43 permits since 2000 (architect on 41 permits, authorized agent-others on 1 permit, designer on 1 permit): 16 completed, 16 never finaled, 11 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 7, 2019 | Completed final sign-off Nov 2021 | 429 Grand View Av | G-Max Construction | revision to pa# 2013/11/19/2313-s1. revision to windows, change to elevator & misc other changes.Details
revision to pa# 2013/11/19/2313-s1. revision to windows, change to elevator & misc other changes. | |
| Nov 21, 2018 | Expired or cancelled withdrawn Dec 2018 | 1547 Clay St | revision to pa# 2017/01/26/8051. changes to kitchen layout closets & adjustments in lighting. ** maher: n/a **Details
revision to pa# 2017/01/26/8051. changes to kitchen layout closets & adjustments in lighting. ** maher: n/a ** | $1,000 | |
| Oct 26, 2018 | Expired or cancelled cancelled Nov 2022 | 65 Buena Vista Tr | rev to pa# 201607273471 adu enlarge ext windows, remove ramp and install stairs, move doors in light court. other misc changes. ** maher: n/a **Details
rev to pa# 201607273471 adu enlarge ext windows, remove ramp and install stairs, move doors in light court. other misc changes. ** maher: n/a ** | $4,000 | |
| Oct 26, 2018 | Completed final sign-off May 2019 | 65 Buena Vista East Av | Wickman Development And Construction | rev to pa# 201607273461 soft story work. ** maher: n/a **Details
rev to pa# 201607273461 soft story work. ** maher: n/a ** | |
| Oct 17, 2018 | Never finaled issued Nov 2018, no final | 828 Jones St | Casman Construction Inc | revision 201710100742, layout adjustment and concrete slab replacementDetails
revision 201710100742, layout adjustment and concrete slab replacement | $5,000 |
| Oct 12, 2018 | Expired or cancelled withdrawn Dec 2018 | 1547 Clay St | revision to 201701268051 including closets, kitchen layout and unit egress, delete rear stairwell maher not reqDetails
revision to 201701268051 including closets, kitchen layout and unit egress, delete rear stairwell maher not req | $189,000 | |
| Jun 15, 2018 | Expired or cancelled cancelled Jan 2026 | 360 Dwight St | kitchen/bath hallway remodel and new skylight at stair (interior)Details
kitchen/bath hallway remodel and new skylight at stair (interior) | $120,000 | |
| Mar 8, 2018 | Expired or cancelled cancelled May 2025 | 1801 Gough St | addition of 5 dwelling units per ordinance# 162-16 . all work is located within (e) building envelope @ the 1st floor.Details
addition of 5 dwelling units per ordinance# 162-16 . all work is located within (e) building envelope @ the 1st floor. | $150,000 | |
| Mar 7, 2018 | Expired or cancelled withdrawn Jan 2019 | 3783 20th St | two adu's to be added to ground fl within existing bld envelope per ordinance 162-16Details
two adu's to be added to ground fl within existing bld envelope per ordinance 162-16 | $150,000 | |
| Nov 1, 2017 | Completed final sign-off Mar 2018 | 2109 Market St | ada toilet upgradeDetails
ada toilet upgrade | $5,000 | |
| Oct 19, 2017 | Completed final sign-off Apr 2018 | 2099 Market St | Wickman Development And Construction | 1st & 2nd floor: ada upgrades to toilet rooms, & stair rails. barrier removal.Details
1st & 2nd floor: ada upgrades to toilet rooms, & stair rails. barrier removal. | $45,000 |
| Oct 10, 2017 | Never finaled issued Oct 2018, no final | 828 Jones St | Casman Construction Inc | legalization of existing illegal unit per ord 43-14. replace elec/plumb upgrade fire rating of egress components. sprinklerper nfpa 13, standpipe and fire alarm under separated applicationsDetails
legalization of existing illegal unit per ord 43-14. replace elec/plumb upgrade fire rating of egress components. sprinklerper nfpa 13, standpipe and fire alarm under separated applications | $79,013 |
| Sep 11, 2017 | Completed final sign-off Jun 2019 | 60 Central Av | Beyond The Horizon Construction | legalize one dwelling unit within building envelope- ordinance 43-14Details
legalize one dwelling unit within building envelope- ordinance 43-14 | $12,150 |
| Sep 5, 2017 | Completed final sign-off May 2018 | 621 Stockton St | Kong's Plumbing & Construction Co. | add new window located on the 4th floor unit 301 at building front @ penthouse frontDetails
add new window located on the 4th floor unit 301 at building front @ penthouse front | $1,000 |
| Sep 5, 2017 | Completed final sign-off Jul 2018 | 2620 Laguna St | Kong's Plumbing & Construction Co. | 1 penthouse dormer to be demo'ed and replaced with new dormer and sliding door. n/a maherDetails
1 penthouse dormer to be demo'ed and replaced with new dormer and sliding door. n/a maher | $10,000 |
| Aug 2, 2017 | Completed final sign-off Oct 2017 | 2620 Laguna St | Casman Construction Inc | revision to app#201610210880 r-2 unit #1, for interior kitchen and bath remodel to unit to be legalized; minor wall layout change & window replacement. n/a for maherDetails
revision to app#201610210880 r-2 unit #1, for interior kitchen and bath remodel to unit to be legalized; minor wall layout change & window replacement. n/a for maher | $10,000 |
| May 4, 2017 | Never finaled issued May 2017, no final | 2677 Larkin St | Architectural Fenestration & Restoration | replace 93 windows - wood to aluminum clad wood, no change in opening size or operation. like for like.Details
replace 93 windows - wood to aluminum clad wood, no change in opening size or operation. like for like. | $30,000 |
| Apr 25, 2017 | Never finaled issued Jul 2017, no final | 624 Brussels St | Williams Construction | rev. to pa#201703211913 (n) conditioned space within (e) envelope at garage level, (n) bath, (n) bedroom and home office, (n) foundation. reconfiguration of (e) deck & exterior stair.Details
rev. to pa#201703211913 (n) conditioned space within (e) envelope at garage level, (n) bath, (n) bedroom and home office, (n) foundation. reconfiguration of (e) deck & exterior stair. | $45,000 |
| Apr 10, 2017 | Expired or cancelled cancelled Jan 2026 | 2828 Geary Bl | residential - soft story retrofit per sfbc chapter 4d engineering criteria ab107 & cebc appendix a-4. commercial soft story 201704103537Details
residential - soft story retrofit per sfbc chapter 4d engineering criteria ab107 & cebc appendix a-4. commercial soft story 201704103537 | $19,884 | |
| Apr 10, 2017 | Expired or cancelled cancelled Jan 2026 | 2830 Geary Bl | commercial - soft story retrofit per sfbc chapter 4d engineering criteria ab107 & cebc appendix a-4. residential 201704103534Details
commercial - soft story retrofit per sfbc chapter 4d engineering criteria ab107 & cebc appendix a-4. residential 201704103534 | $16,916 | |
| Mar 3, 2017 | Never finaled issued Jun 2021, no final | 2227 Taylor St | adu per ord #162-16; 4(n) units within (e) envelope, includes facade work. sprinkler and fire alarm deferred.Details
adu per ord #162-16; 4(n) units within (e) envelope, includes facade work. sprinkler and fire alarm deferred. | $300,410 | |
| Jan 26, 2017 | Completed final sign-off Apr 2019 | 1547 Clay St | Dan Gillies Construction Services Inc | addition of 2 dwelling units per ordinance no# 162-16. (2) one bedroom, one bath unit and (1) studio unit with bath. ** maher: n/a **Details
addition of 2 dwelling units per ordinance no# 162-16. (2) one bedroom, one bath unit and (1) studio unit with bath. ** maher: n/a ** | $189,000 |
| Dec 28, 2016 | Expired or cancelled withdrawn May 2025 | 2828 Geary Bl | addition of (1) dwelling unit per ord #162-16. n/a for maher ordinance no.155-13Details
addition of (1) dwelling unit per ord #162-16. n/a for maher ordinance no.155-13 | $50,000 | |
| Dec 28, 2016 | Never finaled issued Mar 2019, no final | 2824 Geary Bl | addition of 1 dwelling unit per ord #162-16Details
addition of 1 dwelling unit per ord #162-16 | $95,000 | |
| Dec 22, 2016 | Completed final sign-off Dec 2021 | 1064 Dolores St | Metro General Construction Inc | addition of (2) dwelling units within the (e) building envelope per ordinance# 162-16. single exit. sprinklers required per 13r for units, fire alarm to meet sffc 1103.7.6.1 under separate permitDetails
addition of (2) dwelling units within the (e) building envelope per ordinance# 162-16. single exit. sprinklers required per 13r for units, fire alarm to meet sffc 1103.7.6.1 under separate permit | $429,034 |
| Dec 22, 2016 | Never finaled issued Nov 2018, no final | 660 Clipper St | addition of 3 new dwelling units to be built within the (e) envelope of the building per ordinance# 162-16.Details
addition of 3 new dwelling units to be built within the (e) envelope of the building per ordinance# 162-16. | $543,681 | |
| Dec 22, 2016 | Never finaled issued Nov 2018, no final | 610 Clipper St | addition of 6 new dwelling units to be built within the (e) envelope of the building per ordinance# 162-16. fire alarm and sprinkler to nfpa-13 on deferred submittal.Details
addition of 6 new dwelling units to be built within the (e) envelope of the building per ordinance# 162-16. fire alarm and sprinkler to nfpa-13 on deferred submittal. | $532,641 | |
| Dec 6, 2016 | Expired or cancelled cancelled Jan 2026 | 621 Stockton St | repair of existing roof deck including reroofing. repair in kind.Details
repair of existing roof deck including reroofing. repair in kind. | $6,000 | |
| Nov 9, 2016 | Expired or cancelled cancelled Jan 2026 | 1405 Franklin St | Canning Electric Inc | the project scope is to demolition of an existing commercial unit and install a new electrical room.Details
the project scope is to demolition of an existing commercial unit and install a new electrical room. | $10,000 |
| Oct 21, 2016 | Never finaled issued Jun 2017, no final | 2620 Laguna St | legalization of (1) dwelling unit at ground level per ord. 43-14 with one kitchen, one bathroom studio apt. maher ordinance - extended ordinance 155-13 n/aDetails
legalization of (1) dwelling unit at ground level per ord. 43-14 with one kitchen, one bathroom studio apt. maher ordinance - extended ordinance 155-13 n/a | $21,000 | |
| Oct 14, 2016 | Never finaled issued Sep 2017, no final | 2975 Van Ness Av | addition of (6) dwelling units at the ground floor per ordinance #162-16Details
addition of (6) dwelling units at the ground floor per ordinance #162-16 | $394,000 | |
| Oct 14, 2016 | Never finaled issued Jun 2018, no final | 861 Post St | Holland Brooks Builders Inc | addition of one dwelling unit per ordinance #162-16.Details
addition of one dwelling unit per ordinance #162-16. | $68,000 |
| Aug 10, 2016 | Never finaled issued Dec 2018, no final | 563 Webster St | S L M Development Inc. | addition of 3 dwelling units per ordinance no.30-15 soft appln #201504224363. work located entirely within bldg envelope at g/f includes relocation of stair to existing basement changes to facadeDetails
addition of 3 dwelling units per ordinance no.30-15 soft appln #201504224363. work located entirely within bldg envelope at g/f includes relocation of stair to existing basement changes to facade | $226,000 |
| Jul 27, 2016 | Completed final sign-off Apr 2019 | 65 Buena Vista East Av | Wickman Development And Construction | 3 additional dwelling units on g/f per ordinance 30-15. soft story appln #201607273461. (n) corridor, no work @ front facade. area of work ground floor. n/a for maher ordiance no. 155-13.Details
3 additional dwelling units on g/f per ordinance 30-15. soft story appln #201607273461. (n) corridor, no work @ front facade. area of work ground floor. n/a for maher ordiance no. 155-13. | $225,000 |
| Jul 11, 2016 | Never finaled issued Aug 2016, no final | 15 25th North Av | Quality General Construction Co Inc | revision to pa#201408154000, lower roof at nw portion at rear, reframe ceiling/floor above garage.Details
revision to pa#201408154000, lower roof at nw portion at rear, reframe ceiling/floor above garage. | |
| May 25, 2016 | Completed final sign-off Nov 2016 | 1401 Jones St | Sure, Inc. | #a- dwelling unit remodel includint 2 bath remodels, kitchen remodel, addition of 1/2 bath (vanity and toilet), addition of washer/dryer, 2 new wood windows & opening, new exterior door/landing. n/a ordinance #155-13Details
#a- dwelling unit remodel includint 2 bath remodels, kitchen remodel, addition of 1/2 bath (vanity and toilet), addition of washer/dryer, 2 new wood windows & opening, new exterior door/landing. n/a ordinance #155-13 | $218,954 |
| May 10, 2016 | Never finaled issued May 2016, no final | 15 25th North Av | Quality General Construction Co Inc | revision to pa 2014-0815-4000 - removal of habitable square footage at 1st floor, proposed patio.Details
revision to pa 2014-0815-4000 - removal of habitable square footage at 1st floor, proposed patio. | |
| Aug 15, 2014 | Never finaled issued Sep 2015, no final | 15 25th North Av | Quality General Construction Co Inc | alteration, remodel & 85 sf addition to (e) residence. scope includes a reduction in bldg height w/partial demo of 2nd fl, addition of a new roof over remaining 1st fl, facade changes w/new doors & windows, contruction of a new interior stairwell & the interior remodel incl 1 kitchen & 2.5 baths.Details
alteration, remodel & 85 sf addition to (e) residence. scope includes a reduction in bldg height w/partial demo of 2nd fl, addition of a new roof over remaining 1st fl, facade changes w/new doors & windows, contruction of a new interior stairwell & the interior remodel incl 1 kitchen & 2.5 baths. | $700,000 |
| Apr 16, 2014 | Never finaled issued May 2014, no final | 1935 Lawton St | g/f & m/f- interior facelift. prep drywall for new paint. all partitions are existing. separate permit for mep. new baseboards, trim. remove carpet, clean existing concrete, seal concrete floor, remove old finishesDetails
g/f & m/f- interior facelift. prep drywall for new paint. all partitions are existing. separate permit for mep. new baseboards, trim. remove carpet, clean existing concrete, seal concrete floor, remove old finishes | $8,000 | |
| Nov 19, 2013 | Completed final sign-off Nov 2021 | 429 Grand View Av | G-Max Construction | addition of a 2-story unit above an (e) 2-story structure. second unit includes stairs, elevator & car port on site parking.Details
addition of a 2-story unit above an (e) 2-story structure. second unit includes stairs, elevator & car port on site parking. | $600,000 |
| Apr 12, 2012 | Completed final sign-off Jul 2012 | 466 Missouri St | revision to addendum #1 to pa# 201008239387. interior structural alteration revision to original structural design.Details
revision to addendum #1 to pa# 201008239387. interior structural alteration revision to original structural design. | ||
| Aug 23, 2010 | Completed final sign-off Jul 2012 | 466 Missouri St | Power Construction Inc. | interior alterations to a single family dwelling.Details
interior alterations to a single family dwelling. | $250,000 |
| Sep 6, 2006 | Completed final sign-off Jan 2007 | 1367 03rd Av | Rise Construction | interior kkitchen and living room errmodel new appliances, new cabinets, new windows, refurbish floors, fenestration added is lessthan 50 sf u factor for replacement new windows 42 maxDetails
interior kkitchen and living room errmodel new appliances, new cabinets, new windows, refurbish floors, fenestration added is lessthan 50 sf u factor for replacement new windows 42 max | $50,000 |