Amit Wadhwa
- Listed as
- architect, authorized agent-others, designer, engineer
- Firm
- Amit Wadhwa & Associates
- Based in
- San Francisco
- On San Francisco permits
- Nov 2004 to Sep 2026
467 permits since 2000 (engineer on 438 permits, architect on 27 permits, authorized agent-others on 1 permit, designer on 1 permit): 325 completed, 72 in progress, 58 never finaled, 12 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 467.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 23, 2026 | In progress filed Sep 2026, not yet issued | 300 Howard St | 14th fl: dining and servery. ti includes interior walls, ceilkings, millwork, finishes.Details
14th fl: dining and servery. ti includes interior walls, ceilkings, millwork, finishes. | $9,172,090 | |
| Sep 16, 2026 | In progress filed Sep 2026, not yet issued | 1455 Market St | floor: 8 and 9; shall consist of interior demolition of portion of (e) south stair enclosure on floor 8 and new construction of non-structural elements including but not limited to new interior partitions to enclose existing floor 8 and 9 north stair, new door, and associated mechamical and electricDetails
floor: 8 and 9; shall consist of interior demolition of portion of (e) south stair enclosure on floor 8 and new construction of non-structural elements including but not limited to new interior partitions to enclose existing floor 8 and 9 north stair, new door, and associated mechamical and electric | $85,000 | |
| Sep 15, 2026 | In progress filed Sep 2026, not yet issued | 300 Howard St | Novo Construction Inc | 2/f: tenant improvements: in existing office building. improvements to include, architectural, mechanical, electrical and plumbing to accommodate new tenant build out. mep scope to support kitchen build-out and updated restrooms.Details
2/f: tenant improvements: in existing office building. improvements to include, architectural, mechanical, electrical and plumbing to accommodate new tenant build out. mep scope to support kitchen build-out and updated restrooms. | $8,061,217 |
| Sep 15, 2026 | In progress filed Sep 2026, not yet issued | 425 Market St | suite 1600; conversion of a single tenant flr to multi-tenant including full tenant suite demolition, construction of new multi-tenant cooridor and restroom remodel. unit 1600Details
suite 1600; conversion of a single tenant flr to multi-tenant including full tenant suite demolition, construction of new multi-tenant cooridor and restroom remodel. unit 1600 | $250,000 | |
| Sep 2, 2026 | In progress issued Sep 2026 | 345 California St | Gci, Inc | 35th fl - remodel men's women's restrooms. remodel pantry/break room. new non-structural partitions. new lighting & ceilings, wall & floor finishesDetails
35th fl - remodel men's women's restrooms. remodel pantry/break room. new non-structural partitions. new lighting & ceilings, wall & floor finishes | $675,000 |
| Sep 1, 2026 | In progress filed Sep 2026, not yet issued | 300 Howard St | 15th floor: t.i. including new interior walls, ceilings, millwork & finishesDetails
15th floor: t.i. including new interior walls, ceilings, millwork & finishes | $8,361,087 | |
| Aug 31, 2026 | In progress filed Aug 2026, not yet issued | 560 Mission St | interior ti. on portion of 7th floor, including modifications to (e) tenant space including open office areas, breakroom, powder room, conference rooms, as well as new ceiling and light fixtures and mep system in areas throught the floor.Details
interior ti. on portion of 7th floor, including modifications to (e) tenant space including open office areas, breakroom, powder room, conference rooms, as well as new ceiling and light fixtures and mep system in areas throught the floor. | $1,700,000 | |
| Aug 25, 2026 | In progress filed Aug 2026, not yet issued | 300 Howard St | 2nd fl - ti to existing office. includes improvements to arch, mech, electrical and plumbingDetails
2nd fl - ti to existing office. includes improvements to arch, mech, electrical and plumbing | $6,048,657 | |
| Aug 20, 2026 | In progress issued Sep 2026 | 50 California St | Richlen Construction | suit#1350: (e) interior office remodel, scope includes demo & construction of non-structural partitions, ceilings, glazing, finishes, electrical, mechanical, & plumbing fixtures.Details
suit#1350: (e) interior office remodel, scope includes demo & construction of non-structural partitions, ceilings, glazing, finishes, electrical, mechanical, & plumbing fixtures. | $859,574 |
| Aug 17, 2026 | In progress issued Sep 2026 | 55 Spear St | Source Planning And Construction Inc | 18th floor: revision to bpa: 202606032408 room 18-009/ pantry and finishes to single sex rr was deferred. adressing architectural set and corresponding meps for this review.Details
18th floor: revision to bpa: 202606032408 room 18-009/ pantry and finishes to single sex rr was deferred. adressing architectural set and corresponding meps for this review. | $37,488 |
| Jul 28, 2026 | In progress issued Jul 2026 | 101 California St | Bcci Construction Company | 27th and 28th floors: mep submittal to support approved arch. permit. #202607175188Details
27th and 28th floors: mep submittal to support approved arch. permit. #202607175188 | $202,000 |
| Jul 15, 2026 | In progress issued Aug 2026 | 555 Mission St | Novo Construction Inc | 29/fl- ti to include (n) conferencing rooms, employee break area and storage spaceDetails
29/fl- ti to include (n) conferencing rooms, employee break area and storage space | $2,790,000 |
| Jul 6, 2026 | In progress issued Aug 2026 | 50 California St | Swinerton Builders | 16/f: tenant improvement of an existing suite on the 16th floor of a fully sprinklered building.Details
16/f: tenant improvement of an existing suite on the 16th floor of a fully sprinklered building. | $2,234,736 |
| Jun 30, 2026 | In progress issued Jul 2026 | 550 California St | ste #220 (level 2): deferred mep for pa# 202606052702.Details
ste #220 (level 2): deferred mep for pa# 202606052702. | $172,368 | |
| Jun 29, 2026 | In progress issued Jul 2026 | 101 California St | Dpr Construction A | 15/f - ste 1500: deferred mep work for permit# 202604018658Details
15/f - ste 1500: deferred mep work for permit# 202604018658 | $320,000 |
| Jun 26, 2026 | In progress issued Jul 2026 | 550 California St | suite 430: deferred mep for 202604300443Details
suite 430: deferred mep for 202604300443 | $249,000 | |
| Jun 26, 2026 | Completed final sign-off Sep 2026 | 388 Market St | Rudolph Commercial Interiors Inc, Rci | 14/fl- partial ti to include adding partition walls for 3 (n) offices and upgrade hvac system and electrical.Details
14/fl- partial ti to include adding partition walls for 3 (n) offices and upgrade hvac system and electrical. | $130,000 |
| Jun 24, 2026 | In progress issued Jul 2026 | 555 Mission St | Gci, Inc | 21st fl - interior ti to demo and construction new non-structural partitions, ceilings, finishes and associated mepDetails
21st fl - interior ti to demo and construction new non-structural partitions, ceilings, finishes and associated mep | $2,012,760 |
| Jun 23, 2026 | In progress issued Jul 2026 | 345 California St | Source Planning And Construction Inc | 24th floor: mechanical: duct distribution to be modified to serve new space plan in area of work. 5 new vav boxes are being added. electrical: new led light fixtures and power and signal. plumbing: new plumbing in pantry. ref pa #202606233688Details
24th floor: mechanical: duct distribution to be modified to serve new space plan in area of work. 5 new vav boxes are being added. electrical: new led light fixtures and power and signal. plumbing: new plumbing in pantry. ref pa #202606233688 | $375,000 |
| Jun 18, 2026 | In progress issued Jul 2026 | 101 California St | Skyline Construction | 33rd fl - ti to partial suite to include selective demo, new partitions, ceiling, lighting, finishes, electrical, mechanical and plumbingDetails
33rd fl - ti to partial suite to include selective demo, new partitions, ceiling, lighting, finishes, electrical, mechanical and plumbing | $1,583,313 |
| Jun 10, 2026 | In progress issued Jun 2026 | 555 Mission St | Gci, Inc | 24th floor: interior tenant improvement to demo and construct new non-structural partitions, ceilings, finishes and associated mep.Details
24th floor: interior tenant improvement to demo and construct new non-structural partitions, ceilings, finishes and associated mep. | $2,312,760 |
| Jun 4, 2026 | In progress issued Jun 2026 | 550 California St | level 4, suite 440: deferred mep for pa#202604230010Details
level 4, suite 440: deferred mep for pa#202604230010 | $289,656 | |
| Jun 3, 2026 | In progress issued Jun 2026 | 55 Spear St | Source Planning And Construction Inc | 18f t.i: demo done under permit. new partitons & doors, ceilings, lights, el distribution. mep included. including structural work. n unisex accessible toilet. see coversheet for cope. deffered submittal: fire alarm, fire sprinklers, network anchor + health review at pantry.Details
18f t.i: demo done under permit. new partitons & doors, ceilings, lights, el distribution. mep included. including structural work. n unisex accessible toilet. see coversheet for cope. deffered submittal: fire alarm, fire sprinklers, network anchor + health review at pantry. | $3,279,000 |
| May 28, 2026 | In progress issued Aug 2026 | 50 California St | Sc Builders, Inc | unit# 3151: full floor tenant expansion into adjacent vacant space demo of non-load bearing partitions, finishes, ceiling, and lights, constrution of non-load bearing partitions, millwork, finishes, ceilings and lights.Details
unit# 3151: full floor tenant expansion into adjacent vacant space demo of non-load bearing partitions, finishes, ceiling, and lights, constrution of non-load bearing partitions, millwork, finishes, ceilings and lights. | $1,308,872 |
| May 20, 2026 | In progress issued Jul 2026 | 500 Sansome St | Centric Construction Inc | 6/f suite 600 - t.i buildout of an (e) office space. scope include new open office space, enclosed office space, employeee kitchenette and storage. new office space will utilize (e) men's and women's restrooms on 6/f.Details
6/f suite 600 - t.i buildout of an (e) office space. scope include new open office space, enclosed office space, employeee kitchenette and storage. new office space will utilize (e) men's and women's restrooms on 6/f. | $1,300,000 |
| May 19, 2026 | In progress issued May 2026 | 345 California St | Skyline Construction | 5th fl: mechanical revision to pa#202603046904, 202509024401 and 202509024365 to add fsd-14 upgrade bulletin 2.05, fsd matrix, add sequence of operations. add updated smoke control narrative/preapp minutes. smoke control panel.Details
5th fl: mechanical revision to pa#202603046904, 202509024401 and 202509024365 to add fsd-14 upgrade bulletin 2.05, fsd matrix, add sequence of operations. add updated smoke control narrative/preapp minutes. smoke control panel. | |
| May 13, 2026 | In progress issued May 2026 | 425 Market St | Gci, Inc | 12th fl;reference:202604219808. mech: duct distribution is being modified per new space plan, (1) new condenser water pump is being added, no new fsds. elec: electric single line riser diagram & panel, two way comm.system power signal. plumbing:no new tank water heater being added.Details
12th fl;reference:202604219808. mech: duct distribution is being modified per new space plan, (1) new condenser water pump is being added, no new fsds. elec: electric single line riser diagram & panel, two way comm.system power signal. plumbing:no new tank water heater being added. | $250,000 |
| May 12, 2026 | Completed final sign-off Oct 2026 | 555 Mission St | Gci, Inc | 22nd fl revision to pa 202510217782 removing scope to demo certain partitions and offices throughout the floor. mep revision to accomodate removed scopeDetails
22nd fl revision to pa 202510217782 removing scope to demo certain partitions and offices throughout the floor. mep revision to accomodate removed scope | |
| May 7, 2026 | In progress issued May 2026 | 550 California St | 2/fl-ref 202603318646- mepsDetails
2/fl-ref 202603318646- meps | $190,000 | |
| May 5, 2026 | Completed final sign-off Jun 2026 | 425 Market St | Bcci Construction Company | 25/f: mechanical only permit to support approved architectural permit 201908169078. (2) new heat pumps and (1) new condenser water pump is being added. ref permit 201908169078.Details
25/f: mechanical only permit to support approved architectural permit 201908169078. (2) new heat pumps and (1) new condenser water pump is being added. ref permit 201908169078. | $72,000 |
| May 1, 2026 | In progress issued Jun 2026 | 101 California St | Hathaway Dinwiddie Co. | 13th and 14th flr. new tenant, convenience stairs between 13th & 14th floors, work includes new floor opening, structural supports, associated revisions, ceiling & lighting & finishesDetails
13th and 14th flr. new tenant, convenience stairs between 13th & 14th floors, work includes new floor opening, structural supports, associated revisions, ceiling & lighting & finishes | $399,334 |
| May 1, 2026 | In progress issued Jun 2026 | 101 California St | Hathaway Dinwiddie Co. | 11 and 12/fl-(n) ti for convenience stairs between 11th and 12th floors. work include (n) floor, opening, structural supports, associated revisions to partition, ceiling and lighting and finishes. 2-hr separation and smoke controlDetails
11 and 12/fl-(n) ti for convenience stairs between 11th and 12th floors. work include (n) floor, opening, structural supports, associated revisions to partition, ceiling and lighting and finishes. 2-hr separation and smoke control | $399,334 |
| Apr 10, 2026 | In progress issued Jun 2026 | 1 Embarcadero Center | 30/f: interior non-structural partitions modification, and reconfiguration interior ceiling modifications. interior finish replacement. related mechanical, electrical, and plumbing modifications. a non-egress stair connecting lvs 30 & 31.Details
30/f: interior non-structural partitions modification, and reconfiguration interior ceiling modifications. interior finish replacement. related mechanical, electrical, and plumbing modifications. a non-egress stair connecting lvs 30 & 31. | $8,750,000 | |
| Apr 10, 2026 | In progress issued Jun 2026 | 1 Embarcadero Center | Skyline Construction | 31/f: interior tenant improvement. related mechanical, electrical and plumbing modifications. limited area of floor slab demolition is included in this scope for a non-egress stair under seperate permit.Details
31/f: interior tenant improvement. related mechanical, electrical and plumbing modifications. limited area of floor slab demolition is included in this scope for a non-egress stair under seperate permit. | $2,750,000 |
| Apr 9, 2026 | Completed final sign-off Sep 2026 | 400 Howard St | R M I Mechanical Contractors | 4/fl- add 2 heat pumps, supply fan, exhaust fan, and 3 smoke dampers. (n) ductworks, condenser water piping, ceiling and sidewall grilles, 2 thermostats, and air balance. ref-202602196138Details
4/fl- add 2 heat pumps, supply fan, exhaust fan, and 3 smoke dampers. (n) ductworks, condenser water piping, ceiling and sidewall grilles, 2 thermostats, and air balance. ref-202602196138 | $150,000 |
| Apr 7, 2026 | In progress issued May 2026 | 101 California St | Hathaway Dinwiddie Co. | 13th fl partial non-structural demo for a new horizontal exit separation on the 13th fl & revised smoke narrative for an addition of 2 new convenience stairs on 11th to 12th & 13th & 14thDetails
13th fl partial non-structural demo for a new horizontal exit separation on the 13th fl & revised smoke narrative for an addition of 2 new convenience stairs on 11th to 12th & 13th & 14th | $143,772 |
| Mar 30, 2026 | In progress issued Mar 2026 | 120 Kearny St | Bcci Construction Company | 34/f suite 3400: mechanical and electrical submittal to support approved t.i permit 202602125795. duct distribution is being modified per new space plan. new lighting and power.Details
34/f suite 3400: mechanical and electrical submittal to support approved t.i permit 202602125795. duct distribution is being modified per new space plan. new lighting and power. | $150,000 |
| Mar 26, 2026 | In progress issued Mar 2026 | 550 California St | 4th fl, 450 deferred mep for bpa 202602196216Details
4th fl, 450 deferred mep for bpa 202602196216 | $126,000 | |
| Mar 4, 2026 | In progress issued Mar 2026 | 345 California St | Skyline Construction | 5th floor: mechanical, electrical, and plumbing work for t.i. ref pa #202601294807Details
5th floor: mechanical, electrical, and plumbing work for t.i. ref pa #202601294807 | $175,000 |
| Feb 26, 2026 | In progress issued Mar 2026 | 550 California St | 3rd/f: suite 340. deferred mep for t.i. 202512172011Details
3rd/f: suite 340. deferred mep for t.i. 202512172011 | $218,952 | |
| Feb 20, 2026 | Completed final sign-off Jul 2026 | 525 Market St | Ayoob & Peery Plumbing Co Inc | 30/f: add (84) relocate (130) /fire sprinkler per t.i. job#25-658 reference#2025-0812-2833Details
30/f: add (84) relocate (130) /fire sprinkler per t.i. job#25-658 reference#2025-0812-2833 | $132,915 |
| Feb 5, 2026 | In progress issued Feb 2026 | 550 California St | deferred mep for pa#2025-1222-2376Details
deferred mep for pa#2025-1222-2376 | $636,899 | |
| Dec 30, 2025 | Completed final sign-off Feb 2026 | 55 New Montgomery St | M C S Construction Services | to obatain final inspection for work approved under 202012080508 and 202203160143. all work is completeDetails
to obatain final inspection for work approved under 202012080508 and 202203160143. all work is complete | |
| Dec 22, 2025 | Completed final sign-off Jun 2026 | 650 Davis St | Bcci Construction Company | 2/f - mep submittedal to support approved arch permit. (1) new transfer fan, (2) new heat pumps, (5) new fire dampers, and (1) new smokde damper. ref pa# 202512020740Details
2/f - mep submittedal to support approved arch permit. (1) new transfer fan, (2) new heat pumps, (5) new fire dampers, and (1) new smokde damper. ref pa# 202512020740 | $180,000 |
| Dec 17, 2025 | In progress issued Feb 2026 | 550 California St | suite 410- deferred mep ref 202511038810Details
suite 410- deferred mep ref 202511038810 | $247,752 | |
| Dec 3, 2025 | In progress issued Mar 2026 | 101 California St | Hathaway Dinwiddie Co. | 11th flr - partial non-structural demolition and new tenant fit out of the 11th floor. work includes new partitions, ceiling doors, equipment and finishes. new mepDetails
11th flr - partial non-structural demolition and new tenant fit out of the 11th floor. work includes new partitions, ceiling doors, equipment and finishes. new mep | $6,500,000 |
| Dec 3, 2025 | Completed final sign-off Feb 2026 | 425 Market St | Ayoob & Peery Plumbing Co Inc | 18/f: add (47) relocate (177) fire sprinkler per t.i. job #25-678 ref pa#202508143050Details
18/f: add (47) relocate (177) fire sprinkler per t.i. job #25-678 ref pa#202508143050 | $139,126 |
| Dec 3, 2025 | In progress issued Mar 2026 | 101 California St | Hathaway Dinwiddie Co. | 12th fl: non-structural demolition and new tenant fit out of the 12th floor. work includes new partitions, ceiling doors, equipment and finishes. new mep. create new opening in e) 13th/f slab, ancharage design for aperable partition units attached below e) 13th/f slab. no exterior workDetails
12th fl: non-structural demolition and new tenant fit out of the 12th floor. work includes new partitions, ceiling doors, equipment and finishes. new mep. create new opening in e) 13th/f slab, ancharage design for aperable partition units attached below e) 13th/f slab. no exterior work | $9,700,000 |
| Dec 2, 2025 | In progress issued Dec 2025 | 550 California St | level 9 suite 910: deferred mep 202510066834Details
level 9 suite 910: deferred mep 202510066834 | $673,128 | |
| Dec 1, 2025 | In progress issued Mar 2026 | 101 California St | Hathaway Dinwiddie Co. | 14th fl - partial non-structural demolition and new tenant fit out of the 14th floor. work includes new partitions, ceiling doors, equipment and finishes. new mepDetails
14th fl - partial non-structural demolition and new tenant fit out of the 14th floor. work includes new partitions, ceiling doors, equipment and finishes. new mep | $6,600,000 |
| Nov 25, 2025 | Completed final sign-off May 2026 | 525 Market St | M C S Construction Services | 14/f suite 1460: t.i includes demo of non-structural partitions and build new non-structural partitions. all mep work will be fully engineered and included in this permit. all life safety work will be design-built and submitted separately. fully sprinklered building.Details
14/f suite 1460: t.i includes demo of non-structural partitions and build new non-structural partitions. all mep work will be fully engineered and included in this permit. all life safety work will be design-built and submitted separately. fully sprinklered building. | $550,000 |
| Nov 25, 2025 | In progress issued Jan 2026 | 345 California St | Gci, Inc | 25th fl: interior ti- conference room, pantry & restrooms. demo of non structural partitions, ceilings, finishes. new non structural partitions & glazing new doors & hardware, lighting and ceilings.new mepDetails
25th fl: interior ti- conference room, pantry & restrooms. demo of non structural partitions, ceilings, finishes. new non structural partitions & glazing new doors & hardware, lighting and ceilings.new mep | $1,298,024 |
| Nov 17, 2025 | Completed final sign-off Mar 2026 | 575 Market St | M C S Construction Services | 12th fl - office interior improvement. new non-structural partitions, new glazing, new doors, new electrical, new finishes, new ceiling. existing mechanical to remainDetails
12th fl - office interior improvement. new non-structural partitions, new glazing, new doors, new electrical, new finishes, new ceiling. existing mechanical to remain | $200,000 |
| Nov 10, 2025 | In progress issued Nov 2025 | 550 California St | 4/fl- suite 420- 202508274033- deferred mepDetails
4/fl- suite 420- 202508274033- deferred mep | $193,200 | |
| Nov 7, 2025 | In progress issued Jan 2026 | 333 Pine St | Source Planning And Construction Inc | 1/f suite 100: tenant improvement. change of occupancy from b to m. interior modifications involve selective demolition and construction of new non-load bearing partitions, interior door and glazing system, installation of new light fixtures, new millwork and new finishes.Details
1/f suite 100: tenant improvement. change of occupancy from b to m. interior modifications involve selective demolition and construction of new non-load bearing partitions, interior door and glazing system, installation of new light fixtures, new millwork and new finishes. | $670,500 |
| Nov 6, 2025 | In progress issued Nov 2025 | 550 California St | l 2 suite #250: deferred mep for pa #202509195774Details
l 2 suite #250: deferred mep for pa #202509195774 | $187,200 | |
| Nov 6, 2025 | In progress issued Nov 2025 | 550 California St | 2nd fl, ste 230 deferred mep for pa 202509195772Details
2nd fl, ste 230 deferred mep for pa 202509195772 | $107,064 | |
| Nov 3, 2025 | In progress issued Dec 2025 | 550 California St | 12/fl- suite 1220 - ref 202509034469 for defered mepDetails
12/fl- suite 1220 - ref 202509034469 for defered mep | $500,000 | |
| Oct 30, 2025 | In progress issued Nov 2025 | 505 Montgomery St | level 6: defered mep for pa#202508294230Details
level 6: defered mep for pa#202508294230 | $58,176 | |
| Oct 21, 2025 | In progress issued Oct 2025 | 550 California St | 12th fl suite 1200: selective interior demolition of non structural elements that include interior partitions, doors, finishes, ceilings, lighting, mechanical, electrical outlets and switches. construction includes partitions, doors, finishes, lighting, millwork, mech, electrical and plumbing.Details
12th fl suite 1200: selective interior demolition of non structural elements that include interior partitions, doors, finishes, ceilings, lighting, mechanical, electrical outlets and switches. construction includes partitions, doors, finishes, lighting, millwork, mech, electrical and plumbing. | $498,950 | |
| Oct 21, 2025 | Completed final sign-off Oct 2026 | 555 Mission St | Gci, Inc | 22nd fl: office ti. new partitions, light fixtures, ceilings, millwork, ducting, power and plumbing.Details
22nd fl: office ti. new partitions, light fixtures, ceilings, millwork, ducting, power and plumbing. | $835,312 |
| Oct 6, 2025 | In progress issued Oct 2025 | 101 California St | Source Planning And Construction Inc | 8th fl - minor revision to pa 202412126710 for upgrading interior stair vestibule to 2 hour rated with 90 min rated doors. all other areas within previously approved design are to remain unchanged floor 8Details
8th fl - minor revision to pa 202412126710 for upgrading interior stair vestibule to 2 hour rated with 90 min rated doors. all other areas within previously approved design are to remain unchanged floor 8 | |
| Oct 3, 2025 | Completed final sign-off Jul 2026 | 50 California St | Sc Builders, Inc | 28th floor ti: partitions, doors, ceilings, fixtures & finishes, mep.Details
28th floor ti: partitions, doors, ceilings, fixtures & finishes, mep. | $4,135,200 |
| Sep 26, 2025 | In progress issued Oct 2025 | 550 California St | l3 - ste# 310: deferred mep for pa# 202508294228.Details
l3 - ste# 310: deferred mep for pa# 202508294228. | $613,152 | |
| Sep 18, 2025 | Completed final sign-off Apr 2026 | 535 Mission St | Gci, Inc | 4th fl, ste 400 meps for permit 202508072540 include revistion to 202508072540 and pages a0.00 coversheet, a0.02 egress plan and a1.00 construction plan (clarifying the wall type for mech permit)Details
4th fl, ste 400 meps for permit 202508072540 include revistion to 202508072540 and pages a0.00 coversheet, a0.02 egress plan and a1.00 construction plan (clarifying the wall type for mech permit) | $719,496 |
| Sep 16, 2025 | In progress issued Sep 2025 | 550 California St | suite 360, level 3 deferred mep 202508112721Details
suite 360, level 3 deferred mep 202508112721 | $246,024 | |
| Sep 16, 2025 | In progress issued Sep 2025 | 550 California St | level 3, suite 350 deferred mep for 202508042277Details
level 3, suite 350 deferred mep for 202508042277 | $144,792 | |
| Sep 3, 2025 | Completed final sign-off Aug 2026 | 55 Spear St | Novo Construction Inc | 19th floor:revision to pa #202503172361 to revise phone room 1935, pantry 1976 and conference 1911 and 1910 doors. misc. revisions throughout 19th floor.Details
19th floor:revision to pa #202503172361 to revise phone room 1935, pantry 1976 and conference 1911 and 1910 doors. misc. revisions throughout 19th floor. | |
| Sep 2, 2025 | In progress issued Nov 2025 | 345 California St | Skyline Construction | floor 5: common amenity suite for use by building tenants, includes two conference rooms, pantry, storage, lounge with break area and golf simulator. upgrades to existing mens/womens restroom, new womens restroom, wellness room, two vacant tenant suites & rated corridor.Details
floor 5: common amenity suite for use by building tenants, includes two conference rooms, pantry, storage, lounge with break area and golf simulator. upgrades to existing mens/womens restroom, new womens restroom, wellness room, two vacant tenant suites & rated corridor. | $3,500,000 |
| Aug 26, 2025 | Completed final sign-off Sep 2026 | 525 Market St | Bcci Construction Company | suite 3000- office ti to include new partitions, offices, conference rooms, mechanical ducting for heating & cooling, lighting & plumbing. structural submittal deferredDetails
suite 3000- office ti to include new partitions, offices, conference rooms, mechanical ducting for heating & cooling, lighting & plumbing. structural submittal deferred | $3,889,000 |
| Aug 8, 2025 | In progress issued Aug 2025 | 550 California St | l9 suite 920: deffed mep for pa #202506309807Details
l9 suite 920: deffed mep for pa #202506309807 | $334,152 | |
| Aug 8, 2025 | In progress issued Aug 2025 | 550 California St | 9th fl, ste 930 deferred mep for pa 202506309809Details
9th fl, ste 930 deferred mep for pa 202506309809 | $241,488 | |
| Aug 7, 2025 | Completed final sign-off Apr 2026 | 3 Embarcadero Center | Principal Builders Inc. | 25/f, ste 2500. ref arch set #202507160935. mep for this project.Details
25/f, ste 2500. ref arch set #202507160935. mep for this project. | $2,900,000 |
| Aug 5, 2025 | Completed final sign-off Jul 2026 | 425 Market St | Build Group Inc. | 26/f: meps for tenant improvement permit 202507090436.Details
26/f: meps for tenant improvement permit 202507090436. | |
| Jul 24, 2025 | In progress issued Aug 2025 | 550 California St | level 10 suite 1040. deferred mep for pa #202506118512.Details
level 10 suite 1040. deferred mep for pa #202506118512. | $283,752 | |
| Jul 24, 2025 | In progress issued Aug 2025 | 550 California St | 10/f - #1010: deferred mep for pa # 202506118511.Details
10/f - #1010: deferred mep for pa # 202506118511. | $338,688 | |
| Jul 15, 2025 | Completed final sign-off Feb 2026 | 555 Mission St | Gci, Inc | 28/f -revision to pa # 2024-1217-7023 including new office, change of room from conference to office, change room from office to conference, new phone booths at three locations, new light fixtures and electrical work.Details
28/f -revision to pa # 2024-1217-7023 including new office, change of room from conference to office, change room from office to conference, new phone booths at three locations, new light fixtures and electrical work. | |
| Jun 5, 2025 | Completed final sign-off Jan 2026 | 535 Mission St | Gci, Inc | 3rd fl conference ceneter: ti include demo of non structural partitions & building (n) non structural partitions. all new or revised mep included in this permit. life safety & fire alarm/sprinklers will be design build and submitted separately if needed. assembly area partition is deffered submittalDetails
3rd fl conference ceneter: ti include demo of non structural partitions & building (n) non structural partitions. all new or revised mep included in this permit. life safety & fire alarm/sprinklers will be design build and submitted separately if needed. assembly area partition is deffered submittal | $987,000 |
| Apr 30, 2025 | In progress issued May 2025 | 550 California St | 10th fl suite 1030: selective interior demo of non structural elements. (n) interior partitions, doors, finishes, lighting, mechanical and electrical outlets & switches. refer to mech & elec plans. f/l/s and fire sprinkler drawings submitted under separate permit.Details
10th fl suite 1030: selective interior demo of non structural elements. (n) interior partitions, doors, finishes, lighting, mechanical and electrical outlets & switches. refer to mech & elec plans. f/l/s and fire sprinkler drawings submitted under separate permit. | $350,000 | |
| Apr 24, 2025 | In progress issued May 2025 | 550 California St | 3rd fl - selective int'r demo of non-struc'l elements inlcuding but not limited to interior partitions, doors, finishes, clg, lighting, mech & elec outlets & switches refer to mech & elec plans. scope includes rr accessibility upgrades. fls & fire sprinkler drwg's to be submitted separately. scopeDetails
3rd fl - selective int'r demo of non-struc'l elements inlcuding but not limited to interior partitions, doors, finishes, clg, lighting, mech & elec outlets & switches refer to mech & elec plans. scope includes rr accessibility upgrades. fls & fire sprinkler drwg's to be submitted separately. scope | $100,000 | |
| Apr 23, 2025 | Completed final sign-off Apr 2026 | 201 03rd St | Hp Build | 9/f: ti including- demo of non structural partitions, doors, sidelights, millwork, ceiling, lighting, and finishes. new construction includes new non structural partitions, doors, sidelights, millwork, ceiling, lighting, and finishes. upgrades to existing restrooms and construction of new accessibleDetails
9/f: ti including- demo of non structural partitions, doors, sidelights, millwork, ceiling, lighting, and finishes. new construction includes new non structural partitions, doors, sidelights, millwork, ceiling, lighting, and finishes. upgrades to existing restrooms and construction of new accessible | $3,967,600 |
| Apr 22, 2025 | Completed final sign-off Nov 2025 | 1 California St | Gci, Inc | 18/f: deferred mechanical and electrical. ref pa# 202502120145.Details
18/f: deferred mechanical and electrical. ref pa# 202502120145. | $10,000 |
| Apr 10, 2025 | Completed final sign-off May 2026 | 601 Clement St | Lombardi Property Development | prop h: rev #202405031359: include mezzanine scope & cbc compliant accessible lift to access mezzanine. new non-structural partitions, all-gender restrooms, light fixtures & finishes. medical offices t/i to building counselling offices. no ambulatory care on site.Details
prop h: rev #202405031359: include mezzanine scope & cbc compliant accessible lift to access mezzanine. new non-structural partitions, all-gender restrooms, light fixtures & finishes. medical offices t/i to building counselling offices. no ambulatory care on site. | $800,000 |
| Apr 7, 2025 | Completed final sign-off Sep 2025 | 555 California St | Skyline Construction | revision to pa # 2024-1021-3343 revised lobby area fl plan. deleted focus room, relocated reception desk and closet. revision to conference room. mech and electrical revisionsDetails
revision to pa # 2024-1021-3343 revised lobby area fl plan. deleted focus room, relocated reception desk and closet. revision to conference room. mech and electrical revisions | $20,000 |
| Apr 2, 2025 | Completed final sign-off Oct 2025 | 400 Howard St | Sc Builders, Inc | 4th fl t.i.work includes interoir non structural demo of partitons, light fixtures, ceiling assembly, millwork, plumbing and finishes. build back non structural demising partitons, light fixtures,ceiling assembly, power outlets, finishesDetails
4th fl t.i.work includes interoir non structural demo of partitons, light fixtures, ceiling assembly, millwork, plumbing and finishes. build back non structural demising partitons, light fixtures,ceiling assembly, power outlets, finishes | $3,283,298 |
| Mar 31, 2025 | Completed final sign-off Jan 2026 | 500 Howard St | Novo Construction Inc | 5th fl: interior ti. include paint throughout. removal of existing walls, ceilings and finishes. new interior construction of walls, new wall & floor finishes. mechanical, electrical ,plumbing & structural includedDetails
5th fl: interior ti. include paint throughout. removal of existing walls, ceilings and finishes. new interior construction of walls, new wall & floor finishes. mechanical, electrical ,plumbing & structural included | $5,416,864 |
| Mar 17, 2025 | Completed final sign-off Aug 2026 | 55 Spear St | Novo Construction Inc | interior tenant improvement on the 19th fl of approx 8000 sq ft. mech,ele, plumbing and structural includedDetails
interior tenant improvement on the 19th fl of approx 8000 sq ft. mech,ele, plumbing and structural included | $925,000 |
| Mar 10, 2025 | In progress issued Mar 2025 | 345 California St | Gci, Inc | 31st fl - revision to pa 202312132454 updated floor plans door schedule added conference room, reconfigured team rooms/ofces in lieu of open office work stations, updated restroom sheets (34) vav boxes, (2) heat pumps added electrical workDetails
31st fl - revision to pa 202312132454 updated floor plans door schedule added conference room, reconfigured team rooms/ofces in lieu of open office work stations, updated restroom sheets (34) vav boxes, (2) heat pumps added electrical work | |
| Mar 7, 2025 | In progress issued Mar 2025 | 50 California St | R.M.R. Construction Company | 26th fl, partial floor remodel sub dividing existing office suite 2600 into 2 suites. scope includes demo and construction of non-structural partitions, light fixtures, ceiling assembly, and floor finishes; remodel for accessbility compliance a women's toilet compartment.Details
26th fl, partial floor remodel sub dividing existing office suite 2600 into 2 suites. scope includes demo and construction of non-structural partitions, light fixtures, ceiling assembly, and floor finishes; remodel for accessbility compliance a women's toilet compartment. | $440,198 |
| Feb 26, 2025 | Completed final sign-off Feb 2026 | 500 Howard St | Novo Construction Inc | 3rd fl -ti to include new nonstructural partitions, paint, wall covering on, privacy glass film; repairs to existing conditions. mep includedDetails
3rd fl -ti to include new nonstructural partitions, paint, wall covering on, privacy glass film; repairs to existing conditions. mep included | $4,721,444 |
| Feb 24, 2025 | Completed final sign-off Dec 2025 | 500 Howard St | Novo Construction Inc | 5th fl- removal of (e) walls, ceilings, millwork and finishes ab017Details
5th fl- removal of (e) walls, ceilings, millwork and finishes ab017 | $175,000 |
| Feb 21, 2025 | Completed final sign-off May 2025 | 500 Howard St | Novo Construction Inc | 8th fl- revision to pa #202412237306 to add selective new demo for new exhaust duct, new environmental exhuast louver added hand and prep sink, added power, new hot water pump. new exhaust fan, under floor terminal unit and equipment anchorageDetails
8th fl- revision to pa #202412237306 to add selective new demo for new exhaust duct, new environmental exhuast louver added hand and prep sink, added power, new hot water pump. new exhaust fan, under floor terminal unit and equipment anchorage | $75,000 |
| Feb 20, 2025 | Completed final sign-off Oct 2025 | 388 Market St | Bevilacqua & Sons | 14/f-ste 1420: demolition of (e) flr and (e) partitions, (e) ceiling grid/tile to remain, (e) lighting to remain and some to be relocated. the new propsed design includes: offices, break area, open office area, one conference room and new finishes.Details
14/f-ste 1420: demolition of (e) flr and (e) partitions, (e) ceiling grid/tile to remain, (e) lighting to remain and some to be relocated. the new propsed design includes: offices, break area, open office area, one conference room and new finishes. | $285,000 |
| Feb 19, 2025 | In progress issued Mar 2025 | 550 California St | 2/f: selective demo of non-structural elements including but not limited to int. partitions, doors, finishes, ceilings, lighting, mech/elec outs and switches per mech/elec plans. restroom accessibility upgrades. f/l/s and fire sprinkler drawings under separate permit. scope does not affect fixtureDetails
2/f: selective demo of non-structural elements including but not limited to int. partitions, doors, finishes, ceilings, lighting, mech/elec outs and switches per mech/elec plans. restroom accessibility upgrades. f/l/s and fire sprinkler drawings under separate permit. scope does not affect fixture | $75,000 | |
| Feb 10, 2025 | Completed final sign-off Oct 2025 | 388 Market St | Bevilacqua & Sons | 14/f-ste 1450: demolition of (e) flr finishes and (e) partitions and (e) ceiling. the new propsed design includes: offices, break area, open office area, one conference room and new ceiling.Details
14/f-ste 1450: demolition of (e) flr finishes and (e) partitions and (e) ceiling. the new propsed design includes: offices, break area, open office area, one conference room and new ceiling. | $199,500 |
| Feb 10, 2025 | Completed final sign-off Oct 2025 | 388 Market St | Bevilacqua & Sons | 14/f-ste 1460: demolition of (e) flr finishes and (e) partitions and (e) ceiling. the new proposed design includes: offices, break area, open office area, one conference room and new ceiling.Details
14/f-ste 1460: demolition of (e) flr finishes and (e) partitions and (e) ceiling. the new proposed design includes: offices, break area, open office area, one conference room and new ceiling. | $160,000 |
| Jan 10, 2025 | Completed final sign-off Aug 2025 | 500 Howard St | Novo Construction Inc | 4th floor: selective demo of millwork, finshes and wall penetrations, mew carpet, paint and acoustic panels, new exterior window louver alteration of drinking fountain niche, mep includedDetails
4th floor: selective demo of millwork, finshes and wall penetrations, mew carpet, paint and acoustic panels, new exterior window louver alteration of drinking fountain niche, mep included | $325,000 |
| Dec 26, 2024 | Completed final sign-off Jul 2025 | 1 California St | Novo Construction Inc | 8th floor; interior demolition of ceiling height partitions construction of new partiations, doors, glazing, millowrk, finishes, associated mechanical, electrical, and plumbing.Details
8th floor; interior demolition of ceiling height partitions construction of new partiations, doors, glazing, millowrk, finishes, associated mechanical, electrical, and plumbing. | $2,500,000 |
| Dec 23, 2024 | Completed final sign-off May 2025 | 500 Howard St | Novo Construction Inc | 8/fl- ti to convert storage to pantry to include (n) refrigator, freezer, food storage and sinks. mep included.Details
8/fl- ti to convert storage to pantry to include (n) refrigator, freezer, food storage and sinks. mep included. | $250,000 |
| Dec 17, 2024 | Completed final sign-off Feb 2026 | 555 Mission St | Gci, Inc | 28/f: interior tenant improvement including new partitions, light fixtures, ceiling assemblies, millwork, and plumbing fixtures. mechanical, electrical, and plumbing drawings included. fire life safety and sprinkler under separate permit.Details
28/f: interior tenant improvement including new partitions, light fixtures, ceiling assemblies, millwork, and plumbing fixtures. mechanical, electrical, and plumbing drawings included. fire life safety and sprinkler under separate permit. | $965,775 |