13 permits since 2000 (architect on 11 permits, authorized agent-others on 1 permit, engineer on 1 permit): 11 completed, 2 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 18, 2019 | Completed final sign-off Jan 2020 | 3950 24th St | Bsm Construction Inc | provide screen wall on roof for sound mitigationDetails
provide screen wall on roof for sound mitigation | $20,000 |
| Mar 22, 2018 | Never finaled issued Jun 2018, no final | 900 North Point St | tenant improvement, for the previously permited mini golf course/arcade under permit # 201711073329 ~ new finishes and furnitureDetails
tenant improvement, for the previously permited mini golf course/arcade under permit # 201711073329 ~ new finishes and furniture | ||
| Jan 2, 2018 | Completed final sign-off Aug 2018 | 900 North Point St | Swinerton Builders | 3rd fl: exterior alterations on facade windows of woolen mill building 3rd level as required for future mep systems. installation of temporary convering for exterior plaza adjacent to tenant space. maher naDetails
3rd fl: exterior alterations on facade windows of woolen mill building 3rd level as required for future mep systems. installation of temporary convering for exterior plaza adjacent to tenant space. maher na | $30,000 |
| Jan 2, 2018 | Completed final sign-off Oct 2018 | 900 North Point St | Swinerton Builders | (n) exit door, (n) finish floorings, (n) partitions. maher naDetails
(n) exit door, (n) finish floorings, (n) partitions. maher na | |
| Mar 26, 2014 | Completed final sign-off Aug 2014 | 399 04th St | John Sutti & Associates, Inc. | remodel of (e) grocery store bulk dept. into taproom food & drink venue. work includes demo as noted, new equipment, floor sinks, flooring, lighting, electrical, plumbing, refrigeration and finishes. (not a change of use)Details
remodel of (e) grocery store bulk dept. into taproom food & drink venue. work includes demo as noted, new equipment, floor sinks, flooring, lighting, electrical, plumbing, refrigeration and finishes. (not a change of use) | $40,000 |
| Mar 7, 2012 | Completed final sign-off Feb 2013 | 1765 California St | Construction Mgmt & Builders Inc | barrier removal @upper level open parking structure. re-grade & re-stripe accessible path to the accessible parking & public right of way from the store entrance including the top landing at the entrance ramp & level landing outside the entrance to the store. modify (e) guardrails & handrailsDetails
barrier removal @upper level open parking structure. re-grade & re-stripe accessible path to the accessible parking & public right of way from the store entrance including the top landing at the entrance ramp & level landing outside the entrance to the store. modify (e) guardrails & handrails | $50,000 |
| Dec 21, 2011 | Completed final sign-off Feb 2013 | 3950 24th St | Construction Mgmt & Builders Inc | ada accessibility remediation including a striped path of travel to the public right of way & restroom fixture re-configurationsDetails
ada accessibility remediation including a striped path of travel to the public right of way & restroom fixture re-configurations | $15,000 |
| Dec 21, 2011 | Completed final sign-off Apr 2012 | 690 Stanyan St | Construction Mgmt & Builders Inc | ada accessibility remediation - parking stall re-striping, ramp replacement, curb ramp level landing, drinking fountain remediation, men's restroom remodel. barrier removal.Details
ada accessibility remediation - parking stall re-striping, ramp replacement, curb ramp level landing, drinking fountain remediation, men's restroom remodel. barrier removal. | $10,000 |
| Jul 7, 2011 | Completed final sign-off Oct 2011 | 1765 California St | John Sutti & Associates, Inc. | this is a 1,500 sf interior remodel in an extg grocery reail store consisting of ;removal of exg coffee service area millwork & equipment at coffee service. refinish of floor in area of work. new millwork & seating at seating area. refinish of wall & floor at restroom. new toilet accessories.Details
this is a 1,500 sf interior remodel in an extg grocery reail store consisting of ;removal of exg coffee service area millwork & equipment at coffee service. refinish of floor in area of work. new millwork & seating at seating area. refinish of wall & floor at restroom. new toilet accessories. | $115,000 |
| Jul 22, 2010 | Completed final sign-off Sep 2010 | 399 04th St | Construction Mgmt & Builders Inc | revision to existing grocery store remodel permit 2010 0526 3274: new seating, new checkstands, soup self-service, sushi display & work area, deli prep and service island, and new customer service counterDetails
revision to existing grocery store remodel permit 2010 0526 3274: new seating, new checkstands, soup self-service, sushi display & work area, deli prep and service island, and new customer service counter | $100,000 |
| May 25, 2010 | Completed final sign-off Feb 2011 | 690 Stanyan St | Construction Mgmt & Builders Inc | remodel of (e) grocery store. tenant improvement of entire store consisting of exterior, interior structural & non-structural partitions & finishes. new m.e.p. fire alarm & sprinkler under separate permit.Details
remodel of (e) grocery store. tenant improvement of entire store consisting of exterior, interior structural & non-structural partitions & finishes. new m.e.p. fire alarm & sprinkler under separate permit. | $3,744,224 |
| Jun 15, 2009 | Never finaled issued Nov 2009, no final | 3150 Sacramento St | interior remodel of 1st&2nd/fl new finishes, ff & e, elec/mech sys. new public toilet facilities. correct access issues @sidewalk, curb ramp, exteiror ramps/bookdrop & elevator. refurnish perimeter book shelves&windows. restore exterior masonry, terra cotta, main stairs&entry portico ceiling.Details
interior remodel of 1st&2nd/fl new finishes, ff & e, elec/mech sys. new public toilet facilities. correct access issues @sidewalk, curb ramp, exteiror ramps/bookdrop & elevator. refurnish perimeter book shelves&windows. restore exterior masonry, terra cotta, main stairs&entry portico ceiling. | $1,560,000 | |
| Sep 27, 2006 | Completed final sign-off Nov 2007 | 450 Rhode Island St | interior tenant improvement for whole foods store. all life safety, fire sprinkler under separate permit. no exterior work. mechanical, electrical & plumbing included in this permit. complaint #200676484, 200563369, 200562558 & 200666193.Details
interior tenant improvement for whole foods store. all life safety, fire sprinkler under separate permit. no exterior work. mechanical, electrical & plumbing included in this permit. complaint #200676484, 200563369, 200562558 & 200666193. | $5,500,000 |