Permit GraphShortlistSan Francisco building permits since 2000

How long do stairs permits take in San Francisco's Russian Hill neighborhood?

In the Russian Hill neighborhood of San Francisco, of the 20 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 2 days, down from 15 days a year earlier. Of the 14 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 34 days of being issued, down from 68 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's Russian HillneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/russian-hill/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202620 issued216 issued15
Permit issued to final sign-offOctober 2023 through September 202414 finished3416 finished68

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q37501320too recent
2026-Q25220too recent
2026-Q155017525280too recent
2025-Q49848540too recent
2025-Q34440too recent
2025-Q23330too recent
2025-Q1652814430too recent
2024-Q45440too recent
2024-Q33220yes
2024-Q275529230yes
2024-Q16619440yes
2023-Q4660345201710yes
2023-Q35514465873210yes
2023-Q24321yes
2023-Q13330yes
2022-Q49904676925801yes
2022-Q398242645256312yes
2022-Q212129477102687961yes
2022-Q175253232yes
2021-Q44211yes
2021-Q3770377583140yes
2021-Q2862871143yes
2021-Q13220yes
2020-Q44440yes
2020-Q310747761326681yes
2020-Q22220yes
2020-Q1975585072877610yes
2019-Q415121034111974051yes
2019-Q3760416524431yes
2019-Q276463643yes
2019-Q1889324844yes
2018-Q48619640853774000yes
2018-Q313130232111246571yes
2018-Q27623005811,0091yes
2018-Q16641,42661903980yes
2017-Q47702995627411yes
2017-Q36641425263621yes
2017-Q2772390261387341yes
2017-Q13220yes
2016-Q412101616193491,0201yes
2016-Q36605085411,3151yes
2016-Q2971661563890yes
2016-Q15569741yes
2015-Q466712941yes
2015-Q312112067682641,2942yes
2015-Q21092315373561,1111yes
2015-Q1774040042yes
2014-Q4109561,27783646971yes
2014-Q31092526172451,5572yes
2014-Q2121289691751,5102yes
2014-Q177023951625011yes
2013-Q49822553446223yes
2013-Q31110425383429440yes
2013-Q2861519753735990yes
2013-Q15503532yes
2012-Q4771117556882yes
2012-Q310976871917521yes
2012-Q21192711761032921yes
2012-Q11313115911605761yes
2011-Q465540831yes
2011-Q31010215661221,2701yes
2011-Q2151506810512743yes
2011-Q11110121439693821yes
2010-Q4660506763250yes
2010-Q3111001891391442yes
2010-Q255323832yes
2010-Q1662711841yes
2009-Q4993708952310yes
2009-Q3662228953656240yes
2009-Q21086827643yes
2009-Q1109341592386390yes
2008-Q411114194091873870yes
2008-Q3121101581605113yes
2008-Q21814225591113931yes
2008-Q110103224171014940yes
2007-Q4121103089834351yes
2007-Q311110371802362yes
2007-Q2760241yes
2007-Q155024540yes
2006-Q41210067842581yes
2006-Q31414085131053711yes
2006-Q213130010722062yes
2006-Q165030441yes
2005-Q4101001865941541yes
2005-Q31010010591181951yes
2005-Q21313042610823981yes
2005-Q1550020yes
2004-Q48704761402220yes
2004-Q316130081562664yes
2004-Q27706261775321yes
2004-Q176021033yes
2003-Q44431yes
2003-Q31212007423112yes
2003-Q2870932yes
2003-Q18809430yes
2002-Q45507821yes
2002-Q3880647952590yes
2002-Q21010014551002101yes
2002-Q1650830yes
2001-Q46603641yes
2001-Q3131301229792920yes
2001-Q2201804012532290yes
2001-Q112110807802930yes
2000-Q477018830yes
2000-Q34420yes
2000-Q28804230yes
2000-Q18605020yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

97 of the 887 stairs permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Russian Hill neighborhood

Shown apart, with their own page here: bathroom remodel (3,069 filed, 2,224 finished; contractors); kitchen remodel (3,022 filed, 2,219 finished; contractors); stairs (887 filed, 594 finished; contractors); deck (425 filed, 281 finished; contractors); roof deck (310 filed, 176 finished; contractors). Other types: 14,642 permits. All permits in San Francisco's Russian Hill neighborhood

Nearby neighborhoods

Nob Hill, North Beach, Chinatown; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.