A. J. Miller
- Listed as
- architect, authorized agent-others, engineer
- Firm
- A. J. Miller & Associates
- Based in
- Oakland
- On San Francisco permits
- Mar 2002 to Jul 2015
23 permits since 2000 (engineer on 18 permits, architect on 4 permits, authorized agent-others on 1 permit): 21 completed, 1 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 31, 2015 | Never finaled issued Feb 2016, no final | 425 Folsom St | C. Overaa & Co | deffered submitial to pa# 2014/01/13/6157 r-3. building stairs & rail submittal.Details
deffered submitial to pa# 2014/01/13/6157 r-3. building stairs & rail submittal. | |
| Jun 19, 2015 | Completed final sign-off Jan 2016 | 930 Gough St | City Building Inc. | deferred gaurdrail submittal for pa# 2014/06/20/8999.Details
deferred gaurdrail submittal for pa# 2014/06/20/8999. | $40,000 |
| Jun 19, 2015 | Completed final sign-off Jan 2016 | 930 Gough St | City Building Inc. | deferred handrail and stair submittal for pa# 2014/06/20/8999.Details
deferred handrail and stair submittal for pa# 2014/06/20/8999. | $100,000 |
| Jun 19, 2015 | Completed final sign-off Jan 2016 | 888 Turk St | City Building Inc. | deferred handrails & stairs submittal for pa# 2014/06/20/8993 .Details
deferred handrails & stairs submittal for pa# 2014/06/20/8993 . | $100,000 |
| Jun 19, 2015 | Completed final sign-off Jan 2016 | 888 Turk St | City Building Inc. | deferred guardrail submittal. pa# 2014/06/20/8993.Details
deferred guardrail submittal. pa# 2014/06/20/8993. | $40,000 |
| Mar 25, 2015 | Completed final sign-off Mar 2017 | 49 Niagara Av | voluntary structural strengthening- addition of ground floor shear walls, strengthening, installation of sill anchor bolts & related strengthening, etc. per plan. revision to pa2015 0224 9149. to comply with bid nov#201527215.Details
voluntary structural strengthening- addition of ground floor shear walls, strengthening, installation of sill anchor bolts & related strengthening, etc. per plan. revision to pa2015 0224 9149. to comply with bid nov#201527215. | $3,500 | |
| Dec 10, 2014 | Completed final sign-off Jun 2015 | 555 California St | Principal Builders Inc. | structural work to show steel framing at cubicle ceiling frame refer to t.i. #2014.0612.8223 for t.i. work. n/a maher ordinanceDetails
structural work to show steel framing at cubicle ceiling frame refer to t.i. #2014.0612.8223 for t.i. work. n/a maher ordinance | $50,000 |
| May 20, 2014 | Expired or cancelled cancelled Jan 2026 | 155 05th St | 6th floor ceiling - (e) steel beam to be temporarily supported by (n) steel beam prior to demo of slab for (n) stair opening. new stair under this permi. new opening under separate permit. n/a maher ordinance 155-13Details
6th floor ceiling - (e) steel beam to be temporarily supported by (n) steel beam prior to demo of slab for (n) stair opening. new stair under this permi. new opening under separate permit. n/a maher ordinance 155-13 | $10,000 | |
| Feb 12, 2014 | Completed final sign-off Dec 2015 | 690 Long Bridge St | County Builders Construction Inc. | 1 tower crane erection and work. compliance with ordinance no. 155-13 not required.Details
1 tower crane erection and work. compliance with ordinance no. 155-13 not required. | $12,000 |
| Jul 3, 2013 | Completed final sign-off Oct 2013 | 250 Valencia St | Plant Construction Company Lp | new exterior egress stairs h and j at west of building. defereed submittal for permit 201303132128Details
new exterior egress stairs h and j at west of building. defereed submittal for permit 201303132128 | $50,000 |
| Jun 18, 2013 | Completed final sign-off Mar 2014 | 1355 Market St | Truebeck Construction | revision to appl #2012.11.08.3877 - 1 story steel stair & concrete & intermediate landing including structural framing shop, not an exit stair. ada accessibility deferred under ab-056.Details
revision to appl #2012.11.08.3877 - 1 story steel stair & concrete & intermediate landing including structural framing shop, not an exit stair. ada accessibility deferred under ab-056. | $20,000 |
| May 21, 2013 | Completed final sign-off Jul 2013 | 500 Terry A. Francois Bl | Principal Builders Inc. | ref. to pa# 201303212737: installation of stair railing between 4th and 5th floor interconnecting stairs.Details
ref. to pa# 201303212737: installation of stair railing between 4th and 5th floor interconnecting stairs. | |
| Apr 4, 2013 | Completed final sign-off Jun 2016 | 948 Mission St | Layton Construction Co | install footing for tower crane. erect tower crane for the prupose of hosting for permit #201105136051s1r1 942 mission street 15 story hotel.Details
install footing for tower crane. erect tower crane for the prupose of hosting for permit #201105136051s1r1 942 mission street 15 story hotel. | $400,000 |
| Oct 5, 2011 | Completed final sign-off Dec 2011 | 500 Howard St | Matrix Hg Inc | suite 100 - install watersource heat pump connect to existing condenser water line.Details
suite 100 - install watersource heat pump connect to existing condenser water line. | $10,000 |
| May 13, 2009 | Completed final sign-off Jul 2009 | 433 California St | Fabpro | tank restraints for existing water storage tanks in basement and 2 in rooftop enclosed mechanical room.Details
tank restraints for existing water storage tanks in basement and 2 in rooftop enclosed mechanical room. | $22,500 |
| Oct 21, 2008 | Completed final sign-off Nov 2009 | 640 Sutter St | Turner Construction Co | this permit is in reference to approved permit app #200608179733. supply and install new pre fabricated central stairs from 3rd floor to roof level. shop drawings by steel fabricator,glacier iron works, include structural steel framing and calcs. see letter attached rom both the architect of recordDetails
this permit is in reference to approved permit app #200608179733. supply and install new pre fabricated central stairs from 3rd floor to roof level. shop drawings by steel fabricator,glacier iron works, include structural steel framing and calcs. see letter attached rom both the architect of record | $225,000 |
| Jul 21, 2008 | Completed final sign-off Nov 2009 | 640 Sutter St | Turner Construction Co | ref. appl#200608179733, new design-build central stairs serving basement, first fl, second fl. plans include structural steel framing & calcs serving this portion of work. (separate plans will be submitted for stairs serving third fl to roof level.)Details
ref. appl#200608179733, new design-build central stairs serving basement, first fl, second fl. plans include structural steel framing & calcs serving this portion of work. (separate plans will be submitted for stairs serving third fl to roof level.) | $150,000 |
| Apr 24, 2008 | Completed final sign-off Oct 2013 | 680 Folsom St | Plant Construction Company Lp | construct 2 tower crane foundations at basment level of existing building. foundations to be removed on completion of construction. (site app 200712039403) all work within property linesDetails
construct 2 tower crane foundations at basment level of existing building. foundations to be removed on completion of construction. (site app 200712039403) all work within property lines | $77,000 |
| Nov 6, 2006 | Completed final sign-off May 2008 | 55 Concourse Dr | Webcor Construction Lp | erection and dismantal of fixed tower crane on the new cailfornia academy of sciences work site. (tower crane #1).Details
erection and dismantal of fixed tower crane on the new cailfornia academy of sciences work site. (tower crane #1). | $15,000 |
| Nov 6, 2006 | Completed final sign-off May 2008 | 55 Concourse Dr | Webcor Construction Lp | erection and dismantal of tower crane on california academy of sciences, building site, tower crane #2.Details
erection and dismantal of tower crane on california academy of sciences, building site, tower crane #2. | $15,000 |
| May 16, 2006 | Completed final sign-off Aug 2009 | 301 Mission St | erect 2 tower cranes for new construction approved under appl#200210239696Details
erect 2 tower cranes for new construction approved under appl#200210239696 | $23,000 | |
| Nov 1, 2004 | Completed final sign-off Dec 2005 | 612 Howard St | Howard S Wright Construction Co. | remove 4 windows & infill 2/ cmv & drywall to maintain 4 hour rated wall between bldg. all windowsDetails
remove 4 windows & infill 2/ cmv & drywall to maintain 4 hour rated wall between bldg. all windows | $12,000 |
| Mar 18, 2002 | Completed final sign-off Dec 2002 | 1429 Valencia St | demolish portion of 1 story commercial bldg. to comply nov#200113678 provide high security fence@reaDetails
demolish portion of 1 story commercial bldg. to comply nov#200113678 provide high security fence@rea | $10,000 |