How long do bathroom remodel permits take in San Francisco's Mission neighborhood?

In the Mission neighborhood of San Francisco, of the 171 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 1 day, the same as a year earlier. Of the 108 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 146 days of being issued, down from 192 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sMission neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/mission/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026171 issued1163 issued1
Permit issued to final sign-offOctober 2023 through September 2024108 finished146126 finished192

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42100too recent
2026-Q34832027646740too recent
2026-Q2534804718901290too recent
2026-Q1524514619941640too recent
2025-Q45346296321142860too recent
2025-Q35755052371332970too recent
2025-Q247451176261303440too recent
2025-Q13332472211472950too recent
2024-Q43531039251363040too recent
2024-Q32826272221403110yes
2024-Q25150172351794910yes
2024-Q13533042271493500yes
2023-Q433310212241393300yes
2023-Q343402962715451214yes
2023-Q246444152362387746yes
2023-Q14239079321746554yes
2022-Q44543590311905557yes
2022-Q346420242331774806yes
2022-Q27366676532466318yes
2022-Q171640425321057512yes
2021-Q498936112651724458yes
2021-Q3787401065920070111yes
2021-Q274710615715853511yes
2021-Q1817301556119046210yes
2020-Q4716422024718574515yes
2020-Q3595382794118057813yes
2020-Q2292414201162397884yes
2020-Q1666302484822281712yes
2019-Q4787194595929494610yes
2019-Q359550444213662410yes
2019-Q271651575116852912yes
2019-Q1645941154819755810yes
2018-Q4958781586629480118yes
2018-Q3756931274922649714yes
2018-Q2666272654222849518yes
2018-Q1656022233813088819yes
2017-Q4797663085723871013yes
2017-Q3616082824213649613yes
2017-Q2726401004612650818yes
2017-Q164627474502071,0599yes
2016-Q4817011005118766217yes
2016-Q363584303502787145yes
2016-Q2908552045925386721yes
2016-Q193850796616673815yes
2015-Q4847802096120572112yes
2015-Q3878011986223671714yes
2015-Q263601339451645618yes
2015-Q176702171542228789yes
2014-Q461583149532075142yes
2014-Q381750316321759411yes
2014-Q2878032766124656513yes
2014-Q167636794518546416yes
2013-Q4848131356420191114yes
2013-Q386831856925369811yes
2013-Q26260061531684606yes
2013-Q15656014451224688yes
2012-Q448462463423248511yes
2012-Q35453156432066329yes
2012-Q26059195511543815yes
2012-Q15655022471954614yes
2011-Q44138166342174423yes
2011-Q35450013401864828yes
2011-Q24947016411444452yes
2011-Q13635237311193684yes
2010-Q457571203461526288yes
2010-Q347460168391634675yes
2010-Q25048015421404025yes
2010-Q1373709281305465yes
2009-Q442400190301625546yes
2009-Q34039026321243576yes
2009-Q24745060371584793yes
2009-Q13433082282063713yes
2008-Q45146038361274425yes
2008-Q36159019431244578yes
2008-Q255540753412237712yes
2008-Q14542041271292985yes
2007-Q4585201522615235210yes
2007-Q38375073813638118yes
2007-Q2545402361364988yes
2007-Q14545094291032665yes
2006-Q42828044181143574yes
2006-Q3464600251623457yes
2006-Q2404000241343264yes
2006-Q1525200341842786yes
2005-Q4343300242144385yes
2005-Q340390205221704036yes
2005-Q24645070261844125yes
2005-Q1323200212004346yes
2004-Q4262600151074084yes
2004-Q33433062171032507yes
2004-Q23636010191633197yes
2004-Q124240091432437yes
2003-Q42626082141185482yes
2003-Q3222200121122253yes
2003-Q22724093121452613yes
2003-Q125250015954092yes
2002-Q4272700171314372yes
2002-Q3232300171132783yes
2002-Q2282706161183603yes
2002-Q1242402615853281yes
2001-Q41717023101542730yes
2001-Q33030096141164611yes
2001-Q2242400101863360yes
2001-Q12524092161905510yes
2000-Q42323047111212030yes
2000-Q32626020151877510yes
2000-Q22020065101386880yes
2000-Q116150092514730yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

733 of the 5,544 bathroom remodel permits filed since 2000 (13%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Mission neighborhood

Shown apart, with their own page here: bathroom remodel (5,544 filed, 3,781 finished; contractors); kitchen remodel (5,121 filed, 3,441 finished; contractors); stairs (3,714 filed, 2,590 finished; contractors); deck (1,135 filed, 786 finished; contractors); roof deck (332 filed, 202 finished; contractors). Other types: 41,115 permits. All permits in San Francisco's Mission neighborhood

Nearby neighborhoods

Castro/Upper Market, Noe Valley, Potrero Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.