David Baker
- Listed as
- architect, authorized agent-others, engineer
- Firm
- David Baker Architects
- Based in
- San Francisco
- On San Francisco permits
- Apr 2005 to Nov 2019
43 permits since 2000 (architect on 40 permits, engineer on 2 permits, authorized agent-others on 1 permit): 38 completed, 3 never finaled, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 12, 2019 | Completed final sign-off Dec 2021 | 833 Bryant St | Cahill Contractors Llc. | demolish 1-story, office building. maher n/a.Details
demolish 1-story, office building. maher n/a. | $6,888 |
| Sep 5, 2019 | Completed final sign-off Nov 2019 | 222 Taylor St | Cahill Contractors Inc | revision to 201602179822 modifications requested by mod. removal of bab-changing stations in community rm restrooms, addition of braille & raised letter exit routes. modifications to lift fixed approach ramp, addition of power assist to stair doorDetails
revision to 201602179822 modifications requested by mod. removal of bab-changing stations in community rm restrooms, addition of braille & raised letter exit routes. modifications to lift fixed approach ramp, addition of power assist to stair door | $500 |
| Apr 30, 2019 | Never finaled issued May 2019, no final | 210 Taylor St | Cahill Contractors Inc | revisions to handrails + gates at maintenance room and roof to m.o.d requirements. rev to barn door and gate hardware to m.o.d requirements. ref. 201602179822 s2Details
revisions to handrails + gates at maintenance room and roof to m.o.d requirements. rev to barn door and gate hardware to m.o.d requirements. ref. 201602179822 s2 | $1,000 |
| Mar 1, 2019 | Completed final sign-off Nov 2019 | 210 Taylor St | Cahill Contractors Inc | revision to pa 2016-0217-9822s2 and 2019-0102-9503 including addition of roof farm and revised pavig to roof level, revised community kitchen configuration, and landscape details including tree pit surrounds and turf specificationDetails
revision to pa 2016-0217-9822s2 and 2019-0102-9503 including addition of roof farm and revised pavig to roof level, revised community kitchen configuration, and landscape details including tree pit surrounds and turf specification | |
| Jun 6, 2018 | Completed final sign-off Nov 2019 | 210 Taylor St | Cahill Contractors Llc. | rev to pa# 201602179822 s2; revision of fire rattng to electric closet-sheet g602 to show 2-hr fire rating, to be consistent with the rest of approved set for s-2Details
rev to pa# 201602179822 s2; revision of fire rattng to electric closet-sheet g602 to show 2-hr fire rating, to be consistent with the rest of approved set for s-2 | |
| May 23, 2018 | Completed final sign-off Mar 2019 | 1001 Howard St | Cookline Construction Inc | ref t.i. pa#201805048251: mechanical adjustments for limited use restaurant. maher n/a.Details
ref t.i. pa#201805048251: mechanical adjustments for limited use restaurant. maher n/a. | $165,000 |
| May 23, 2018 | Completed final sign-off Mar 2021 | 1601 Mariposa St | Liberty West Construction Services Llc | erect tower crane to aid wood frame construction - ref pa 2016-0303-1058. (1601 mariposa). n/a for maher.Details
erect tower crane to aid wood frame construction - ref pa 2016-0303-1058. (1601 mariposa). n/a for maher. | $200,000 |
| May 4, 2018 | Completed final sign-off Mar 2019 | 1001 Howard St | Cookline Construction Inc | bini's kitchen - ti of (e) restaurant space to become a restaurant with work including gyp board walls, finishes, commercial kitchen, millwork, lighting and paintingDetails
bini's kitchen - ti of (e) restaurant space to become a restaurant with work including gyp board walls, finishes, commercial kitchen, millwork, lighting and painting | $60,000 |
| Jun 30, 2017 | Completed final sign-off Apr 2019 | 210 Taylor St | Cahill Contractors Llc. | shoring ref pa #201602179822Details
shoring ref pa #201602179822 | $200,000 |
| Apr 4, 2017 | Completed final sign-off Aug 2018 | 388 Fulton St | K Bali Construction | mep work for deffered submittal 201608185378 for ti- (e) retail space to become a limited bakeryDetails
mep work for deffered submittal 201608185378 for ti- (e) retail space to become a limited bakery | $60,000 |
| Dec 22, 2016 | Completed final sign-off Mar 2017 | 588 Mission Bay Blvd North Bl | Nibbi Bros Assoc Inc. | revision to 201404042522 s3 to revise the draft stopping in roof. crickets combustible concealed space - includes ab-005 maher naDetails
revision to 201404042522 s3 to revise the draft stopping in roof. crickets combustible concealed space - includes ab-005 maher na | $10,000 |
| Dec 19, 2016 | Completed final sign-off May 2017 | 140 Middle Point Rd | Cahill-Nibbi Joint Venture | revision to 201308204720 addenda 2, add access panel and smoke detector to elevator shaft detail per fire alarm review requirementsDetails
revision to 201308204720 addenda 2, add access panel and smoke detector to elevator shaft detail per fire alarm review requirements | |
| Sep 21, 2016 | Completed final sign-off May 2021 | 1950 Mission St | mod. erect two type 1a buildings, one 9 story mixed use 93 unit residential building, and a 6 story mixed use 64 unit residential building with day care facilities, building function, offices, and commercial tenant spaces on the ground floorDetails
mod. erect two type 1a buildings, one 9 story mixed use 93 unit residential building, and a 6 story mixed use 64 unit residential building with day care facilities, building function, offices, and commercial tenant spaces on the ground floor | $60,000,000 | |
| Aug 8, 2016 | Completed final sign-off Aug 2017 | 801 Brannan St | Ferma Corporation, Balfour Beatty Construction Llc | roof deck fire pit (ref. pa 201309045886); maher n/aDetails
roof deck fire pit (ref. pa 201309045886); maher n/a | $5,000 |
| Apr 5, 2016 | Completed final sign-off May 2017 | 1380 07th St | James E Roberts-Obayashi Corporation | correction notice from jeff barnes to indicate on drawings that storage loft is not a mezzanine. rev. to pa# 201112070234. n/a ordinance #155-13. n/a maher ord. # 155-13Details
correction notice from jeff barnes to indicate on drawings that storage loft is not a mezzanine. rev. to pa# 201112070234. n/a ordinance #155-13. n/a maher ord. # 155-13 | |
| Mar 3, 2016 | Completed final sign-off Mar 2021 | 1601 Mariposa St | to erect 4 stories, no basement, 145 units residential & commercial building. ** maher: exempted; see approval letter from dph on the plans **Details
to erect 4 stories, no basement, 145 units residential & commercial building. ** maher: exempted; see approval letter from dph on the plans ** | $40,000,000 | |
| Mar 1, 2016 | Completed final sign-off Sep 2020 | 210 Arkansas St | Nibbi Bros Inc. | to erect 4 stories, 1 basement, type va & ia, 154 units residential with commercial & parking.Details
to erect 4 stories, 1 basement, type va & ia, 154 units residential with commercial & parking. | $50,000,000 |
| Jan 25, 2016 | Completed final sign-off May 2017 | 801 Brannan St | Balfour Beatty Construction Llc | comply with correction notice and report per app#201309045886 regarding top plates detail. n/a for maher.Details
comply with correction notice and report per app#201309045886 regarding top plates detail. n/a for maher. | |
| Dec 17, 2015 | Completed final sign-off Dec 2018 | 801 Brannan St | Ferma Corporation, Balfour Beatty Construction Llc | revision to pa# 2013/09/04/5886 s-2. added one transformer room for ac revision. added ac unit support on roof. revise garage b entrance. ** maher: n/a **Details
revision to pa# 2013/09/04/5886 s-2. added one transformer room for ac revision. added ac unit support on roof. revise garage b entrance. ** maher: n/a ** | $5,700,000 |
| Aug 26, 2015 | Completed final sign-off Aug 2021 | 1174 Folsom St | North Star Plumbing & Fire Protection, Transworld Construction | erect 6-story, 1 basement for 42 dwelling units, retail and office building. type 3-a construction. maher ordinance is comply.Details
erect 6-story, 1 basement for 42 dwelling units, retail and office building. type 3-a construction. maher ordinance is comply. | $6,300,000 |
| Oct 23, 2014 | Completed final sign-off May 2020 | 150 Hooper St | Dpr Construction | construct (n) mercantile/retail/pdr building.Details
construct (n) mercantile/retail/pdr building. | $7,500,000 |
| Sep 13, 2013 | Completed final sign-off Jun 2014 | 401 Grove St | Cahill Contractors Inc | base building revisions for future restaurant tenant. replace retail shaft 2 hr rated intermediate shaft walls at grease ducts with 2 hr rated intermediate shaft walls at grease ducts with 2 hr rated 3m fire barrier duct wrap 615+ and revise roof discharge of makeup air and general exhaust forDetails
base building revisions for future restaurant tenant. replace retail shaft 2 hr rated intermediate shaft walls at grease ducts with 2 hr rated intermediate shaft walls at grease ducts with 2 hr rated 3m fire barrier duct wrap 615+ and revise roof discharge of makeup air and general exhaust for | $10,000 |
| Aug 14, 2013 | Completed final sign-off Nov 2013 | 1075 Le Conte Av | Cahill Contractors Inc | revision to pa#201007196949, replace fire dampers at supply air ducts with fire smoke dampers at each unit supply shaft penetration.Details
revision to pa#201007196949, replace fire dampers at supply air ducts with fire smoke dampers at each unit supply shaft penetration. | $48,000 |
| Mar 27, 2013 | Completed final sign-off Aug 2017 | 388 Fulton St | Oliver & Company Inc. | erect 6 stories, no basement, 69 units residential apartments with ground floor retail.Details
erect 6 stories, no basement, 69 units residential apartments with ground floor retail. | $12,500,000 |
| Nov 7, 2012 | Completed final sign-off May 2016 | 1751 Carroll Av | Nibbi Bros Assoc Inc. | erect 4-story, type 5, 121 dwelling units building.Details
erect 4-story, type 5, 121 dwelling units building. | $32,000,000 |
| Dec 7, 2011 | Completed final sign-off May 2017 | 1400 07th St | erect 6 story 65 units residential & commercial building.Details
erect 6 story 65 units residential & commercial building. | $25,000,000 | |
| Dec 7, 2011 | Completed final sign-off May 2017 | 1380 07th St | erect 6 story 393 units residential & commercial building.Details
erect 6 story 393 units residential & commercial building. | $55,000,000 | |
| Jun 30, 2011 | Expired or cancelled cancelled Jan 2026 | 222 Sutter St | Plant Construction Co, Lp | 9th floor #900 -renovation of an existing office , to remain an office, including non-structural demolition, gyp board partitions, glass aprtitions, refinish floor, casework, & painting.Details
9th floor #900 -renovation of an existing office , to remain an office, including non-structural demolition, gyp board partitions, glass aprtitions, refinish floor, casework, & painting. | $300,000 |
| Sep 1, 2010 | Completed final sign-off Oct 2010 | 5688 03rd St | Nibbi Bros Assoc Inc. | suite d -tenant improvement build out for leasing office from retail space, new interior metal stud walls, sheetrock, decorative wood system, carpet, new lighting, hvac, duct work.Details
suite d -tenant improvement build out for leasing office from retail space, new interior metal stud walls, sheetrock, decorative wood system, carpet, new lighting, hvac, duct work. | $50,000 |
| Apr 7, 2010 | Completed final sign-off Sep 2011 | 365 Fulton St | Cahill Contractors Inc | building of foundation for tower crane to be used during construction of new bldg (pa #200807116520-s).Details
building of foundation for tower crane to be used during construction of new bldg (pa #200807116520-s). | $4,500 |
| Oct 3, 2008 | Expired or cancelled expired Aug 2010 | 5600 03rd St | install of 8 precast, prestressed 14" square indicator piles on vacant lot, ref new #200703136088s.Details
install of 8 precast, prestressed 14" square indicator piles on vacant lot, ref new #200703136088s. | $45,000 | |
| Jul 11, 2008 | Completed final sign-off Sep 2011 | 365 Fulton St | Cahill Contractors Inc | erect 5 stories ,120 residential units & commercial.Details
erect 5 stories ,120 residential units & commercial. | $20,000,000 |
| Mar 13, 2007 | Completed final sign-off Oct 2010 | 5600 03rd St | bldg #3 - erect a 5 stories, 116 residential with daycare, retail and parking building.Details
bldg #3 - erect a 5 stories, 116 residential with daycare, retail and parking building. | $18,000,000 | |
| Nov 2, 2006 | Completed final sign-off Feb 2010 | 5600 03rd St | to erect 3 stories 2 dwelling units bldg.Details
to erect 3 stories 2 dwelling units bldg. | $250,000 | |
| Nov 2, 2006 | Completed final sign-off Feb 2010 | 5600 03rd St | to erect 3 stories 2 dwelling units bldg.Details
to erect 3 stories 2 dwelling units bldg. | $250,000 | |
| Nov 2, 2006 | Completed final sign-off Feb 2010 | 5600 03rd St | to erect 3 stories 2 dwelling units bldg.Details
to erect 3 stories 2 dwelling units bldg. | $250,000 | |
| Nov 2, 2006 | Completed final sign-off Feb 2010 | 5600 03rd St | to erect 3 stories 2 dwelling units bldg.Details
to erect 3 stories 2 dwelling units bldg. | $250,000 | |
| Nov 2, 2006 | Completed final sign-off Feb 2010 | 5600 03rd St | to erect 3 stories 2 dwelling units bldg.Details
to erect 3 stories 2 dwelling units bldg. | $250,000 | |
| Sep 29, 2005 | Completed final sign-off Feb 2010 | 5600 03rd St | bldg. 2- erect 5 stories 67 multi family dwelling/office bldg.Details
bldg. 2- erect 5 stories 67 multi family dwelling/office bldg. | $16,500,000 | |
| Jul 27, 2005 | Never finaled issued Jan 2006, no final | 5600 03rd St | Swinerton Builders | bldg #5 - demolish industrial manufacturing, 1 story building.Details
bldg #5 - demolish industrial manufacturing, 1 story building. | |
| Jul 13, 2005 | Completed final sign-off Nov 2005 | 145 Taylor St | Cahill Contractors Inc | correct drawing to show sprinkler protection at all property line windowsDetails
correct drawing to show sprinkler protection at all property line windows | |
| May 11, 2005 | Completed final sign-off Oct 2007 | 420 Berry St | erect 4 stories 236 dwelling residential/fitness room/common room.Details
erect 4 stories 236 dwelling residential/fitness room/common room. | $5,000,000 | |
| Apr 11, 2005 | Never finaled filed Apr 2005, never issued | 339 Shotwell St | to erect 3 stories, 1 dwelling single family. at rear of 339 shotwell st.Details
to erect 3 stories, 1 dwelling single family. at rear of 339 shotwell st. | $100,000 |