How long do deck permits take in San Francisco's Oceanview/Merced/Ingleside neighborhood?

In the Oceanview/Merced/Ingleside neighborhood of San Francisco, of the 12 deck permits filed from October 2025 through September 2026 that have been issued, half were issued within 18 days, the same as a year earlier. Of the 10 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 240 days of being issued, up from 138 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long deck permits take in San Francisco'sOceanview/Merced/Ingleside neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge02004006008002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/oceanview-merced-ingleside/deck · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202612 issued1827 issued18
Permit issued to final sign-offOctober 2023 through September 202410 finished24016 finished138

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 164 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42100too recent
2026-Q32000too recent
2026-Q286184020too recent
2026-Q17420too recent
2025-Q46210too recent
2025-Q36613819430too recent
2025-Q28714575251470too recent
2025-Q14430too recent
2024-Q412102313761462530too recent
2024-Q31212815562404100yes
2024-Q24210yes
2024-Q13330yes
2023-Q43300yes
2023-Q39844595744222yes
2023-Q26516346251293431yes
2023-Q14210yes
2022-Q4761010651435890yes
2022-Q34411yes
2022-Q255635340yes
2022-Q17434yes
2021-Q4881817051404143yes
2021-Q37739459943yes
2021-Q2773251061402811yes
2021-Q14421yes
2020-Q42220yes
2020-Q33320yes
2020-Q24220yes
2020-Q1768897452827310yes
2019-Q41181842941yes
2019-Q39819473876221,0890yes
2019-Q28815489652574313yes
2019-Q1861929441yes
2018-Q41072117262303840yes
2018-Q3872538853229282yes
2018-Q211102024082064262yes
2018-Q177281,40743yes
2017-Q4761515251564921yes
2017-Q3873429441yes
2017-Q255628751562390yes
2017-Q176411242yes
2016-Q41191921252033255yes
2016-Q3662451952536211yes
2016-Q28811761571814791yes
2016-Q1771127642yes
2015-Q44331yes
2015-Q3661018462486840yes
2015-Q24321yes
2015-Q175527251772,3450yes
2014-Q477491133yes
2014-Q376350251302901yes
2014-Q2662626762494180yes
2014-Q155727440yes
2013-Q43330yes
2013-Q34440yes
2013-Q25572,03340yes
2013-Q16667553145471yes
2012-Q42220yes
2012-Q33321yes
2012-Q25440yes
2012-Q14422yes
2011-Q43330yes
2011-Q3870456901331yes
2011-Q2181702614572111yes
2011-Q18844981422870yes
2010-Q455110640yes
2010-Q34440yes
2010-Q26628961121240yes
2010-Q15501526950yes
2009-Q47601243yes
2009-Q3111033716821354yes
2009-Q21110yes
2009-Q166020648890yes
2008-Q44440yes
2008-Q35430yes
2008-Q2988556801280yes
2008-Q13330yes
2007-Q45509841yes
2007-Q3870475201131yes
2007-Q2660041yes
2007-Q14311yes
2006-Q4550031yes
2006-Q3990626844111yes
2006-Q27702306663921yes
2006-Q14420yes
2005-Q44311yes
2005-Q32100yes
2005-Q25501085671940yes
2005-Q12220yes
2004-Q41110yes
2004-Q32220yes
2004-Q277045120yes
2004-Q155012431yes
2003-Q42210yes
2003-Q34440yes
2003-Q26510235731yes
2003-Q13320yes
2002-Q43330yes
2002-Q36330yes
2002-Q23310yes
2002-Q1661421630yes
2001-Q44420yes
2001-Q37701125633360yes
2001-Q22210yes
2001-Q13320yes
2000-Q41110yes
2000-Q22210yes
2000-Q14310yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

70 of the 605 deck permits filed since 2000 (12%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Oceanview/Merced/Ingleside neighborhood

Shown apart, with their own page here: bathroom remodel (2,842 filed, 2,115 finished; contractors); kitchen remodel (2,071 filed, 1,499 finished; contractors); stairs (917 filed, 606 finished; contractors); deck (605 filed, 389 finished; contractors). Other types: 9,103 permits. All permits in San Francisco's Oceanview/Merced/Ingleside neighborhood

Nearby neighborhoods

Outer Mission, Lakeshore, West of Twin Peaks; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.