry Casey Builders Inc | 13th fl: ti of an (e) business space for doctor's office & treatment rooms. interior non-bearing partitions, millwork & interior finishes. mep under separate permit.Details
13th fl: ti of an (e) business space for doctor's office & treatment rooms. interior non-bearing partitions, millwork & interior finishes. mep under separate permit. | $65,000 |
| Oct 18, 2019 | Expired or cancelled cancelled Jan 2026 | 166 Geary St | architectural interior barrier removal. upgrade (e) stair handrail from all occupied floors to 16th floor to become as compliant as possible. reference to pa #2019-0111-0177Details
architectural interior barrier removal. upgrade (e) stair handrail from all occupied floors to 16th floor to become as compliant as possible. reference to pa #2019-0111-0177 | $100,000 | |
| Jul 30, 2019 | Completed final sign-off Oct 2020 | 201 Spear St | Build Group Inc. | 4th flr. installation of interior partitions, door and celings. non-prep micro kitchen millwork and supporting equipment, (n) lighting, (n) plumbing fixturesDetails
4th flr. installation of interior partitions, door and celings. non-prep micro kitchen millwork and supporting equipment, (n) lighting, (n) plumbing fixtures | $94,500 |
| Jul 25, 2019 | Completed final sign-off Dec 2019 | 49 Stevenson St | Rudolph Commercial Interiors Inc, Rci | ti- partial demo of paritions & floor coverins, new finishes throughout and ada upgrade to restroomDetails
ti- partial demo of paritions & floor coverins, new finishes throughout and ada upgrade to restroom | $153,081 |
| Jul 16, 2019 | Completed final sign-off Jul 2020 | 71 Stevenson St | Wework Construction Llc Dba Wework Const | 6th & 7th flr - installation of: new partitions & gyp board ceiling, millwork, countertops 7 fixutres, light fixtures. new finishes throughout, paint and floor coveringDetails
6th & 7th flr - installation of: new partitions & gyp board ceiling, millwork, countertops 7 fixutres, light fixtures. new finishes throughout, paint and floor covering | $735,000 |
| Jun 25, 2019 | Completed final sign-off Oct 2019 | 71 Stevenson St | Wework Construction Llc Dba Wework Const | demo permit for 6th & 7th floors; remove non-structural partitions, remove storefront & doors, remove selected fixtures & framing, remove selected plumbing fixtures & accessories & cap. per ab-017Details
demo permit for 6th & 7th floors; remove non-structural partitions, remove storefront & doors, remove selected fixtures & framing, remove selected plumbing fixtures & accessories & cap. per ab-017 | $75,000 |
| Jun 6, 2019 | Never finaled issued Oct 2019, no final | 166 Geary St | Concord Construction Inc, Trainor Commercial Construction Inc. | 14th and 15th flrs. install (n) partitions, gyp, ceiling. (n) millwork, countertops, fixtures. (n) finishes, paint, floor covers. install card readers at elevator lobby. install light fixtures, electr equip. install plumbing equip. fire alarm, sprinklers under separate permit. emerg resp def submit.Details
14th and 15th flrs. install (n) partitions, gyp, ceiling. (n) millwork, countertops, fixtures. (n) finishes, paint, floor covers. install card readers at elevator lobby. install light fixtures, electr equip. install plumbing equip. fire alarm, sprinklers under separate permit. emerg resp def submit. | $1,320,600 |
| May 21, 2019 | Completed final sign-off Jul 2021 | 550 Kearny St | Wework Construction Llc Dba Wework Const | 3rd and 4th floors - remove selected non-load bearing partitions, ceiling & assoc framing. installation of (n) partition, gyp board ceiling, (n) millwork & appliances. (n) paint & flooring in selected areas (n) light fixtures & mep equipmentsDetails
3rd and 4th floors - remove selected non-load bearing partitions, ceiling & assoc framing. installation of (n) partition, gyp board ceiling, (n) millwork & appliances. (n) paint & flooring in selected areas (n) light fixtures & mep equipments | $2,774,532 |
| May 7, 2019 | Completed final sign-off Dec 2019 | 180 Geary St | Rod Heisler Construction | 5th & 6th fl - remove and install selected non-load bearing partitions. remove selected t-bar ceiling. new casework @ pantry & appliances. new finishes/refresh throughout. new light fixture & mech equipment. remove toilet partition for ada upgrade. shifting plumbing fixture (urinal) to comply w/codeDetails
5th & 6th fl - remove and install selected non-load bearing partitions. remove selected t-bar ceiling. new casework @ pantry & appliances. new finishes/refresh throughout. new light fixture & mech equipment. remove toilet partition for ada upgrade. shifting plumbing fixture (urinal) to comply w/code | $1,200,000 |
| Apr 19, 2019 | Completed final sign-off Oct 2019 | 201 Spear St | Dome Construction Corp | revision to pa #201903296594. update room names to correct name. replacement of (e) sliding door to 36" swing door. fls: 4,5,6Details
revision to pa #201903296594. update room names to correct name. replacement of (e) sliding door to 36" swing door. fls: 4,5,6 | |
| Mar 29, 2019 | Completed final sign-off Oct 2019 | 201 Spear St | Dome Construction Corp | replacement of interior office partitions and doors. replacement of gyp walls and doors/frames. addition of card readers, new finishes - carpet & paint. no change in basic room layout and uses. maher naDetails
replacement of interior office partitions and doors. replacement of gyp walls and doors/frames. addition of card readers, new finishes - carpet & paint. no change in basic room layout and uses. maher na | $175,000 |
| Mar 12, 2019 | Completed final sign-off Jun 2019 | 2280 Market St | Premier Structures Inc | revision to bpa 2018-0626-3037 to clarify that the building is and will remain as b occupancy class with 49 or lessDetails
revision to bpa 2018-0626-3037 to clarify that the building is and will remain as b occupancy class with 49 or less | |
| Feb 11, 2019 | Never finaled issued Feb 2019, no final | 201 Spear St | Bcci Construction Company | improvement to the elevator lobby, common areas, and restroomDetails
improvement to the elevator lobby, common areas, and restroom | $442,000 |
| Dec 19, 2018 | Completed final sign-off Sep 2019 | 44 Montgomery St | Dome Construction Corp | 17th floor: remove elevator lobby doors and hardware. install new fire rated elevator lobby doors and hardware. all interior work.Details
17th floor: remove elevator lobby doors and hardware. install new fire rated elevator lobby doors and hardware. all interior work. | $50,000 |
| Dec 3, 2018 | Completed final sign-off Oct 2019 | 201 Spear St | Northern Sun Associates | 1st fl, ste 2f - existing restaurant ti.remove selected non-bearing partitions; remove selected ceiling & associated framing; install in-line grease exhaust fan & make-up air unit; install vapor exhaust system; install grease interceptor. to obtain demo & mep permit.Details
1st fl, ste 2f - existing restaurant ti.remove selected non-bearing partitions; remove selected ceiling & associated framing; install in-line grease exhaust fan & make-up air unit; install vapor exhaust system; install grease interceptor. to obtain demo & mep permit. | $150,000 |
| Aug 13, 2018 | Completed final sign-off Nov 2018 | 44 Montgomery St | Dome Construction Corp | 17th fl - revision to pa 2018-0502-7950 installation of light fixtures and other electric equipment. installation of plumbing equipment. revise toilet and urinal layout. revise power plan and data. electrical deferred under separate permit.Details
17th fl - revision to pa 2018-0502-7950 installation of light fixtures and other electric equipment. installation of plumbing equipment. revise toilet and urinal layout. revise power plan and data. electrical deferred under separate permit. | $50,000 |
| Aug 2, 2018 | Never finaled issued Sep 2018, no final | 845 Market St | Swinerton Builders | 1st fl. addition of 3 offices, open work area, storage room, assembly area & conference room. new exhaust fan per smoke controll, exit sign and emergency lighting. assembly space in work area with 15 occupant load has 2 levels but considered same room. sprinklers n fire alarm separate permit.Details
1st fl. addition of 3 offices, open work area, storage room, assembly area & conference room. new exhaust fan per smoke controll, exit sign and emergency lighting. assembly space in work area with 15 occupant load has 2 levels but considered same room. sprinklers n fire alarm separate permit. | $210,000 |
| Jul 5, 2018 | Completed final sign-off Dec 2018 | 44 Montgomery St | Dome Construction Corp | revision to pa 2017-1005-0542 installation of new non-bearing partitions, gyp bd, ceilings, millwork, countertops, fixture and finishes throughout. addition of card readers @ enter/lounge doors and other locations. 2 way communication under separate permit. separate permit for mep, fire/life safetyDetails
revision to pa 2017-1005-0542 installation of new non-bearing partitions, gyp bd, ceilings, millwork, countertops, fixture and finishes throughout. addition of card readers @ enter/lounge doors and other locations. 2 way communication under separate permit. separate permit for mep, fire/life safety | $200,000 |
| Jun 26, 2018 | Completed final sign-off Jun 2019 | 2280 Market St | Premier Structures Inc | tenant improvement ot an existing retail space for a new specialty fitness sutdio, work to include: gond fl, interior non-bearing partitions, millwork & interior finishes, electrical, plumbing & hvac, accoustical treatment for studio space. new fuel/juice barDetails
tenant improvement ot an existing retail space for a new specialty fitness sutdio, work to include: gond fl, interior non-bearing partitions, millwork & interior finishes, electrical, plumbing & hvac, accoustical treatment for studio space. new fuel/juice bar | $150,000 |
| Jun 12, 2018 | Completed final sign-off Jul 2021 | 415 Mission St | Dome Construction Corp | rev to #201805088538 (36th fl), #201805088541 (37th fl), #201804247247 & #201801088085 (38th fl)= demo portion of 37th fl to connect with 38th fl to create 3 story atrium, installation of tiered assembly seating on 36th fl to 37th fl. updated smoke control narrative dated 7/26/18 for fire shutters.Details
rev to #201805088538 (36th fl), #201805088541 (37th fl), #201804247247 & #201801088085 (38th fl)= demo portion of 37th fl to connect with 38th fl to create 3 story atrium, installation of tiered assembly seating on 36th fl to 37th fl. updated smoke control narrative dated 7/26/18 for fire shutters. | $1,558,000 |
| May 11, 2018 | Expired or cancelled cancelled Jan 2026 | 110 Channel | revision to existing permit #201707131746. elimiate drinking fountain and replace with bottle filling station.Details
revision to existing permit #201707131746. elimiate drinking fountain and replace with bottle filling station. | $1,000 | |
| May 9, 2018 | Never finaled issued May 2018, no final | 150 Stockton St | Trainor Commercial Construction Inc. | 3rd floor - ti within an (e) retail space, sinishes, ele, lighting, power, soffit framing maher naDetails
3rd floor - ti within an (e) retail space, sinishes, ele, lighting, power, soffit framing maher na | $45,500 |
| May 8, 2018 | Expired or cancelled expired Jul 2021 | 415 Mission St | Dome Construction Corp | revision to 201802090937. change layout to unisex restroom. sorting room and hallway. change mail room and add card readersDetails
revision to 201802090937. change layout to unisex restroom. sorting room and hallway. change mail room and add card readers | $15,600 |
| May 2, 2018 | Never finaled issued May 2018, no final | 150 Stockton St | Trainor Commercial Construction Inc. | 1st fl: interior tenant improvemnt in existing retail store, includes mechanical & electrical. maher naDetails
1st fl: interior tenant improvemnt in existing retail store, includes mechanical & electrical. maher na | $100,000 |
| Apr 11, 2018 | Completed final sign-off Mar 2019 | 600 California St | Novo Construction Inc | 19th & 20th floors - demolition of existing and installation of new office suite on 2 floors of an existing building includes: partitions, ceilings, millwork, finishes and security card readers. life safety, mep under separate permit. maher naDetails
19th & 20th floors - demolition of existing and installation of new office suite on 2 floors of an existing building includes: partitions, ceilings, millwork, finishes and security card readers. life safety, mep under separate permit. maher na | $3,036,057 |
| Mar 28, 2018 | Expired or cancelled withdrawn Sep 2024 | 33 29th St | change of use. existing medical cannabis disp to cannabis retail orig appl 200505182807 (0 plan). maher n/a.Details
change of use. existing medical cannabis disp to cannabis retail orig appl 200505182807 (0 plan). maher n/a. | ||
| Mar 23, 2018 | Expired or cancelled withdrawn Sep 2024 | 4811 Geary Bl | change of use, medical cannabis dispensary to recreational cannabis dispensary. reference to permit #201507302958. **maher n/a**Details
change of use, medical cannabis dispensary to recreational cannabis dispensary. reference to permit #201507302958. **maher n/a** | ||
| Feb 21, 2018 | Completed final sign-off Jul 2018 | 44 Montgomery St | Dome Construction Corp | revision to pa #201710050540. installtion of new interconnecting stairway between 2nd & 3rd fl in an existing high ceiling space. life safety under separate permit.Details
revision to pa #201710050540. installtion of new interconnecting stairway between 2nd & 3rd fl in an existing high ceiling space. life safety under separate permit. | $25,000 |
| Feb 12, 2018 | Completed final sign-off Jul 2018 | 44 Montgomery St | Dome Construction Corp | revision to existing permit #201710050540, layout changes to walls/doors, lights and power/signal. 2nd fl. maher naDetails
revision to existing permit #201710050540, layout changes to walls/doors, lights and power/signal. 2nd fl. maher na | |
| Feb 8, 2018 | Never finaled issued Feb 2018, no final | 150 Stockton St | Trainor Commercial Construction Inc. | 4th flr - interior improvements to womens customer restroom, within (e) retail store. includes finishes, doors, ceiling and lighting maher naDetails
4th flr - interior improvements to womens customer restroom, within (e) retail store. includes finishes, doors, ceiling and lighting maher na | $32,000 |
| Jan 19, 2018 | Expired or cancelled expired Jul 2021 | 415 Mission St | Dome Construction Corp | 36/f: structural reinforcement for future tenant, maher ord 155-13 naDetails
36/f: structural reinforcement for future tenant, maher ord 155-13 na | $30,000 |
| Jan 8, 2018 | Completed final sign-off Jul 2021 | 415 Mission St | Dome Construction Corp | remove slab cut for stair (future). new opening for interconnecting stairs. interconnected stories are not open to other stories. cbc1019.3.1. maher naDetails
remove slab cut for stair (future). new opening for interconnecting stairs. interconnected stories are not open to other stories. cbc1019.3.1. maher na | $60,000 |
| Dec 21, 2017 | Completed final sign-off Jul 2021 | 415 Mission St | Dome Construction Corp | 36th fl: installation of non-bearing partitions, ceiling, millworks & fixtures. card readers at elevator lobbies. sprinkler & fire alarm on separate permits. maher naDetails
36th fl: installation of non-bearing partitions, ceiling, millworks & fixtures. card readers at elevator lobbies. sprinkler & fire alarm on separate permits. maher na | $2,762,934 |
| Dec 13, 2017 | Expired or cancelled withdrawn Feb 2018 | 415 Mission St | structural reinforcement of the 36th floor for future ti project the result will be an increase in floor live load from 65 psf to 100 psf maher naDetails
structural reinforcement of the 36th floor for future ti project the result will be an increase in floor live load from 65 psf to 100 psf maher na | $20,000 | |
| Dec 12, 2017 | Completed final sign-off Jan 2018 | 201 Spear St | Rudolph And Sletten Inc | 9th flr: revision to 201710302554 changing some exit sign placement, move card reader to inside vestible and adjusting exit egress pathway. maher naDetails
9th flr: revision to 201710302554 changing some exit sign placement, move card reader to inside vestible and adjusting exit egress pathway. maher na | |
| Dec 6, 2017 | Completed final sign-off May 2018 | 49 Stevenson St | Bcci Construction Company | 4th - full floor installation of (n) partitions and gyp bd ceiling installation of (n) millwork, countertops and fixtures, new finishes throughout. paint and floor covereings. installation of card reader at elevator lobby and other locations. fire and mep will be design build under separate permitsDetails
4th - full floor installation of (n) partitions and gyp bd ceiling installation of (n) millwork, countertops and fixtures, new finishes throughout. paint and floor covereings. installation of card reader at elevator lobby and other locations. fire and mep will be design build under separate permits | $836,745 |
| Nov 29, 2017 | Completed final sign-off Jan 2019 | 303 02nd St | install new wall, doors, floor penetrations, case work eq, furniture, wall floor finishes, ceiling, light fix, restrooms, outdoor furniture. demo ex walls, provide new mech ducts maher not reqDetails
install new wall, doors, floor penetrations, case work eq, furniture, wall floor finishes, ceiling, light fix, restrooms, outdoor furniture. demo ex walls, provide new mech ducts maher not req | $350,000 | |
| Nov 9, 2017 | Completed final sign-off Nov 2018 | 201 Spear St | Dome Construction Corp | 13th floor - revision to pa #201707242796: removal of walls & doors, relcoation of new power/signal & lighting. addition of millwork & sink. (mep #201708084144) n/a maher ordinanceDetails
13th floor - revision to pa #201707242796: removal of walls & doors, relcoation of new power/signal & lighting. addition of millwork & sink. (mep #201708084144) n/a maher ordinance | $40,000 |
| Nov 7, 2017 | Never finaled issued Nov 2017, no final | 650 California St | Bcci Construction Company | 30th floor - interior tenant improvement of an existing space. new partitions, new millwork, countertops, fixtures, m.e.p., card reader in elevator lobby. n/a maher ordinanceDetails
30th floor - interior tenant improvement of an existing space. new partitions, new millwork, countertops, fixtures, m.e.p., card reader in elevator lobby. n/a maher ordinance | $1,500,000 |
| Nov 1, 2017 | Completed final sign-off May 2019 | 455 Market St | T C B Builders Inc | suite #100 - renovation of existing unit "starbucks coffee" - remove existing & install new walls, doors, casework, furniture, finishes, ceilings & lighting. new restrooms fixtures & accessories for compliance. permit 201605036413 is to be cancelled. maher naDetails
suite #100 - renovation of existing unit "starbucks coffee" - remove existing & install new walls, doors, casework, furniture, finishes, ceilings & lighting. new restrooms fixtures & accessories for compliance. permit 201605036413 is to be cancelled. maher na | $129,245 |
| Oct 23, 2017 | Never finaled issued Nov 2017, no final | 1998 Union St | Patrick Uniacke | revision to pa #201409196889. revised lighting & equipment layout. added exhaust fan per health department.Details
revision to pa #201409196889. revised lighting & equipment layout. added exhaust fan per health department. | $1,000 |
| Oct 5, 2017 | Completed final sign-off Dec 2018 | 44 Montgomery St | Dome Construction Corp | 21st fl: installation of new non-bearing partitions, gyp bd ceilings, millwork, countertops, fxitures, paint & floor covering througout; card readers various locations. mechanical, electrical, plumbing, fire sprinklers/life safety under seperate permit. maher naDetails
21st fl: installation of new non-bearing partitions, gyp bd ceilings, millwork, countertops, fxitures, paint & floor covering througout; card readers various locations. mechanical, electrical, plumbing, fire sprinklers/life safety under seperate permit. maher na | $1,133,071 |
| Oct 5, 2017 | Completed final sign-off Jul 2018 | 44 Montgomery St | Dome Construction Corp | 2nd fl full floor ti: installation of new non-bearing partitions, gyp bd ceilings, millwork, countertops, fxitures, paint & floor covering througout; card readers at elevator lobby and other locations. mechanical, electrical, plumbing, fire/life safety, 2-way comm under seperate permit. maher naDetails
2nd fl full floor ti: installation of new non-bearing partitions, gyp bd ceilings, millwork, countertops, fxitures, paint & floor covering througout; card readers at elevator lobby and other locations. mechanical, electrical, plumbing, fire/life safety, 2-way comm under seperate permit. maher na | $1,304,026 |
| Sep 8, 2017 | Completed final sign-off Oct 2018 | 201 Spear St | Dome Construction Corp | 3rd fl: revision to bpa# 2017-0307-0829 & 2017-0427-5088. installation of 2 new interior storefront doors and convert an office to reception area.Details
3rd fl: revision to bpa# 2017-0307-0829 & 2017-0427-5088. installation of 2 new interior storefront doors and convert an office to reception area. | $6,000 |
| Aug 7, 2017 | Completed final sign-off Apr 2018 | 44 Montgomery St | Dome Construction Corp | interior improvement including walls, ceiling/lights, furniture and finishes. mechanical & electrical under a separate permitDetails
interior improvement including walls, ceiling/lights, furniture and finishes. mechanical & electrical under a separate permit | $2,266,142 |
| Jul 27, 2017 | Completed final sign-off Aug 2017 | 1400 Van Ness Av | Trainor Commercial Construction Inc. | g/f -coffee shop: upgrade existing restroom. barrier removal (ada restroom). electrical under sep. permit.Details
g/f -coffee shop: upgrade existing restroom. barrier removal (ada restroom). electrical under sep. permit. | $7,500 |
| Jul 24, 2017 | Completed final sign-off Dec 2018 | 201 Spear St | Dome Construction Corp | installation of new gyp partitions & ceilings & lights. new millwork & finishes. demo of (e) interior partitions & t-bar/grid & lights. no exterior or structural work. n/a maherDetails
installation of new gyp partitions & ceilings & lights. new millwork & finishes. demo of (e) interior partitions & t-bar/grid & lights. no exterior or structural work. n/a maher | $1,008,122 |
| Jun 7, 2017 | Completed final sign-off Jun 2018 | 655 Montgomery St | Dome Construction Corp | 6th & 7th floors - office ti installation of new partitions and gyp board ceilings; installation of new millwork, countertops and fixtures. new finishes throughout; paint and floor coverings; installation of card readers at elevator lobby and other locationsDetails
6th & 7th floors - office ti installation of new partitions and gyp board ceilings; installation of new millwork, countertops and fixtures. new finishes throughout; paint and floor coverings; installation of card readers at elevator lobby and other locations | $2,240,950 |
| Jun 7, 2017 | Completed final sign-off Jun 2018 | 655 Montgomery St | Dome Construction Corp | 5th floor - office ti installation of new partitions and gyp board ceilings; installation of new millwork, countertops and fixtures. new finishes throughout; paint and floor coverings; installation of card readers at elevator lobby and other locationsDetails
5th floor - office ti installation of new partitions and gyp board ceilings; installation of new millwork, countertops and fixtures. new finishes throughout; paint and floor coverings; installation of card readers at elevator lobby and other locations | $1,132,915 |
| May 31, 2017 | Expired or cancelled cancelled Jan 2026 | 655 Montgomery St | demolition of non-bearing partitions, ceilings, lighting and flooring in prepartion of future tenant improvementDetails
demolition of non-bearing partitions, ceilings, lighting and flooring in prepartion of future tenant improvement | $263,044 | |
| May 10, 2017 | Never finaled issued Jun 2017, no final | 50 California St | Marini Construction Inc | ground floor - install new walls, doors & casework, equipments: install new rest room; install new ceiling & lighting modify mechanical; electrical & plumbing; install new floor, ceiling, wall finishes. no exterior work. signage & fire sprinkler/alarm under separate permit. n/a for maher.Details
ground floor - install new walls, doors & casework, equipments: install new rest room; install new ceiling & lighting modify mechanical; electrical & plumbing; install new floor, ceiling, wall finishes. no exterior work. signage & fire sprinkler/alarm under separate permit. n/a for maher. | $300,000 |
| Apr 25, 2017 | Never finaled issued Jul 2017, no final | 2213 Fillmore St | Trainor Commercial Construction Inc. | non structural interior tenant improvement for cafe. new partitions, lighting, mechanical + electrical systems. new finishes & food service equipement.Details
non structural interior tenant improvement for cafe. new partitions, lighting, mechanical + electrical systems. new finishes & food service equipement. | $300,000 |
| Apr 10, 2017 | Completed final sign-off Mar 2019 | 2132 Chestnut St | Gray West Construction Inc | commercial tenant improvement to existing store, new wall, new finishes, 2 new ada restrooms, modify elec, mech, plumbing. exterior work and signage under sep permitDetails
commercial tenant improvement to existing store, new wall, new finishes, 2 new ada restrooms, modify elec, mech, plumbing. exterior work and signage under sep permit | $183,260 |
| Apr 5, 2017 | Expired or cancelled cancelled Feb 2020 | 299 Fremont St | commercial ti, new wall, equipment, furniture, finishes, 1 ada ret 4 standard rr, modify plumbing electrical, mechanical maher not reqDetails
commercial ti, new wall, equipment, furniture, finishes, 1 ada ret 4 standard rr, modify plumbing electrical, mechanical maher not req | $366,765 | |
| Mar 1, 2017 | Completed final sign-off Dec 2017 | 201 Mission St | T C B Builders Inc | ground flr: selective demo of partially vacant tenant unit (e) restrooms, interior walls and electrical panels. suspended ceiling under separate permit (until sprinkler or construction plans approved, separate). floor slab to be drilled for future plumbing connections ref const. ti pa# 201702280344Details
ground flr: selective demo of partially vacant tenant unit (e) restrooms, interior walls and electrical panels. suspended ceiling under separate permit (until sprinkler or construction plans approved, separate). floor slab to be drilled for future plumbing connections ref const. ti pa# 201702280344 | $11,778 |
| Feb 28, 2017 | Completed final sign-off Dec 2017 | 201 Mission St | T C B Builders Inc | commercial tenant improvement to existing vacant unit. includes restrooms, fixtures, furniture and equipment. maher na fire and life safety under separate permitsDetails
commercial tenant improvement to existing vacant unit. includes restrooms, fixtures, furniture and equipment. maher na fire and life safety under separate permits | $382,860 |