- On San Francisco permits
- Mar 2010 to Sep 2020
8 permits since 2000 (architect on 5 permits, engineer on 3 permits): 7 completed, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 19, 2020 | Completed final sign-off May 2022 | 362 Judson Av | Anxin Associates Construction Inc. | convert (e) storage area in grage level into 1 bedroom, 1.5 bathrooms. remodel (e) kitchen & (e) bathroom on upper level. replace interior stairs. cover/enclose lightwell.Details
convert (e) storage area in grage level into 1 bedroom, 1.5 bathrooms. remodel (e) kitchen & (e) bathroom on upper level. replace interior stairs. cover/enclose lightwell. | $125,000 |
| Jul 7, 2014 | Completed final sign-off Aug 2014 | 367 17th Av | Emi Design & Construction, Inc | revision to 201201132203. change roof to slate at front elevation. change window moulding, reconfigure 3rd fl bath and master bath, relocate closet at 2nd flDetails
revision to 201201132203. change roof to slate at front elevation. change window moulding, reconfigure 3rd fl bath and master bath, relocate closet at 2nd fl | |
| Dec 12, 2012 | Never finaled issued Dec 2012, no final | 463 Eureka St | D C Design & Construction Services | replace (e) retaining wall in the back yard.Details
replace (e) retaining wall in the back yard. | $5,000 |
| Jul 18, 2011 | Completed final sign-off Aug 2026 | 2945 25th Av | convert e closet to bath at ground floor. replace window (not facing street) at new bathroom.Details
convert e closet to bath at ground floor. replace window (not facing street) at new bathroom. | $5,000 | |
| Apr 1, 2011 | Completed final sign-off Jun 2014 | 463 Eureka St | Barry M Nadell Construction Inc, Jema Construction Inc, D C Design & Construction Services | enlarge garage & add one bedrm, one & half bathroom & one family room at lower level,convert (e) bedrooms & storage rms to living room, dining rm, kitchen & one bathrm at main level, convert (e) living rm, dining room & kitchen to 3 bedrms & 2 bathrms at upper level, add railing for (n) roof deck.Details
enlarge garage & add one bedrm, one & half bathroom & one family room at lower level,convert (e) bedrooms & storage rms to living room, dining rm, kitchen & one bathrm at main level, convert (e) living rm, dining room & kitchen to 3 bedrms & 2 bathrms at upper level, add railing for (n) roof deck. | $105,000 |
| Mar 11, 2011 | Completed final sign-off Feb 2012 | 1839 20th Av | T J Constr Inc***Ck Id,Tie Liu Only***** | add family room, office & full bath @ ground floor. rebuilt interior stair. enclose lower space for office.Details
add family room, office & full bath @ ground floor. rebuilt interior stair. enclose lower space for office. | $45,000 |
| Mar 30, 2010 | Completed final sign-off Nov 2011 | 20 Hoffman Av | Xin Xin Construction | flatten the pitch roof at back portion of the house by building new exterior walls. reduce size of (e) roof deck. add 1 more full bathroom & 1 (n) bedroom on 3rd level. relocate stairway & remodel kitchen & bathroom on 2nd floor. add 1 half bath & 1 laundry room on 1st level.Details
flatten the pitch roof at back portion of the house by building new exterior walls. reduce size of (e) roof deck. add 1 more full bathroom & 1 (n) bedroom on 3rd level. relocate stairway & remodel kitchen & bathroom on 2nd floor. add 1 half bath & 1 laundry room on 1st level. | $82,000 |
| Mar 11, 2010 | Completed final sign-off Jan 2011 | 2832 Anza St | J P E Construction | add one family room, two bedrooms and one full bathroom in garage floor. add one bedroom, one bath in 2nd floor and 3rd floor. enlarge opening, remodel (e) kitchen and (e) bathroom in 2nd floor 3rd floor. replace drywall for 2 (e) bedrooms, (e) dinning room & (e) living room in 2nd level & 3rd levelDetails
add one family room, two bedrooms and one full bathroom in garage floor. add one bedroom, one bath in 2nd floor and 3rd floor. enlarge opening, remodel (e) kitchen and (e) bathroom in 2nd floor 3rd floor. replace drywall for 2 (e) bedrooms, (e) dinning room & (e) living room in 2nd level & 3rd level | $80,000 |