- Apr 2005 to Jul 2026
126 permits since 2000 (engineer on 94 permits, designer on 16 permits, architect on 12 permits, authorized agent-others on 4 permits): 104 completed, 2 in progress, 6 never finaled, 14 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 126.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 22, 2026 | In progress issued Jul 2026 | 2008 Lombard St | Jian's Builder Corp | unit #a: conversion of existing bedroom to a 3 fixture bath to a wet bar.Details
unit #a: conversion of existing bedroom to a 3 fixture bath to a wet bar. | $20,000 |
| May 5, 2026 | Completed final sign-off Jul 2026 | 1444 Egbert Av | Anything Is Possible Construction | to comply wiht nov#: 202651039; reverse front security door swinging to inward, remove bollards at front exterior wall. legalize of interior partitions modifications.Details
to comply wiht nov#: 202651039; reverse front security door swinging to inward, remove bollards at front exterior wall. legalize of interior partitions modifications. | $40,000 |
| May 7, 2024 | In progress issued Jun 2024 | 731 Capp St | Joe 88 Construction Co | revision to pa# 202308094084: garage- laundry stays, add (2) fixture bath. 1/f- remodel (e) bath as 3 fixture bath, combine (e) bedrooms, hallway closet and (e) w/c to a master bedroom. combine bedroom #3, (e) hallway sloet and (e) bath to a master bedroom on the 3/f.Details
revision to pa# 202308094084: garage- laundry stays, add (2) fixture bath. 1/f- remodel (e) bath as 3 fixture bath, combine (e) bedrooms, hallway closet and (e) w/c to a master bedroom. combine bedroom #3, (e) hallway sloet and (e) bath to a master bedroom on the 3/f. | |
| Aug 9, 2023 | Never finaled issued Aug 2023, no final | 731 Capp St | Joe 88 Construction Co | 1/f: demo partition wall, relocate (e) water heater, furnace, add lights; 2/f:change (e) closet to half bath at stairwell, change (e) closet to a full bath, combine (e) bedrm & bath to masterbedrm, demo (e) non-bearing wall btw kitchen & dining & remodel; 3/f: change (e) closet to full bath, combineDetails
1/f: demo partition wall, relocate (e) water heater, furnace, add lights; 2/f:change (e) closet to half bath at stairwell, change (e) closet to a full bath, combine (e) bedrm & bath to masterbedrm, demo (e) non-bearing wall btw kitchen & dining & remodel; 3/f: change (e) closet to full bath, combine | $200,000 |
| May 25, 2023 | Completed final sign-off Dec 2024 | 72 Tucker Av | F C Company | add a deck in rear yard extending from 2/f connecting to groundDetails
add a deck in rear yard extending from 2/f connecting to ground | $5,000 |
| Oct 14, 2022 | Completed final sign-off Nov 2023 | 1317 Masonic Av | Topline Builders Corp | commencent of work not started under prev approved permit. 201708094367. seismic retrofit soft storyDetails
commencent of work not started under prev approved permit. 201708094367. seismic retrofit soft story | $75,000 |
| Jul 17, 2018 | Completed final sign-off Nov 2018 | 2930 Sacramento St | G L Construction Company | structural upgrade: install shear walls, retaining walls and moment frames. comply with spebc chapter 4d per 2016 cebc appendix a-4.Details
structural upgrade: install shear walls, retaining walls and moment frames. comply with spebc chapter 4d per 2016 cebc appendix a-4. | $38,000 |
| Dec 29, 2017 | Never finaled issued Sep 2019, no final | 226 Irving St | to comply with nov 201717854 - soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appx a4Details
to comply with nov 201717854 - soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appx a4 | $54,000 | |
| Nov 30, 2017 | Completed final sign-off May 2019 | 4840 California St | Jason Liu Construction Company | voluntary structural strengthening, repair substandard framing and dry rot unconditioned. repair existing sun room at rear in kind. interior remodel including kitchen and bathrooms. add new skylights. windows at front ot be in-kind replacement wd to wd w/individual lites per google jan 2017 photo.Details
voluntary structural strengthening, repair substandard framing and dry rot unconditioned. repair existing sun room at rear in kind. interior remodel including kitchen and bathrooms. add new skylights. windows at front ot be in-kind replacement wd to wd w/individual lites per google jan 2017 photo. | $250,000 |
| Sep 13, 2017 | Completed final sign-off Feb 2019 | 3232 Taraval St | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $65,000 | |
| Sep 13, 2017 | Expired or cancelled cancelled Jan 2026 | 1532 Larkin St | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $12,000 | |
| Sep 13, 2017 | Completed final sign-off Feb 2019 | 1215 Pacific Av | Jones Bros Construction & Design Inc | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $50,000 |
| Sep 8, 2017 | Completed final sign-off Jul 2019 | 3674 16th St | Joe 88 Construction Co | comply with san francisco soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appendix chapter a-4.Details
comply with san francisco soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appendix chapter a-4. | $65,000 |
| Sep 8, 2017 | Completed final sign-off Aug 2020 | 821 Vallejo St | Jason Liu Construction Company | comply with san francisco soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appendix chapter a-4.Details
comply with san francisco soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appendix chapter a-4. | $60,000 |
| Sep 8, 2017 | Completed final sign-off Jan 2021 | 2335 Chestnut St | Joe 88 Construction Co | upgrade (e) accessible entrance door and rstroom at unit 2335 on g/f.Details
upgrade (e) accessible entrance door and rstroom at unit 2335 on g/f. | $10,000 |
| Sep 8, 2017 | Completed final sign-off Apr 2022 | 2335 Chestnut St | Joe 88 Construction Co | commericial: to comply with sf soft-story seismic retrofit program sfebc ch. 4d per 2016 cebc appendix chapter a-4.Details
commericial: to comply with sf soft-story seismic retrofit program sfebc ch. 4d per 2016 cebc appendix chapter a-4. | $10,000 |
| Sep 8, 2017 | Completed final sign-off Jul 2019 | 3674 16th St | Joe 88 Construction Co | unit #1 - remodel (e) living room, kitchen, bathroom, family roo & bedroom on 1st floor.Details
unit #1 - remodel (e) living room, kitchen, bathroom, family roo & bedroom on 1st floor. | $80,000 |
| Sep 8, 2017 | Completed final sign-off Mar 2020 | 2335 Chestnut St | Joe 88 Construction Co | residential: to comply with sf soft-story seismic retrofit program sfebc ch. 4d per 2016 cebc appendix chapter a-4.Details
residential: to comply with sf soft-story seismic retrofit program sfebc ch. 4d per 2016 cebc appendix chapter a-4. | $65,000 |
| Aug 25, 2017 | Completed final sign-off Apr 2019 | 1277 Mcallister St | Jones Bros Construction & Design Inc | to comply with sf soft story seismic retrofit program sfebc chapter f4 per 2016 cebc appendix chapter a-4.Details
to comply with sf soft story seismic retrofit program sfebc chapter f4 per 2016 cebc appendix chapter a-4. | $70,000 |
| Aug 25, 2017 | Completed final sign-off Aug 2019 | 4314 17th St | Jones Bros Construction & Design Inc | to comply with sf soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appendix chatper a-4.Details
to comply with sf soft story seismic retrofit program sfebc chapter 4d per 2016 cebc appendix chatper a-4. | $58,000 |
| Aug 25, 2017 | Completed final sign-off Nov 2018 | 120 Pierce St | Jones Bros Construction & Design Inc | to comply with sf soft story seismic retrofit program sfebc chapter f4 per 2016 cebc appendix chatper a-4.Details
to comply with sf soft story seismic retrofit program sfebc chapter f4 per 2016 cebc appendix chatper a-4. | $80,000 |
| Aug 18, 2017 | Completed final sign-off Aug 2019 | 800 Filbert St | Jason Liu Construction Company | soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. maher naDetails
soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. maher na | $90,000 |
| Aug 18, 2017 | Completed final sign-off Aug 2019 | 1276 Jackson St | Jason Liu Construction Company | soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. | $50,000 |
| Aug 9, 2017 | Completed final sign-off Aug 2019 | 1234 Jackson St | Jason Liu Construction Company | soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. maher naDetails
soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. maher na | $50,000 |
| Aug 9, 2017 | Completed final sign-off Jan 2018 | 3674 16th St | 3rd fl remodel existing unit #4, add one (n) bath and (n) bedroom.Details
3rd fl remodel existing unit #4, add one (n) bath and (n) bedroom. | $30,000 | |
| Aug 9, 2017 | Expired or cancelled expired Nov 2023 | 1321 Masonic Av | soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. maher naDetails
soft story retrofit per sfebc chapter 4d per engineering creteria 2016 cebc appendix a-4. maher na | $60,000 | |
| May 19, 2017 | Completed final sign-off Feb 2018 | 210 Casitas Av | Kevin Lin Construction Inc | 2nd fl: remodel (e) bath. main fl: remodel (e) kitchen & bath, add one half bath. lower fl: convert family rm to master bedroom, add laundry room to family rm. remodel (e) bath, add half bath, replace w/h, furnace. basement fl: add exercise room & wine rm, construct wood deck at rear yard.Details
2nd fl: remodel (e) bath. main fl: remodel (e) kitchen & bath, add one half bath. lower fl: convert family rm to master bedroom, add laundry room to family rm. remodel (e) bath, add half bath, replace w/h, furnace. basement fl: add exercise room & wine rm, construct wood deck at rear yard. | $80,000 |
| May 19, 2017 | Completed final sign-off Apr 2018 | 124 Bacon St | Southgate Home Design Inc | 2nd fl: remodel (e) bath & (e) kitchen, add one (n) bath. ground fl: add two bedrooms, two bathrooms, & one storage. replace water heater & furnace. construct (n) bearing wall with footing instead of central beam.Details
2nd fl: remodel (e) bath & (e) kitchen, add one (n) bath. ground fl: add two bedrooms, two bathrooms, & one storage. replace water heater & furnace. construct (n) bearing wall with footing instead of central beam. | $65,000 |
| Jan 13, 2017 | Completed final sign-off Jun 2017 | 1 Vega St | Jason Liu Construction Company | soft story retrofit per sfbc chapter 34b engineering criteria 2012 iebc appendix a-4, infill shear walls and moment frames.Details
soft story retrofit per sfbc chapter 34b engineering criteria 2012 iebc appendix a-4, infill shear walls and moment frames. | $70,000 |
| Oct 13, 2016 | Completed final sign-off Dec 2017 | 423 34th Av | P & L Construction Co | wood frame seismic retrofit, install (4) steel moment frame, tie beam & shear wall, all work at ground floor.Details
wood frame seismic retrofit, install (4) steel moment frame, tie beam & shear wall, all work at ground floor. | $60,000 |
| Mar 25, 2016 | Completed final sign-off Nov 2016 | 1940 Ellis St | Nbay Construction | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4Details
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4 | $38,000 |
| Mar 25, 2016 | Completed final sign-off Aug 2016 | 530 Page St | G L Construction Company | soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4, structural upgrade install shear walls & moment framesDetails
soft story retrofit per sfbc chapter 34b, 2012 iebc appendix a-4, structural upgrade install shear walls & moment frames | $45,000 |
| Mar 24, 2016 | Completed final sign-off Oct 2017 | 22 Fernwood Dr | G L Construction Company | 3rd floor - remodel 9e) bath and add (n) bath; 2nd floor - remodel (e) kitchen and bath, replace fireplace with gas insert; ground floor - add one bedroom, bath, exercise, ad family room. replace water heater and furnace; construct under 3' (n) wood deck at rear yard.Details
3rd floor - remodel 9e) bath and add (n) bath; 2nd floor - remodel (e) kitchen and bath, replace fireplace with gas insert; ground floor - add one bedroom, bath, exercise, ad family room. replace water heater and furnace; construct under 3' (n) wood deck at rear yard. | $65,000 |
| Mar 11, 2016 | Completed final sign-off Aug 2017 | 155 Tucker Av | Weiping Yin Construction Co | to comply his-201109721-to revert back to the last legal use. and to comply his-201111441 & 201111442-to repair cord wiring, waste and vent pipe. legalize (e) bath, bedrooms, family room on ground floor. remodel kitchen, bath & living room on 2nd floor.Details
to comply his-201109721-to revert back to the last legal use. and to comply his-201111441 & 201111442-to repair cord wiring, waste and vent pipe. legalize (e) bath, bedrooms, family room on ground floor. remodel kitchen, bath & living room on 2nd floor. | $60,000 |
| Feb 12, 2016 | Expired or cancelled withdrawn Apr 2016 | 138 08th Av | 3rd floor (#138) - remodel kitchen, bath and living rm, add 1 (n) bath and office rm; 2nd floor - (3140), remodel kitchen, bath and living room; add one (n) bath. on ground floor - add 2 bedrooms and 1 bath for unit 140; construct (n) intermediate footing and interior stairDetails
3rd floor (#138) - remodel kitchen, bath and living rm, add 1 (n) bath and office rm; 2nd floor - (3140), remodel kitchen, bath and living room; add one (n) bath. on ground floor - add 2 bedrooms and 1 bath for unit 140; construct (n) intermediate footing and interior stair | $68,000 | |
| Dec 23, 2015 | Completed final sign-off May 2016 | 441 24th Av | Jones Bros Construction Inc | revision to pa #201511233335 - revise & add structural detail for inspection.Details
revision to pa #201511233335 - revise & add structural detail for inspection. | |
| Nov 4, 2015 | Completed final sign-off Jun 2016 | 1619 Gough St | G L Construction Company | structural upgrade: install shear walls & moment frames per soft story ordinance 2012 iebc appendix a-4. n/a maher ordinanceDetails
structural upgrade: install shear walls & moment frames per soft story ordinance 2012 iebc appendix a-4. n/a maher ordinance | $50,000 |
| Nov 4, 2015 | Completed final sign-off Sep 2016 | 1509 Golden Gate Av | Nbay Construction, Jones Bros Construction Inc | structural upgrade: install shear walls & moment frames per soft story sfbc chapter 34b; ordinance 2012 iebc appendix a-4. n/a maher ordinanceDetails
structural upgrade: install shear walls & moment frames per soft story sfbc chapter 34b; ordinance 2012 iebc appendix a-4. n/a maher ordinance | $60,000 |
| Nov 4, 2015 | Completed final sign-off Apr 2016 | 1615 Gough St | G L Construction Company | structural upgrade: install shear walls & moment frames per soft story ordinance 2012 iebc appendix a-4. n/a maher ordinanceDetails
structural upgrade: install shear walls & moment frames per soft story ordinance 2012 iebc appendix a-4. n/a maher ordinance | $50,000 |
| Jul 8, 2015 | Expired or cancelled cancelled Jan 2025 | 863 Colby St | horiz & vert. addition of a 2 story single fam dwg. g/f: add 1 bedrm, 1 fam rm, 1 bathrm, 2/f: add 2 bedrms, 1.5 bathrm, 3/f: add 1 bedrm, 1 computer rm, and 1 bathrm.Details
horiz & vert. addition of a 2 story single fam dwg. g/f: add 1 bedrm, 1 fam rm, 1 bathrm, 2/f: add 2 bedrms, 1.5 bathrm, 3/f: add 1 bedrm, 1 computer rm, and 1 bathrm. | $200,000 | |
| Jun 11, 2015 | Completed final sign-off Nov 2015 | 1014 Clement St | Innovate Design Construction Inc | remodel (e) retail: construct partition wall. new unisex restroom on ground floor. compliance with maher ordinance no 155-13 not required.Details
remodel (e) retail: construct partition wall. new unisex restroom on ground floor. compliance with maher ordinance no 155-13 not required. | $20,000 |
| Jun 1, 2015 | Expired or cancelled withdrawn Jun 2015 | 1014 Clement St | remove existing elevator and construct storage rooms on 3rd and 2nd fl. remodel existing retail space and construct partition walls, and unisex accesible restroom on gr flDetails
remove existing elevator and construct storage rooms on 3rd and 2nd fl. remodel existing retail space and construct partition walls, and unisex accesible restroom on gr fl | $20,000 | |
| Jun 1, 2015 | Expired or cancelled withdrawn Jun 2015 | 1014 Clement St | remove existing elevator and construct storage rooms on 3rd and 2nd fl. remodel existing retail space and construct partition wallsand unisex accessible restroom on gr flDetails
remove existing elevator and construct storage rooms on 3rd and 2nd fl. remodel existing retail space and construct partition wallsand unisex accessible restroom on gr fl | $20,000 | |
| May 20, 2015 | Completed final sign-off Mar 2016 | 27 Santa Rita Av | Innovate Design Construction Inc | construct new less than 10 ft high deck at rear. replace rear window with sliding glass door, new stairs off deck to rear yard.Details
construct new less than 10 ft high deck at rear. replace rear window with sliding glass door, new stairs off deck to rear yard. | $5,000 |
| May 20, 2015 | Completed final sign-off Feb 2016 | 1867 22nd Av | Steven Liao Construction Company | construct one new bath, bedroom, family room & storage on ground floor. construct new less than 10 ft high deck & stair at rear yard.Details
construct one new bath, bedroom, family room & storage on ground floor. construct new less than 10 ft high deck & stair at rear yard. | $50,000 |
| Mar 20, 2015 | Completed final sign-off May 2015 | 350 27th St | Handy Construction Team Inc | replacement existing wood deck & wood stair @ rear yard.Details
replacement existing wood deck & wood stair @ rear yard. | $9,000 |
| Feb 25, 2015 | Completed final sign-off Dec 2022 | 371 Haight St | to comply with nov #201498951,201312772,201402681,200876042. 1st fl: fully remodel, demo and construct nw partition walls, 2nd fl: fully remodel, add 1 bedrm, & nw partition walls. 3rd fl: 371a fully remodel. structural strengthening.Details
to comply with nov #201498951,201312772,201402681,200876042. 1st fl: fully remodel, demo and construct nw partition walls, 2nd fl: fully remodel, add 1 bedrm, & nw partition walls. 3rd fl: 371a fully remodel. structural strengthening. | $150,000 | |
| Jan 28, 2015 | Completed final sign-off Aug 2015 | 171 Vernon St | Seabee Construction | revision to pa#201409237071, add 2 bathrooms on ground floor. repair stucco 300sf at front in-kindDetails
revision to pa#201409237071, add 2 bathrooms on ground floor. repair stucco 300sf at front in-kind | $10,000 |
| Jan 13, 2015 | Completed final sign-off Apr 2015 | 2482 45th Av | C L & Y Construction Inc. | construct 2 new bathrooms, 1 office, family room and storage room on ground floor.Details
construct 2 new bathrooms, 1 office, family room and storage room on ground floor. | $38,000 |
| Dec 30, 2014 | Never finaled issued Mar 2015, no final | 25 Italy Av | construct one (n) bathroom, family room, den & two bedrooms on ground floor. replace (e) furnace & water heater.Details
construct one (n) bathroom, family room, den & two bedrooms on ground floor. replace (e) furnace & water heater. | $50,000 | |
| Dec 30, 2014 | Completed final sign-off Aug 2015 | 50 Farragut Av | Lin's Builder | construct two (n) bathrooms, one family room, & three bedrooms on ground floor. replace (e) furnace & water heater.Details
construct two (n) bathrooms, one family room, & three bedrooms on ground floor. replace (e) furnace & water heater. | $60,000 |
| Dec 30, 2014 | Completed final sign-off Feb 2015 | 2026 15th St | 328 Construction | construct one full bathroom on 2nd floor @ unit #2026.Details
construct one full bathroom on 2nd floor @ unit #2026. | $5,000 |
| Dec 24, 2014 | Completed final sign-off Sep 2015 | 950 Madrid St | Jason Liu Construction Company | revision to appl #2014.0909.5864 for remodeling existing kitchen & bathroom. add one new bathroom & upgate existing electrical on 2nd floor.Details
revision to appl #2014.0909.5864 for remodeling existing kitchen & bathroom. add one new bathroom & upgate existing electrical on 2nd floor. | $10,000 |
| Dec 8, 2014 | Completed final sign-off Apr 2015 | 2151 16th Av | Jones Bros Construction Inc | remodel existing kitchen, add one (n) bath, study room on 2/f. construct one (n) family room, one bedroom, one storage and 2 bathrooms on g/f. replace existing water heater and furnace on g/f.Details
remodel existing kitchen, add one (n) bath, study room on 2/f. construct one (n) family room, one bedroom, one storage and 2 bathrooms on g/f. replace existing water heater and furnace on g/f. | $60,000 |
| Nov 7, 2014 | Completed final sign-off May 2016 | 84 Manor Dr | construct (n) retaining walls, add one bath, bedroom, and family room, relocate interior stair on grnd flr, remodel (e) bath, add laundry rm on 2nd flr, remodel (e) bath, add master bath on 3rd fl, replace (e) furnace & water heater.Details
construct (n) retaining walls, add one bath, bedroom, and family room, relocate interior stair on grnd flr, remodel (e) bath, add laundry rm on 2nd flr, remodel (e) bath, add master bath on 3rd fl, replace (e) furnace & water heater. | $60,000 | |
| Nov 7, 2014 | Expired or cancelled cancelled Jan 2026 | 2431 27th Av | construct one (n) bath, family, and 2 bedrooms on ground floor, remodel (e) bath, and add one (n) bath on 2nd flr, remodel (e) bath and bedroom on 3rd flr, replace (e) furnace and water heater.Details
construct one (n) bath, family, and 2 bedrooms on ground floor, remodel (e) bath, and add one (n) bath on 2nd flr, remodel (e) bath and bedroom on 3rd flr, replace (e) furnace and water heater. | $50,000 | |
| Nov 3, 2014 | Completed final sign-off Jan 2015 | 4 Farallones St | Jason Liu Construction Company | to comply w/complaint #201499121 - legalize (e) one bedroom, bath, den & two storage rooms on ground floor. unit legalization per ordinance 43-14.Details
to comply w/complaint #201499121 - legalize (e) one bedroom, bath, den & two storage rooms on ground floor. unit legalization per ordinance 43-14. | $25,000 |
| Nov 3, 2014 | Completed final sign-off Apr 2015 | 235 Lee Av | Steven Liao Construction Company | remodel (e) social rm & bathrm; relocate interior stair; add one (n) bedroom, bathrm,& exercise area; leaglize two (e) storage rm on ground floor. add one (n) bathroom on 2nd floor. replace (e) furnace & water heater.Details
remodel (e) social rm & bathrm; relocate interior stair; add one (n) bedroom, bathrm,& exercise area; leaglize two (e) storage rm on ground floor. add one (n) bathroom on 2nd floor. replace (e) furnace & water heater. | $38,000 |
| Oct 14, 2014 | Completed final sign-off Jun 2015 | 1032 Junipero Serra Bl | Modern Craft Construction | remodel (e) kitchen, add one new bathroom, new family roon on ground floor. remodel (e) bathroom on second floor. construct a new deck at rear (stratford dr. side). relace (e) furnace and water heater.Details
remodel (e) kitchen, add one new bathroom, new family roon on ground floor. remodel (e) bathroom on second floor. construct a new deck at rear (stratford dr. side). relace (e) furnace and water heater. | $40,000 |
| Sep 11, 2014 | Expired or cancelled cancelled Jan 2026 | 2840 Judah St | soft story retrofit per sfbc chapter 34b, engineering criteria asce 41-13: wood frame seismic retrofit, install (5) steel moment frame, tie beams & shear wall. all work at ground floor.Details
soft story retrofit per sfbc chapter 34b, engineering criteria asce 41-13: wood frame seismic retrofit, install (5) steel moment frame, tie beams & shear wall. all work at ground floor. | $60,000 | |
| Jul 28, 2014 | Completed final sign-off Oct 2014 | 7730 Geary Bl | Southgate Home Design Inc | construct one new bedroom, new bath, new storage, & new family room on ground floor.Details
construct one new bedroom, new bath, new storage, & new family room on ground floor. | $38,000 |
| Jul 8, 2014 | Completed final sign-off Mar 2016 | 755 12th Av | 328 Construction | construct new one level rear deck at rar of existing bldg. legalize one bath, one laundry & convert (e) storage to new family rm on grnd flr, demolish (e)side stair & remodel (e) kitchen on 2nd flrDetails
construct new one level rear deck at rar of existing bldg. legalize one bath, one laundry & convert (e) storage to new family rm on grnd flr, demolish (e)side stair & remodel (e) kitchen on 2nd flr | $38,000 |
| Jun 30, 2014 | Expired or cancelled cancelled Jan 2026 | 15 Modoc Av | infill existing deck to construct one bedroom and bathroom on ground floor.Details
infill existing deck to construct one bedroom and bathroom on ground floor. | $15,000 | |
| Jun 27, 2014 | Completed final sign-off Dec 2014 | 2419 34th Av | Luo's Construction Company **Check Id*** | construct 2 bedrooms, 2 bathrooms, one family room, and one storage room on ground floor.Details
construct 2 bedrooms, 2 bathrooms, one family room, and one storage room on ground floor. | $50,000 |
| Jun 26, 2014 | Expired or cancelled cancelled Sep 2017 | 874 30th Av | reloc garage door & entrance & expand (e) driveway. expand & reconfig 1/fl(unit 1). reconf 2/fl(unit 2), a (n) 3/fl, with 2 mstr bedroom w/ bathroom, & 1 bathrm & 1 bedroom. (n) landscape at front & back yard. ref:2007-11-28-9065 site permit issued 1/26/2009.Details
reloc garage door & entrance & expand (e) driveway. expand & reconfig 1/fl(unit 1). reconf 2/fl(unit 2), a (n) 3/fl, with 2 mstr bedroom w/ bathroom, & 1 bathrm & 1 bedroom. (n) landscape at front & back yard. ref:2007-11-28-9065 site permit issued 1/26/2009. | $558,000 | |
| Jun 20, 2014 | Completed final sign-off Jan 2015 | 2362 38th Av | Dw & Jy Construction | construct one bedroom, den, storage, & two bathrooms on ground floor. infill at rear extg storage on ground floor. remove extg door on 2nd floor.Details
construct one bedroom, den, storage, & two bathrooms on ground floor. infill at rear extg storage on ground floor. remove extg door on 2nd floor. | $45,000 |
| Jun 13, 2014 | Completed final sign-off Aug 2014 | 1235 Bush St | W Chen's Construction | remove extg illegal units. legalize extg full bath room and storages behind the garage on the ground floor to comply with complaint #201473744. n/a for the maher ordinance #155-13Details
remove extg illegal units. legalize extg full bath room and storages behind the garage on the ground floor to comply with complaint #201473744. n/a for the maher ordinance #155-13 | $10,000 |
| Jun 13, 2014 | Completed final sign-off Oct 2014 | 66 Rossi Av | Southgate Home Design Inc | remodel extg kitchen and bathroom, add new bath on 2nd floor, legalize extg bath room and convert extg storages to bedroom and den on ground floor.Details
remodel extg kitchen and bathroom, add new bath on 2nd floor, legalize extg bath room and convert extg storages to bedroom and den on ground floor. | $45,000 |
| Jun 6, 2014 | Completed final sign-off Oct 2015 | 1514 29th Av | Rubio Construction | remodel existing kitchen and bath on 2nd fl.Details
remodel existing kitchen and bath on 2nd fl. | $20,000 |
| Jun 2, 2014 | Completed final sign-off Oct 2014 | 2628 Clement St | Jason Liu Construction Company | remodel existing kitchen, add one new bathroom & add new laundry area on 2nd floor.Details
remodel existing kitchen, add one new bathroom & add new laundry area on 2nd floor. | $10,000 |
| Apr 23, 2014 | Completed final sign-off Nov 2016 | 448 Madrid St | Tad Van Nguyen | complete remodel and vertical addition (add 2 stories),totally become 4 bedrooms and 3 baths, (currently 2 bedrooms and 1 bath on 1st level)Details
complete remodel and vertical addition (add 2 stories),totally become 4 bedrooms and 3 baths, (currently 2 bedrooms and 1 bath on 1st level) | $200,000 |
| Jan 7, 2014 | Never finaled issued Jan 2014, no final | 444 Warren Dr | Handy Construction Team Inc | provide new water proofing along existing footing.no change in footingDetails
provide new water proofing along existing footing.no change in footing | $12,000 |
| Oct 9, 2013 | Completed final sign-off Jun 2014 | 1669 Sacramento St | T J Constr Inc***Ck Id,Tie Liu Only***** | comply with nov 201321831, 201325701, 201322691, 201321402. construct two full and one half-bath; two study rooms, one office, one family room, two storage rooms, exercise room, foyer and laundry room on ground floor for unit #1669. replace window (in kind) at rear.Details
comply with nov 201321831, 201325701, 201322691, 201321402. construct two full and one half-bath; two study rooms, one office, one family room, two storage rooms, exercise room, foyer and laundry room on ground floor for unit #1669. replace window (in kind) at rear. | $40,000 |
| Oct 2, 2013 | Completed final sign-off Jan 2014 | 7509 Geary Bl | Joe 88 Construction Co | construct one new bathroom, 2 new bedrooms and one new laundry room on g/f, replace (e) furnace and water heater.Details
construct one new bathroom, 2 new bedrooms and one new laundry room on g/f, replace (e) furnace and water heater. | $30,000 |
| Sep 11, 2013 | Completed final sign-off Feb 2014 | 2250 21st Av | Calvin Chan Constr Inc. **See Note ** | add 4' wood deck and 3' stair by sides at the back yard. provide opening at dining room and kitchen at 2nd fl. remove existing wood post at gr floor. no new habitable spaceDetails
add 4' wood deck and 3' stair by sides at the back yard. provide opening at dining room and kitchen at 2nd fl. remove existing wood post at gr floor. no new habitable space | $9,000 |
| Jul 29, 2013 | Completed final sign-off Sep 2013 | 1235 Bush St | W Chen's Construction | comply with complaint #201304751 dated 6/5/13-replace (e) fence with new concrete footing in back yardDetails
comply with complaint #201304751 dated 6/5/13-replace (e) fence with new concrete footing in back yard | $10,000 |
| Apr 22, 2013 | Completed final sign-off Feb 2014 | 875 Faxon Av | Jun Meng Li | add one new bath, one new bedroom & replace exisitng footing wall on ground floor. construct new retaining wall at back yard. to maintain (e) grade.Details
add one new bath, one new bedroom & replace exisitng footing wall on ground floor. construct new retaining wall at back yard. to maintain (e) grade. | $50,000 |
| Apr 22, 2013 | Completed final sign-off Sep 2013 | 2439 42nd Av | legalize (e) bedroom, add one new bath & new exercise room on ground floor. replace (e) furnace.Details
legalize (e) bedroom, add one new bath & new exercise room on ground floor. replace (e) furnace. | $20,000 | |
| Jan 25, 2013 | Completed final sign-off Apr 2014 | 231 Randall St | Lee & Georgiou Inc. Dba Georgiou Const. | revision to comply with complaint #201385463. revision to pa#201210162102r/1. shotcrete to be used, 4000 psi minimum compressive strength per plan.Details
revision to comply with complaint #201385463. revision to pa#201210162102r/1. shotcrete to be used, 4000 psi minimum compressive strength per plan. | |
| Dec 11, 2012 | Completed final sign-off Mar 2013 | 418 40th Av | Jason Liu Construction Company | revision to appl #2012.10.17.2254 for remodeling (e) master bedroom on 2nd floor. replace (e) side & rear windows on 1st & 2nd floor. not visible from street.Details
revision to appl #2012.10.17.2254 for remodeling (e) master bedroom on 2nd floor. replace (e) side & rear windows on 1st & 2nd floor. not visible from street. | $10,000 |
| Nov 16, 2012 | Completed final sign-off May 2013 | 1401 41st Av | Start Construction | add one (n) bath, one (n) den on the ground floor. replace (e) furnace and (e) water heater.Details
add one (n) bath, one (n) den on the ground floor. replace (e) furnace and (e) water heater. | $29,000 |
| Oct 16, 2012 | Completed final sign-off Feb 2013 | 300 Foote Av | Xinh Hua Construction | add 1 bathroom, 1 new bedroom, 1 new den on ground floorDetails
add 1 bathroom, 1 new bedroom, 1 new den on ground floor | $25,000 |
| Oct 16, 2012 | Completed final sign-off Jul 2013 | 2733 Santiago St | Jason Liu Construction Company | add 1 new bathroom, master bedroom & new powder room on ground floor. remodel (e) social room on ground floorDetails
add 1 new bathroom, master bedroom & new powder room on ground floor. remodel (e) social room on ground floor | $28,000 |
| Oct 16, 2012 | Never finaled issued Oct 2012, no final | 231 Randall St | Lee & Georgiou Inc. Dba Georgiou Const. | upgrade (e) foundation for new garage (structural work only)Details
upgrade (e) foundation for new garage (structural work only) | $45,000 |
| Jul 27, 2012 | Completed final sign-off Apr 2014 | 167 Sadowa St | contruct two story rear horizontal additon for bedrooms, family and kitchen. contruct one level rear deck. conveer (e) ground floor space to living space (bedrooms & bath).Details
contruct two story rear horizontal additon for bedrooms, family and kitchen. contruct one level rear deck. conveer (e) ground floor space to living space (bedrooms & bath). | $118,000 | |
| May 11, 2012 | Completed final sign-off Sep 2012 | 330 05th Av | Gary Liu Construction (Ask For Id) | remodel (e) kitchen, (e) bath, relocate living room,bedrooms, add new bath on 3rd floor unit 330. replace (e) water heater and (e) furnaceDetails
remodel (e) kitchen, (e) bath, relocate living room,bedrooms, add new bath on 3rd floor unit 330. replace (e) water heater and (e) furnace | $30,000 |
| Apr 30, 2012 | Completed final sign-off Apr 2013 | 724 Peru Av | relocate (e) kitchen, (e) living, (e) bedroom & add 1 new bathroom on (e) 2nd floor. relocate interior stairs, (e) bathroom on (e) ground floor. legalize (e) deck at rearDetails
relocate (e) kitchen, (e) living, (e) bedroom & add 1 new bathroom on (e) 2nd floor. relocate interior stairs, (e) bathroom on (e) ground floor. legalize (e) deck at rear | $38,000 | |
| Apr 30, 2012 | Completed final sign-off Oct 2012 | 236 Saint Charles Av | Golden Hammer | construct 2 new bedrooms, 1 bathroom & 1 new laundry area on ground floor. replace (e) water heater & (e) furnaceDetails
construct 2 new bedrooms, 1 bathroom & 1 new laundry area on ground floor. replace (e) water heater & (e) furnace | $45,000 |
| Apr 30, 2012 | Completed final sign-off Feb 2013 | 1306 30th Av | John Jin Hang Wai | construct 2 new bedrooms, 1 new bathroom, 1 new family room on ground floor. replace (e) water heater & (e) furnaceDetails
construct 2 new bedrooms, 1 new bathroom, 1 new family room on ground floor. replace (e) water heater & (e) furnace | $50,000 |
| Apr 2, 2012 | Expired or cancelled cancelled Jun 2012 | 825 Monterey Bl | East Rainbow Electrical | 1)revision to app#201201172314. 2)revise roofline addition to back to origin for complying nov#201207521Details
1)revision to app#201201172314. 2)revise roofline addition to back to origin for complying nov#201207521 | |
| Jan 18, 2012 | Completed final sign-off Mar 2012 | 472 Gaven St | Gary Liu Construction (Ask For Id) | construct one (n) bath, one (n) office, & (n) exercise room on basement floor.Details
construct one (n) bath, one (n) office, & (n) exercise room on basement floor. | $20,000 |
| Jan 17, 2012 | Completed final sign-off Nov 2012 | 825 Monterey Bl | construct 1 new bedroom, 2 bathrooms, 1 family room on ground floor. remodel kitchen & dining room on 2nd floor. construct 1 office, 1 new bathroom on attic floor. convert attic into habitable spaceDetails
construct 1 new bedroom, 2 bathrooms, 1 family room on ground floor. remodel kitchen & dining room on 2nd floor. construct 1 office, 1 new bathroom on attic floor. convert attic into habitable space | $85,000 | |
| Dec 2, 2011 | Completed final sign-off Feb 2012 | 161 Thrift St | Southgate Home Design Inc | construct one new bedroom, one bathroom, one family room o ground floor. construct one new deck at rear yard.Details
construct one new bedroom, one bathroom, one family room o ground floor. construct one new deck at rear yard. | $30,000 |
| Nov 14, 2011 | Completed final sign-off Jan 2012 | 3100 Franklin St | Steven Liao Construction Company | revision to appl #201108011424 for replacing floor beam.Details
revision to appl #201108011424 for replacing floor beam. | $2,000 |
| Aug 16, 2011 | Completed final sign-off Nov 2011 | 29 Oliver St | Southgate Home Design Inc | 1)to comply with nov #200703464 to repair leaking.2)remodel extg bath on 2nd floor. 3)remodel extg bedrooms and extg bath on ground floor to comply with nov #201032221 & 201033049.4)install new interior stair & repair extg rear stair. 5) replace extg water heater and extg furnace.Details
1)to comply with nov #200703464 to repair leaking.2)remodel extg bath on 2nd floor. 3)remodel extg bedrooms and extg bath on ground floor to comply with nov #201032221 & 201033049.4)install new interior stair & repair extg rear stair. 5) replace extg water heater and extg furnace. | $45,000 |
| Aug 8, 2011 | Completed final sign-off Nov 2012 | 3514 24th St | Handy Construction Team Inc | revision to pa# 2010.10.28.3925. provide (n) den, bedroom, add a tub, and cut (e) brick chimney and supported by steel tube at ground floor. change the storage to new bathrm at 1st fl. strengthen ceiling joist at 2nd fl and structural strenghtening upgrade at ground and 1st fl.Details
revision to pa# 2010.10.28.3925. provide (n) den, bedroom, add a tub, and cut (e) brick chimney and supported by steel tube at ground floor. change the storage to new bathrm at 1st fl. strengthen ceiling joist at 2nd fl and structural strenghtening upgrade at ground and 1st fl. | $30,000 |
| Jul 13, 2011 | Completed final sign-off Apr 2012 | 519 25th Av | Jason Liu Construction Company | construct 1 new bedroom, 1 bath, 1 family room on gr fl. remodel e kitchen and e bath on 2nd fl, replace e water heater and furnace, upgrade e rear partial foundationDetails
construct 1 new bedroom, 1 bath, 1 family room on gr fl. remodel e kitchen and e bath on 2nd fl, replace e water heater and furnace, upgrade e rear partial foundation | $50,000 |
| Jul 13, 2011 | Completed final sign-off Aug 2012 | 266 Prague St | construct new bedroom, 1 new bath, 1 new family room and 1 storage rm at gr fl. replce e water heater and e furnaceDetails
construct new bedroom, 1 new bath, 1 new family room and 1 storage rm at gr fl. replce e water heater and e furnace | $38,000 | |
| Jul 13, 2011 | Completed final sign-off Aug 2012 | 771 Naples St | construct 1 new bedroom, 1 ndw bath, 1 new family room on gr fl. replace e water heater and e furnaceDetails
construct 1 new bedroom, 1 ndw bath, 1 new family room on gr fl. replace e water heater and e furnace | $30,000 | |
| May 6, 2011 | Completed final sign-off Jun 2011 | 1421 Felton St | Golden Hammer | 1)revision to app#201102049670. no work on 2nd floor.Details
1)revision to app#201102049670. no work on 2nd floor. |