- Oct 2006 to Sep 2026
39 permits since 2000 (architect on 38 permits, engineer on 1 permit): 30 completed, 4 in progress, 3 never finaled, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 17, 2026 | In progress filed Sep 2026, not yet issued | 300 Howard St | 3rd & 4th floors: t.i. including new interior walls, ceilings, millwork and finishes.Details
3rd & 4th floors: t.i. including new interior walls, ceilings, millwork and finishes. | $15,451,442 | |
| Sep 1, 2026 | In progress filed Sep 2026, not yet issued | 300 Howard St | 5ht & 6th fl - ti including new interior walls, ceilings, millwork & finishesDetails
5ht & 6th fl - ti including new interior walls, ceilings, millwork & finishes | $15,451,442 | |
| Dec 16, 2025 | In progress filed Dec 2025, not yet issued | 1089 03rd St | proj-25-625; mou port. ti on 5th, 6th, 7th & 8th floor in (e) 8 story office building. imporvements to include arch, mep, structural, full prep kitchen & satellite food service stations work to accomodate new tenant build out. includes change of occupancy from b to a-2 on lvl 5 & b to a-3 on lvl.7Details
proj-25-625; mou port. ti on 5th, 6th, 7th & 8th floor in (e) 8 story office building. imporvements to include arch, mep, structural, full prep kitchen & satellite food service stations work to accomodate new tenant build out. includes change of occupancy from b to a-2 on lvl 5 & b to a-3 on lvl.7 | $32,500,000 | |
| Oct 15, 2025 | Completed final sign-off Feb 2026 | 505 Howard St | Novo Construction Inc | documenting the 2 way commander system location in the elevator lobby on the 3rd floor .Details
documenting the 2 way commander system location in the elevator lobby on the 3rd floor . | $125,000 |
| Oct 15, 2025 | Completed final sign-off Sep 2026 | 505 Howard St | Novo Construction Inc | installation of phone booths throughout the 2nd, 3rd, and 4th floor.Details
installation of phone booths throughout the 2nd, 3rd, and 4th floor. | $660,000 |
| Sep 12, 2024 | Completed final sign-off Mar 2025 | 1 Harrison St | Truebeck Construction | demo of interior partitions, ceilings, finishes on all floors. structural and architectural upgrades under sep permitDetails
demo of interior partitions, ceilings, finishes on all floors. structural and architectural upgrades under sep permit | $609,000 |
| Aug 29, 2024 | In progress issued Sep 2024 | 444 De Haro St | Skyline Construction | revision to pa#: 202405071536 with revised attachment details for booths on the 2nd flr as they can not be braced to the concrete floor because of radiant coilsDetails
revision to pa#: 202405071536 with revised attachment details for booths on the 2nd flr as they can not be braced to the concrete floor because of radiant coils | |
| Jan 31, 2018 | Completed final sign-off Nov 2018 | 345 Spear St | Bcci Construction Company | 1st floor - add 1 fire rated door in passagewayDetails
1st floor - add 1 fire rated door in passageway | $5,000 |
| Dec 19, 2016 | Completed final sign-off May 2017 | 188 The Embarcadero | Dpr Construction | #420 - interior alterations including walls, coilings, flooring and casework. mechanical, electrical and plumbing work to support new interior space, demo and safe off per the demo drawings. ref. sprinkler permit app#2016-1202-4076. n/a ordinance #155-13Details
#420 - interior alterations including walls, coilings, flooring and casework. mechanical, electrical and plumbing work to support new interior space, demo and safe off per the demo drawings. ref. sprinkler permit app#2016-1202-4076. n/a ordinance #155-13 | $1,200,000 |
| Oct 19, 2016 | Completed final sign-off Jan 2018 | 2 Embarcadero Center | Peacock Construction | 21st floor:demo selected non-structural partitions, ceilings, doors, new non-structural partitions, millwork, ada shower, ceiling, doors, frames and finishes. mep, fire life safty sprinkler under seperate permit. n/a for maherDetails
21st floor:demo selected non-structural partitions, ceilings, doors, new non-structural partitions, millwork, ada shower, ceiling, doors, frames and finishes. mep, fire life safty sprinkler under seperate permit. n/a for maher | $715,000 |
| Aug 9, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to ref pa 201604013708 clearification about technical infeasibility of ada van accessible parking at garage maher naDetails
revision to ref pa 201604013708 clearification about technical infeasibility of ada van accessible parking at garage maher na | |
| Aug 9, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to ref pa 201502037319 clearification about technical infeasibility of ada van accessible parking at garage maher naDetails
revision to ref pa 201502037319 clearification about technical infeasibility of ada van accessible parking at garage maher na | |
| Aug 5, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to (e) pa 201504204092: clarification about technical infeasiblity of ada van accessible parking at garage maher naDetails
revision to (e) pa 201504204092: clarification about technical infeasiblity of ada van accessible parking at garage maher na | |
| Aug 5, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to (e) pa 201505126148: clarification about technical infeasiblity of ada van accessible parking at garage, maher naDetails
revision to (e) pa 201505126148: clarification about technical infeasiblity of ada van accessible parking at garage, maher na | |
| Aug 5, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to (e) pa 201509116686: clarification about technical infeasiblity of ada van accessible parking at garage maher naDetails
revision to (e) pa 201509116686: clarification about technical infeasiblity of ada van accessible parking at garage maher na | |
| Aug 5, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to ref pa 201606028968: clarification about technical infeasibility of ada van accessible parking at garage. maher naDetails
revision to ref pa 201606028968: clarification about technical infeasibility of ada van accessible parking at garage. maher na | |
| Aug 5, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to (e) pa 201504204091 clarification about technical infeasiblity of ada van accessible parking at garage maher naDetails
revision to (e) pa 201504204091 clarification about technical infeasiblity of ada van accessible parking at garage maher na | |
| Aug 5, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | revision to (e) pa 201510210369: clarification about technical infeasiblity of ada van accessible parking at garage maher naDetails
revision to (e) pa 201510210369: clarification about technical infeasiblity of ada van accessible parking at garage maher na | |
| Aug 3, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | 8/f- revision to existing pa#201506048095 to clarify technical infeasibility of ada van accessible parking at garage. n/a ordinance #155-13Details
8/f- revision to existing pa#201506048095 to clarify technical infeasibility of ada van accessible parking at garage. n/a ordinance #155-13 | |
| Aug 3, 2016 | Never finaled issued Aug 2016, no final | 188 The Embarcadero | Dpr Construction Inc | 6/f- revision to existing pa#201511031646 to clarify technical infeasibility of ada van accessible parking at garage. n/a ordinance #155-13Details
6/f- revision to existing pa#201511031646 to clarify technical infeasibility of ada van accessible parking at garage. n/a ordinance #155-13 | |
| Aug 3, 2016 | Completed final sign-off Sep 2016 | 188 The Embarcadero | Dpr Construction Inc | 4/f- revision to existing pa#201506038003 to clarify technical infeasibility of ada van accessible parking at garage. n/a ordinance #155-13Details
4/f- revision to existing pa#201506038003 to clarify technical infeasibility of ada van accessible parking at garage. n/a ordinance #155-13 | |
| Mar 21, 2016 | Completed final sign-off Jun 2017 | 345 Spear St | Bcci Construction Company | minor demolition of 9 existing offices to create more open office space and restroom upgradesDetails
minor demolition of 9 existing offices to create more open office space and restroom upgrades | $205,700 |
| Sep 11, 2015 | Never finaled issued Sep 2015, no final | 188 The Embarcadero | Dpr Construction | 2nd floor: ti - addition of conference rooms and open office seating. mep & electrical included. maher naDetails
2nd floor: ti - addition of conference rooms and open office seating. mep & electrical included. maher na | $2,500,000 |
| Sep 3, 2015 | Completed final sign-off Jan 2016 | 22 04th St | Sc Builders, Inc | minor demo, t.i. construction, upgrade/replace extg card reader, new ada pantry millwork on 4th and 5th floor. n/a for maher.Details
minor demo, t.i. construction, upgrade/replace extg card reader, new ada pantry millwork on 4th and 5th floor. n/a for maher. | $40,000 |
| Jul 28, 2015 | Completed final sign-off Feb 2016 | 188 The Embarcadero | Dpr Construction | revision to pa#201506048095 re-arranging some conference room walls. n/a ordinance #155-13.Details
revision to pa#201506048095 re-arranging some conference room walls. n/a ordinance #155-13. | |
| Jun 29, 2015 | Expired or cancelled cancelled Jan 2026 | 188 The Embarcadero | Dpr Construction | 5th floor: permit ammendment: utilize class rading of wood in decorative trellis as suitable material in lieu of fire resistive paint. ref pa# #201504204092. n/a for maher.Details
5th floor: permit ammendment: utilize class rading of wood in decorative trellis as suitable material in lieu of fire resistive paint. ref pa# #201504204092. n/a for maher. | |
| Jun 29, 2015 | Expired or cancelled cancelled Jan 2026 | 188 The Embarcadero | Dpr Construction | 3rd floor: permit ammendment: utilize class rading of wood in decorative trellis as suitable material in lieu of fire resistive paint. revision to pa #201504204091. n/a for maher.Details
3rd floor: permit ammendment: utilize class rading of wood in decorative trellis as suitable material in lieu of fire resistive paint. revision to pa #201504204091. n/a for maher. | |
| May 11, 2015 | Completed final sign-off Nov 2016 | 22 04th St | Sc Builders, Inc | floors 8,9,11 & 13: replace extg and add new card reader devices at stairwells elevator doors and misc, and closets those floors. also replace new lobby doors at floor 8,9 & 13. minor partition demo on floor 8. n/a for maher.Details
floors 8,9,11 & 13: replace extg and add new card reader devices at stairwells elevator doors and misc, and closets those floors. also replace new lobby doors at floor 8,9 & 13. minor partition demo on floor 8. n/a for maher. | $20,000 |
| Apr 22, 2015 | Completed final sign-off Aug 2015 | 22 04th St | Dpr Construction | 6th floor: t.i. to upgrade office space. work includes refurbishing open office, private offices, breakfast, and training room. n/a for the maher.Details
6th floor: t.i. to upgrade office space. work includes refurbishing open office, private offices, breakfast, and training room. n/a for the maher. | $200,000 |
| Mar 16, 2015 | Completed final sign-off Jan 2016 | 505 Howard St | Skyline Construction | 8th floor: electrical work for t.i. ref app#201502047414. n/a for the maher.Details
8th floor: electrical work for t.i. ref app#201502047414. n/a for the maher. | $30,000 |
| Feb 11, 2015 | Completed final sign-off Oct 2015 | 22 04th St | Dpr Construction | t.i. to upgrade office space on 3/f. work includes breakroom, restroom expansion, refurbishing, open and private offices, scope of work also includes training room. no increase in square footage, no change in use. n/a ordinance #155-13Details
t.i. to upgrade office space on 3/f. work includes breakroom, restroom expansion, refurbishing, open and private offices, scope of work also includes training room. no increase in square footage, no change in use. n/a ordinance #155-13 | $822,000 |
| Feb 11, 2015 | Never finaled issued Feb 2015, no final | 22 04th St | Dpr Construction | soft demolition of 3/f & 10/f, ab-17 compliant. n/a ordinance #155-13Details
soft demolition of 3/f & 10/f, ab-17 compliant. n/a ordinance #155-13 | $80,000 |
| Feb 11, 2015 | Completed final sign-off Jul 2015 | 22 04th St | Dpr Construction | t.i. to upgrade office space on 10/f. work includes breakroom, restroom expansion, refurbishing, open and private offices. no increase in square footage, no change in use. n/a ordinance #155-13Details
t.i. to upgrade office space on 10/f. work includes breakroom, restroom expansion, refurbishing, open and private offices. no increase in square footage, no change in use. n/a ordinance #155-13 | $822,000 |
| Feb 3, 2015 | Completed final sign-off Oct 2016 | 188 The Embarcadero | Dpr Construction | new interior build out of idf room on 3rd fl. minor mech and elec work. 1 floor drain. somoe work on 2nd fl to support 3rd fl room. no changes to e fire alarm or smoke systemsDetails
new interior build out of idf room on 3rd fl. minor mech and elec work. 1 floor drain. somoe work on 2nd fl to support 3rd fl room. no changes to e fire alarm or smoke systems | $110,000 |
| Aug 18, 2014 | Completed final sign-off Jun 2016 | 345 Spear St | Bcci Construction Company | t.i. on 3/f including new offices, conference rooms & restrooms. mechanical, electrical, fire alarm system & fire sprinkler system under seperate permit. n/a ordinance #155-13.Details
t.i. on 3/f including new offices, conference rooms & restrooms. mechanical, electrical, fire alarm system & fire sprinkler system under seperate permit. n/a ordinance #155-13. | $3,805,000 |
| Aug 14, 2014 | Completed final sign-off Sep 2014 | 345 Spear St | Bcci Construction Company | 1st floor tenant improvement including new non-load bearing partitions & finiahes. associated life safety under spearate permit. n/a maher ordinanceDetails
1st floor tenant improvement including new non-load bearing partitions & finiahes. associated life safety under spearate permit. n/a maher ordinance | $145,000 |
| Aug 8, 2013 | Completed final sign-off Feb 2016 | 1600 Owens St | The Whiting-Turner Contracting Company | altered site permit. change of occupancy from what was approved, change from l occupancy to b office occupancy. admin bulletin no# ab-032 for refrence. original site permit approved under pa# 2007/11/09/7802s. reduce stories from 10 stories to 9 stories.Details
altered site permit. change of occupancy from what was approved, change from l occupancy to b office occupancy. admin bulletin no# ab-032 for refrence. original site permit approved under pa# 2007/11/09/7802s. reduce stories from 10 stories to 9 stories. | $1,000,000 |
| Oct 10, 2006 | Completed final sign-off Oct 2007 | 1700 Owens St | oti-2 on 5th floor, new m.e.p.Details
oti-2 on 5th floor, new m.e.p. | $13,500 | |
| Oct 10, 2006 | Completed final sign-off Oct 2007 | 1700 Owens St | oti-1 of partial 5th floor (1670 sq.ft.), new partitions for divided office space. first time tenant built out office space.Details
oti-1 of partial 5th floor (1670 sq.ft.), new partitions for divided office space. first time tenant built out office space. | $25,000 |