How long do stairs permits take in San Francisco's Chinatown neighborhood?

In the Chinatown neighborhood of San Francisco, of the 16 stairs permits filed from October 2025 through September 2026 that have been issued, half were issued within 34 days, up from 30 days a year earlier. Of the 7 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 104 days of being issued, down from 130 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long stairs permits take in San Francisco's ChinatownneighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge01002003004005002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/chinatown/stairs · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 202616 issued3422 issued30
Permit issued to final sign-offOctober 2023 through September 20247 finished1049 finished130

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 7 days to issue and 175 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q41000too recent
2026-Q39794810too recent
2026-Q22200too recent
2026-Q12200too recent
2025-Q455346710too recent
2025-Q310103017552232690too recent
2025-Q24420too recent
2025-Q13320too recent
2024-Q4558817430too recent
2024-Q35510740130yes
2024-Q21110yes
2024-Q14320yes
2023-Q41110yes
2023-Q3654328621yes
2023-Q25431yes
2023-Q13211yes
2022-Q43330yes
2022-Q34412yes
2022-Q21110yes
2022-Q166266724yes
2021-Q43321yes
2021-Q32110yes
2021-Q22220yes
2021-Q14330yes
2020-Q44440yes
2020-Q33220yes
2020-Q21101yes
2020-Q13321yes
2019-Q466824064486120yes
2019-Q34431yes
2019-Q24420yes
2019-Q11110yes
2018-Q41110yes
2018-Q31100yes
2018-Q22202yes
2018-Q14440yes
2017-Q42220yes
2017-Q33202yes
2017-Q25440yes
2017-Q11110yes
2016-Q43211yes
2016-Q33210yes
2016-Q22110yes
2016-Q14330yes
2015-Q44431yes
2015-Q376179252452791yes
2015-Q22220yes
2014-Q45431yes
2014-Q35412yes
2014-Q24440yes
2014-Q15320yes
2013-Q4768986453467761yes
2013-Q39919769334710yes
2013-Q210968081203781yes
2013-Q12210yes
2012-Q48824382071,2820yes
2012-Q37737952985231yes
2012-Q25440yes
2012-Q13321yes
2011-Q4550351121770yes
2011-Q34430yes
2011-Q23330yes
2011-Q12220yes
2010-Q476358762444110yes
2010-Q33320yes
2010-Q24330yes
2010-Q13321yes
2009-Q43201yes
2009-Q36623441yes
2009-Q23330yes
2009-Q1551589732yes
2008-Q42220yes
2008-Q33321yes
2008-Q22220yes
2008-Q13321yes
2007-Q4661213951372971yes
2007-Q36602642yes
2007-Q24440yes
2007-Q12220yes
2006-Q4556815051542400yes
2006-Q3770566962701yes
2006-Q25440yes
2006-Q12220yes
2005-Q4880051341541yes
2005-Q37702386442881yes
2005-Q28802278252930yes
2005-Q1880737491110yes
2004-Q499007601640yes
2004-Q3664413823yes
2004-Q22211yes
2004-Q12201yes
2003-Q455017231yes
2003-Q31110yes
2003-Q25501240yes
2003-Q14430yes
2002-Q44440yes
2002-Q34440yes
2002-Q2884419541yes
2002-Q15501340yes
2001-Q41100yes
2001-Q32210yes
2001-Q13320yes
2000-Q43330yes
2000-Q32200yes
2000-Q24410yes
2000-Q14410yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

47 of the 431 stairs permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Chinatown neighborhood

Shown apart, with their own page here: bathroom remodel (823 filed, 547 finished; contractors); kitchen remodel (802 filed, 556 finished; contractors); stairs (431 filed, 289 finished; contractors); roof deck (63 filed, 35 finished; contractors); deck (61 filed, 38 finished; contractors). Other types: 13,839 permits. All permits in San Francisco's Chinatown neighborhood

Nearby neighborhoods

Financial District/South Beach, North Beach, Nob Hill; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.