- Mar 2005 to Nov 2022
13 permits since 2000 (engineer on 12 permits, architect on 1 permit): 11 completed, 2 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 15, 2022 | Completed final sign-off Apr 2023 | 55 02nd St | M C S Construction Services | ste 1975 mechanical and electrical scope under office tenant improvement project reference permit 202210063900Details
ste 1975 mechanical and electrical scope under office tenant improvement project reference permit 202210063900 | $44,000 |
| Aug 31, 2016 | Completed final sign-off Sep 2017 | 2100 Webster St | Derry Casey Builders | ste. #115- provide voluntary access barriers remodel; provide accessible signs, remodel exam 4 to be accessible, lower service counters to accessible.Details
ste. #115- provide voluntary access barriers remodel; provide accessible signs, remodel exam 4 to be accessible, lower service counters to accessible. | $20,000 |
| Apr 20, 2016 | Completed final sign-off Jan 2017 | 711 Van Ness Av | 3rd fl:rev to appl.#2015-0914-6894. arch, plumbing, elec. changes. adding 4 sinks to suite 300, add elec. outlets, add data outlets, revise lighting suites 300 & 340, revise finishes. also, clarify that there is a change of use from office to clinic(ophthalmology) to original appll. 2015-0914-6894.Details
3rd fl:rev to appl.#2015-0914-6894. arch, plumbing, elec. changes. adding 4 sinks to suite 300, add elec. outlets, add data outlets, revise lighting suites 300 & 340, revise finishes. also, clarify that there is a change of use from office to clinic(ophthalmology) to original appll. 2015-0914-6894. | $80,000 | |
| Sep 16, 2015 | Never finaled issued Nov 2015, no final | 241 06th St | addition of domestic hot water return piping. n/a for maher. penetrations thru fire rated construction, see note on sheet p02Details
addition of domestic hot water return piping. n/a for maher. penetrations thru fire rated construction, see note on sheet p02 | $50,000 | |
| May 4, 2015 | Completed final sign-off Mar 2016 | 425 Market St | Source Planning And Construction Inc | level 2b- mechanical only for pa#201409226970. n/a ordinance #155-13Details
level 2b- mechanical only for pa#201409226970. n/a ordinance #155-13 | |
| Feb 5, 2015 | Completed final sign-off Jul 2015 | 100 01st St | Commercial Interior Builders Inc | 12th floor: lighting and mechanical work per title 24, work includes new lights and installing new grilles, relocate existing grilles and duct work. ref. to pa#201411262611 for architectural work. revision to arch is 2015-02128131.Details
12th floor: lighting and mechanical work per title 24, work includes new lights and installing new grilles, relocate existing grilles and duct work. ref. to pa#201411262611 for architectural work. revision to arch is 2015-02128131. | $42,000 |
| Nov 18, 2014 | Completed final sign-off Mar 2015 | 201 Spear St | Peacock Construction | 17th flr: mechanical t-24 for work done under pa #201408224521; maher n/aDetails
17th flr: mechanical t-24 for work done under pa #201408224521; maher n/a | $17,000 |
| Aug 29, 2014 | Never finaled issued Nov 2014, no final | 77 Beale St | Aire Sheet Metal, Inc. | 32nd flr: install (1) chw fc unit above ceiling, install (2) wall mounted chw (ductless) units, ductwork & diffusers; maher n/aDetails
32nd flr: install (1) chw fc unit above ceiling, install (2) wall mounted chw (ductless) units, ductwork & diffusers; maher n/a | $180,000 |
| Jun 6, 2013 | Completed final sign-off Oct 2013 | 1095 Mission St | D & S Leong Associates | add 6 gallon boiler feeder. connect existing 50 gal surge tank to boiler feeder vent. run drain from surge tank & boiler feeder to existing floor sink, add steam trap at drain of surge tank. revision to pa# 201001215124Details
add 6 gallon boiler feeder. connect existing 50 gal surge tank to boiler feeder vent. run drain from surge tank & boiler feeder to existing floor sink, add steam trap at drain of surge tank. revision to pa# 201001215124 | $5,000 |
| Jul 2, 2008 | Completed final sign-off Nov 2008 | 505 Montgomery St | Peacock Construction Inc | mechanical, install 1 new vav box and replace existing supply and return grillsDetails
mechanical, install 1 new vav box and replace existing supply and return grills | $24,000 |
| Mar 18, 2008 | Completed final sign-off Jul 2009 | 390 Clementina St | D.F.P.F Corp Dba Fine Line Construction | miscellaneous demolition. new 1st floor staff toilet room (unisex). replace (e) emergency generator on ground 200703085757Details
miscellaneous demolition. new 1st floor staff toilet room (unisex). replace (e) emergency generator on ground 200703085757 | $75,000 |
| Oct 31, 2007 | Completed final sign-off Jan 2008 | 388 Market St | Paradigm General Contractors | 9th floor-suite 960: install (2) fire smoke damper's, mandatory mechanical measuresDetails
9th floor-suite 960: install (2) fire smoke damper's, mandatory mechanical measures | $25,000 |
| Mar 28, 2005 | Completed final sign-off Dec 2005 | 100 01st St | Dome Construction Corp | oti-3, 11th floor, el, me.Details
oti-3, 11th floor, el, me. | $48,000 |