How long do bathroom remodel permits take in San Francisco's Castro/Upper Market neighborhood?

In the Castro/Upper Market neighborhood of San Francisco, of the 152 bathroom remodel permits filed from October 2025 through September 2026 that have been issued, half were issued within 0 days, the same as a year earlier. Of the 105 permits filed from October 2023 through September 2024 that have reached final sign-off, half did so within 177 days of being issued, up from 168 days the year before.

From the city’s permit records, by the quarter each permit was filed. Data as of 8 October 2026. How to cite this · How this is calculated

How long until a permit is issued, and until final sign-off?

How long bathroom remodel permits take in San Francisco'sCastro/Upper Market neighborhoodMedian days from filing to permit issuedMedian days from issue to final sign-offToo recent to judge0501001502002503002017201820192020202120222023202420252026DaysSource: San Francisco Department of Building Inspection permit data via DataSF, analysis by Permit Graph(permitgraph.org), CC BY 4.0.permitgraph.org/neighborhoods/castro-upper-market/bathroom · Data as of 8 October 2026By the quarter the permit was filed. A median counts only permits that finished the stage, so recent quarterslook faster than they will end up. Gaps: fewer than 5 permits.

This chart as an image (SVG), with its title, source and date, free to embed under CC BY 4.0.

At a glance

StagePermits filedPermits countedMedian daysCounted a year earlierMedian a year earlier
Filed to permit issuedOctober 2025 through September 2026152 issued0165 issued0
Permit issued to final sign-offOctober 2023 through September 2024105 finished177130 finished168

“Counted” is the permits the median was taken over: those filed in the window that have been issued, or that have reached final sign-off. The first stage covers the last four complete quarters, since most permits are issued within the year. The second covers the last four quarters that ended two or more years ago, so that most of their permits have had time to finish. Citywide, the median was 0 days to issue and 169 days from issue to final over the same quarters.

Every quarter since 2000

Quarter filedFiledIssuedMedian days to issueSlowest 10%Reached finalMedian days issue to finalSlowest 10%Never finaledSettled
2026-Q42000too recent
2026-Q3302301330too recent
2026-Q2484205516861260too recent
2026-Q14342069231261910too recent
2025-Q447451257221243000too recent
2025-Q352513145371412840too recent
2025-Q23636094251272590too recent
2025-Q14038099241063680too recent
2024-Q440402157291743710too recent
2024-Q334320118241703880yes
2024-Q23938060321624040yes
2024-Q13735037332085450yes
2023-Q422210251161955491yes
2023-Q351502663616749011yes
2023-Q24036046311584313yes
2023-Q14338032312054946yes
2022-Q447435402322095347yes
2022-Q34440065311535947yes
2022-Q257521104452167996yes
2022-Q15554158422267258yes
2021-Q44947870402581,0385yes
2021-Q359571345462478826yes
2021-Q26964089572656728yes
2021-Q1535002793316660213yes
2020-Q460580194441735459yes
2020-Q357539120452045948yes
2020-Q213136312101826993yes
2020-Q150470205332248209yes
2019-Q456516853919764711yes
2019-Q356511206432311,0216yes
2019-Q2494802243317383111yes
2019-Q154481150441705504yes
2018-Q44038179351474281yes
2018-Q349460156371553765yes
2018-Q253486168401824562yes
2018-Q141404160321827047yes
2017-Q440361134302027916yes
2017-Q351500182361985839yes
2017-Q252500263401697244yes
2017-Q1666221115017164811yes
2016-Q452452331332466586yes
2016-Q359551673720956311yes
2016-Q24946017361216137yes
2016-Q16056052422017459yes
2015-Q445430902814672111yes
2015-Q354514440432576965yes
2015-Q254513191421926228yes
2015-Q156541121471714676yes
2014-Q460562207451355656yes
2014-Q357560105491756715yes
2014-Q251480279361731,05910yes
2014-Q159561102431204056yes
2013-Q442392264282164927yes
2013-Q35652038381725259yes
2013-Q25150028431155045yes
2013-Q151511126431625874yes
2012-Q45854034412695137yes
2012-Q35855038522023621yes
2012-Q24545033351353729yes
2012-Q14242034361683984yes
2011-Q44442031351463772yes
2011-Q35047083401474684yes
2011-Q251490124451736442yes
2011-Q13735019271273655yes
2010-Q442391105341706512yes
2010-Q336360234282116047yes
2010-Q24240014321577833yes
2010-Q13837038321623372yes
2009-Q42626076251254710yes
2009-Q35353027421944705yes
2009-Q240391134362215851yes
2009-Q13433012292165052yes
2008-Q43533074241924352yes
2008-Q335330184261853972yes
2008-Q238380409291724494yes
2008-Q145430171311533506yes
2007-Q45248080281583586yes
2007-Q3555203291252706yes
2007-Q25756079392086446yes
2007-Q1454402371453872yes
2006-Q4414007291614223yes
2006-Q3515100361644544yes
2006-Q2585700381825274yes
2006-Q14443087311727352yes
2005-Q4373500252792,3165yes
2005-Q3333200211904148yes
2005-Q2333200221944495yes
2005-Q130300671521937212yes
2004-Q4191900101202236yes
2004-Q3313000201833435yes
2004-Q239370140211203889yes
2004-Q122220155151965444yes
2003-Q4181805121122332yes
2003-Q32120019121303085yes
2003-Q22625052141545515yes
2003-Q12423052131952707yes
2002-Q415150170102512934yes
2002-Q3252300121592465yes
2002-Q22120067131532722yes
2002-Q123220284111274566yes
2001-Q413130237911961yes
2001-Q327260153142136232yes
2001-Q221210122111642030yes
2001-Q11918042131272150yes
2000-Q41715026121766200yes
2000-Q32322025151173570yes
2000-Q22120065101382710yes
2000-Q12020082101893200yes

A blank median means fewer than 5 permits behind it: issued permits for the first stage, and for the second, finished permits whose final is dated after their issue (a permit never issued has no span). “Slowest 10%” is the 90th percentile: one permit in ten took at least this long. Download the table as CSV or JSON; both carry the source, license and data date.

What the numbers leave out

498 of the 4,510 bathroom remodel permits filed since 2000 (11%) have no final sign-off 3 years after they were issued or, if never issued, filed. A median over finished permits understates the real wait: the permits that never finish are not in it. Inspection records are not yet included: “final sign-off” is the city’s own completion date on the permit.

Project types in San Francisco's Castro/Upper Market neighborhood

Shown apart, with their own page here: bathroom remodel (4,510 filed, 3,216 finished; contractors); kitchen remodel (3,859 filed, 2,761 finished; contractors); stairs (2,478 filed, 1,664 finished; contractors); deck (1,649 filed, 1,111 finished; contractors); roof deck (322 filed, 187 finished; contractors). Other types: 22,946 permits. All permits in San Francisco's Castro/Upper Market neighborhood

Nearby neighborhoods

Haight Ashbury, Twin Peaks, Noe Valley; all of San Francisco; every neighborhood compared.

How this is calculated

Approved means the city issued the permit: the permit’s issue date. The first stage counts days from the filing date to the issue date, over permits issued on or after they were filed. Final sign-off means the city’s own status for the permit is “complete”, with its completion date; this site does not yet read inspection records, so the inspection date is not a separate stage. The second stage counts days from the issue date to the completion date, over permits that have reached it.

Permits are grouped by the quarter they were filed. A quarter’s median counts only its permits that have finished the stage, so recent quarters look faster than they will end up: their slow permits have not finished yet. Quarters that ended two or more years ago are marked settled; the rest are shaded in the chart. The headline’s first stage uses the last four complete quarters; its second uses the last four settled quarters.

The median is the middle permit: half took less, half more. The slowest 10% is the 90th percentile. A median needs at least 5 permits behind it, or it is left out. A project type is shown apart within a neighborhood only when it has 30 or more finished permits there; the rest are “other types”.

Never finaled means no final sign-off three years after the permit was issued (or filed, if never issued), and not expired, cancelled, withdrawn, revoked, disapproved, denied or suspended (the site’s “expired or cancelled” outcome). About a quarter of permits citywide end this way; often the work was done and nobody called for the final inspection. These permits are in the counts and not in the medians.

A permit’s neighborhood is the Analysis Neighborhood the city writes on the permit record (the official set of 41). Permits with none are counted citywide only; the page says how many. “Nearby” neighborhoods are the three nearest by the center of their permits. The site reloads the city’s data every night; permits filed since 1 January 2000 are included. The placement of a permit, its dates and its status are the city’s; the grouping and the words are this site’s. How to read these records.