7 permits since 2000 (architect on 5 permits, authorized agent-others on 2 permits, designer on 1 permit): 4 completed, 3 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 31, 2026 | In progress issued Aug 2026 | 3133 Scott St | Sure, Inc. | unit 3133, level 3: replace all windows in kind. new skylights and roof framing for additional support. interior non load bearing walls. remodel existing kitchen, remove e windows, install 1 new window side north elevation. new laundry area with stacked. remodel e split bath to full.Details
unit 3133, level 3: replace all windows in kind. new skylights and roof framing for additional support. interior non load bearing walls. remodel existing kitchen, remove e windows, install 1 new window side north elevation. new laundry area with stacked. remodel e split bath to full. | $60,000 |
| Apr 7, 2025 | Completed final sign-off Aug 2025 | 120 Duncan St | Highq Inc | level 2 (120 ducan st): relocated kitchen. reconfigure interior walls, new bathroom. replace rear yard facing window (same size), new laundry closet. level 3 (122 ducan st): new bathroom. relocate laundry closet.Details
level 2 (120 ducan st): relocated kitchen. reconfigure interior walls, new bathroom. replace rear yard facing window (same size), new laundry closet. level 3 (122 ducan st): new bathroom. relocate laundry closet. | $130,000 |
| Feb 4, 2025 | In progress issued Feb 2025 | 501 Crescent Av | Atrisco Construction | revision to approved pa # 2021-0317-6756 add 3 (n) bathrooms, relocate the kitchen & reconfigure interior walls. rear yard design. change window frame material from aluminum to fibrex. change wall finish stucco to hardie architectural panel. no change to the exterior envelope, total sq ft orDetails
revision to approved pa # 2021-0317-6756 add 3 (n) bathrooms, relocate the kitchen & reconfigure interior walls. rear yard design. change window frame material from aluminum to fibrex. change wall finish stucco to hardie architectural panel. no change to the exterior envelope, total sq ft or | $23,100 |
| Jul 8, 2024 | In progress issued Sep 2024 | 80 Lomita Av | new horizontal addition of 251 sf w/new family rm, powder rm, new elevator. reconfigure e) stairway at entry lvl hall. e) kitchen remodel & expansion. replace e) select windows in kind. interior walls reconfigure. new skylight, new rear deck. extend e) gas service to exterior bbq & fire pit.Details
new horizontal addition of 251 sf w/new family rm, powder rm, new elevator. reconfigure e) stairway at entry lvl hall. e) kitchen remodel & expansion. replace e) select windows in kind. interior walls reconfigure. new skylight, new rear deck. extend e) gas service to exterior bbq & fire pit. | $251,000 | |
| Jun 5, 2023 | Completed final sign-off Jun 2023 | 156 12th Av | to comply wihh nov# 202306387 dbi internal audit. legalize current roof parapet. project is 42" roof perimeter solid wall.Details
to comply wihh nov# 202306387 dbi internal audit. legalize current roof parapet. project is 42" roof perimeter solid wall. | ||
| Feb 9, 2021 | Completed final sign-off Mar 2025 | 99 Bosworth St | Towers Construction | add unit per density. bring ceiling height (level 1) and 2 stairways to compliance. remodel kitchen (level 1) and all bathrooms. reconfigure interior walls. roof deck (level 3). replace all windows, add new windows, and a skylight. add 3 new dormers. remove existing chimney. mep and structural workDetails
add unit per density. bring ceiling height (level 1) and 2 stairways to compliance. remodel kitchen (level 1) and all bathrooms. reconfigure interior walls. roof deck (level 3). replace all windows, add new windows, and a skylight. add 3 new dormers. remove existing chimney. mep and structural work | $272,000 |
| May 30, 2017 | Completed final sign-off Jul 2018 | 1550 Bryant St | Towers Construction | demo of non structural partitions. new non structural partitions. demo of demising wall between suite 555 & 545, create 3 conference rooms, carpet removal, new carpet & installation. mep/fire/life safety, under sep permit maher naDetails
demo of non structural partitions. new non structural partitions. demo of demising wall between suite 555 & 545, create 3 conference rooms, carpet removal, new carpet & installation. mep/fire/life safety, under sep permit maher na | $129,065 |