M.L. Hicks
- Listed as
- architect, authorized agent-others, engineer, pmt consultant/expediter
- Firm
- Sheerline Structural Engineer
- Based in
- San Francisco
- On San Francisco permits
- Jan 2003 to Mar 2022
81 permits since 2000 (engineer on 78 permits, architect on 1 permit, authorized agent-others on 1 permit, pmt consultant/expediter on 1 permit): 60 completed, 1 in progress, 10 never finaled, 10 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 25, 2022 | Completed final sign-off May 2022 | 99 Prospect Av | Underpinning Specialist Inc. | repairs to existing concrete garage.Details
repairs to existing concrete garage. | $30,000 |
| Jan 27, 2020 | Completed final sign-off May 2020 | 232 Diamond St | E H B Construction | foundation repair in response to correction noticeDetails
foundation repair in response to correction notice | $8,000 |
| Jan 9, 2020 | Completed final sign-off Sep 2024 | 78 Parker Av | soft story retrofit per sfebc chapter 4d engineering 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering 2016 cebc appendix a-4 | $75,500 | |
| Nov 26, 2019 | Completed final sign-off Jan 2022 | 123 Ripley St | Nolan Construction Inc | (south building) soft story retrofit per sfebc ch.4d - 2016 cebc appendex a-4. maher n/a.Details
(south building) soft story retrofit per sfebc ch.4d - 2016 cebc appendex a-4. maher n/a. | $75,000 |
| Nov 19, 2019 | Completed final sign-off Jul 2020 | 901 Stanyan St | Gartan Construction, Connor Daly Corporation | ref pa# 201808036432 & soft story retrofit per ab-107 & accessability improvementDetails
ref pa# 201808036432 & soft story retrofit per ab-107 & accessability improvement | |
| Nov 7, 2019 | Never finaled filed Nov 2019, never issued | 1534 Taylor St | F P Investments Inc | to comply with nov #201987601. soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4.Details
to comply with nov #201987601. soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. | $20,000 |
| Nov 7, 2019 | Completed final sign-off Mar 2022 | 45 28th St | interior renovation to (e) g/f unit, convert (e) storage into bedroom, relocate laundry & full bathroom, add new 1/2 bathroom, expand (e) bedroom merge with (e) office+. reducing height of (e) roof deck, reducing rear stairs, partial foundation replacement.Details
interior renovation to (e) g/f unit, convert (e) storage into bedroom, relocate laundry & full bathroom, add new 1/2 bathroom, expand (e) bedroom merge with (e) office+. reducing height of (e) roof deck, reducing rear stairs, partial foundation replacement. | $160,000 | |
| Oct 22, 2019 | Completed final sign-off Aug 2020 | 1386 Golden Gate Av | mandatory accessible entrance compliance permit for new entry location at westside to accomodate ada ramp, interior remodel. relocation of exam rooms, reception and waiting area. some structural work. n/a for maherDetails
mandatory accessible entrance compliance permit for new entry location at westside to accomodate ada ramp, interior remodel. relocation of exam rooms, reception and waiting area. some structural work. n/a for maher | $70,000 | |
| Sep 17, 2019 | Completed final sign-off Jun 2021 | 839 Broderick St | mandatory soft story retrofit - soft story retrofit per sfebc chapter 4d & 2016 cebc appx a4 & sf ab-107Details
mandatory soft story retrofit - soft story retrofit per sfebc chapter 4d & 2016 cebc appx a4 & sf ab-107 | $210,000 | |
| Aug 12, 2019 | Expired or cancelled withdrawn Jan 2021 | 123 Ripley St | (north building) mandatory seismic retrofit soft-story retrofit per sfebc chapter 4d & 2016 cebc appendix a-4Details
(north building) mandatory seismic retrofit soft-story retrofit per sfebc chapter 4d & 2016 cebc appendix a-4 | $125,000 | |
| Jul 17, 2019 | Completed final sign-off Dec 2020 | 2350 Union St | L E C A Construction Llc | revision to 201710060622 soft story retrofit per 2016 cebc appx a-4: shear walls changes (2)Details
revision to 201710060622 soft story retrofit per 2016 cebc appx a-4: shear walls changes (2) | |
| Jun 24, 2019 | Never finaled issued Jul 2019, no final | 25 Hotaling Pl | Ken O'sullivan Construction And Renovati | re-support of rooftop hvac equipment for noise reduction.Details
re-support of rooftop hvac equipment for noise reduction. | $20,000 |
| Feb 14, 2019 | Completed final sign-off Feb 2020 | 2108 Castro St | Alef Construction Corp | remodel the back of the house, the (e) bathroom to be relocated, shower will only be installed, west wall wll have a 11'0" nana wall installed, (n) electrical & plumbing only in area of remodelDetails
remodel the back of the house, the (e) bathroom to be relocated, shower will only be installed, west wall wll have a 11'0" nana wall installed, (n) electrical & plumbing only in area of remodel | $95,000 |
| Feb 11, 2019 | Never finaled issued Feb 2019, no final | 690 Arguello Bl | Pellandini & Company | unit 101:interior remodel to e codo. relocate interior wall and replace door between master bath and master closet, remove interior wall by kitchen, structural interior wall by kitchen, replace add light fixtures, plumbing, wall finishes, floorDetails
unit 101:interior remodel to e codo. relocate interior wall and replace door between master bath and master closet, remove interior wall by kitchen, structural interior wall by kitchen, replace add light fixtures, plumbing, wall finishes, floor | $100,000 |
| Aug 16, 2018 | Completed final sign-off Jul 2019 | 1630 Clay St | revision to 9906098 and 201808147250 modifications to framingDetails
revision to 9906098 and 201808147250 modifications to framing | $30,000 | |
| Aug 3, 2018 | Completed final sign-off Jul 2019 | 3916 Sacramento St | Brellin Company | construct new roof deck. new internal staircase from 3rd floor to new roof deck.Details
construct new roof deck. new internal staircase from 3rd floor to new roof deck. | $100,000 |
| Aug 3, 2018 | Completed final sign-off Jul 2020 | 901 Stanyan St | new accesible entrance in conjunction w/ mandatory soft story upgrade/retrofit per sfebc chapter 4-d. for commercial only. residential portion #201808036434.Details
new accesible entrance in conjunction w/ mandatory soft story upgrade/retrofit per sfebc chapter 4-d. for commercial only. residential portion #201808036434. | $12,750 | |
| Apr 27, 2018 | Completed final sign-off Nov 2019 | 2395 29th Av | Itu Construction | mandatory soft story retrofit per sfebc chapter 4d cebc appx a4 residential commercial ref - 201804277595Details
mandatory soft story retrofit per sfebc chapter 4d cebc appx a4 residential commercial ref - 201804277595 | $125,000 |
| Apr 27, 2018 | Completed final sign-off Nov 2019 | 2395 29th Av | Itu Construction | mandatory soft story retrofit per sfebc chapter 4d cebc appx a4 commercial residential ref - 201804277596Details
mandatory soft story retrofit per sfebc chapter 4d cebc appx a4 commercial residential ref - 201804277596 | $25,000 |
| Mar 16, 2018 | Completed final sign-off Nov 2019 | 1813 15th St | D K G Construction Inc | soft story retrofit in accordance w/ sfebc chp 4d & 2016 cebc appendix a-4Details
soft story retrofit in accordance w/ sfebc chp 4d & 2016 cebc appendix a-4 | $83,000 |
| Mar 6, 2018 | Never finaled issued Feb 2020, no final | 1534 Taylor St | F P Investments Inc | soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4 | $20,000 |
| Mar 6, 2018 | Completed final sign-off Nov 2019 | 359 Green St | F P Investments Inc | soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d: 2016 cebc appendix a-4 | $100,000 |
| Feb 23, 2018 | Completed final sign-off Jul 2019 | 704 Wisconsin St | M M I A Inc Dba Keith Fontana Constructi | revision to pa #201502037358, which included (renovate e residence, add a floor & horiz addit @ rear. rebuild e front entry stair & bay. renovate e kitchen & bathrms. remeove & replace substandard 2nd floor framing @ kitchen area.) new scope to reframe substandard floor framing per inspector requestDetails
revision to pa #201502037358, which included (renovate e residence, add a floor & horiz addit @ rear. rebuild e front entry stair & bay. renovate e kitchen & bathrms. remeove & replace substandard 2nd floor framing @ kitchen area.) new scope to reframe substandard floor framing per inspector request | $12,000 |
| Feb 5, 2018 | Completed final sign-off Jan 2020 | 250 Beacon St | repair 3 exsting exterior decks in-kindDetails
repair 3 exsting exterior decks in-kind | $40,000 | |
| Dec 13, 2017 | Completed final sign-off Oct 2018 | 2108 Castro St | Alef Construction Corp | revision # 2017-0306-0712. wall moved in master bedrooom required structural engineering for roof support.Details
revision # 2017-0306-0712. wall moved in master bedrooom required structural engineering for roof support. | $4,500 |
| Nov 27, 2017 | Completed final sign-off Oct 2019 | 815 Burnett Av | Vector Construction Inc. | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201719791Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201719791 | $50,000 |
| Nov 27, 2017 | Completed final sign-off Aug 2019 | 1416 Broadway | Vector Construction Inc. | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201714506Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201714506 | $75,000 |
| Nov 27, 2017 | Completed final sign-off Aug 2019 | 740 Monterey Bl | Vector Construction Inc. | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201719791Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201719791 | $20,000 |
| Nov 27, 2017 | Completed final sign-off Jul 2019 | 32 Lundys Ln | Vector Construction Inc. | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201719791Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. to comply with nov 201719791 | $40,000 |
| Nov 9, 2017 | In progress issued Jan 2024 | 113 Precita Av | to construct a (n) one bedroom apartment in the basement of an (e) 2 unit buildging.the apartment will have one bedroom, living & dining room, kitchen & bath. adu oridinace 162-16 (n) electrical, lighting & mechanical.Details
to construct a (n) one bedroom apartment in the basement of an (e) 2 unit buildging.the apartment will have one bedroom, living & dining room, kitchen & bath. adu oridinace 162-16 (n) electrical, lighting & mechanical. | $150,000 | |
| Nov 6, 2017 | Completed final sign-off Dec 2019 | 880 Oak St | L E C A Construction Llc | soft story retrofit per sfebc ch 4d 2016 cebc app a4Details
soft story retrofit per sfebc ch 4d 2016 cebc app a4 | $40,000 |
| Oct 6, 2017 | Completed final sign-off Jan 2021 | 2350 Union St | soft story retrofit using 2016cebc ch. 4d. engineering criteria appendeix a-4. maher n/a.Details
soft story retrofit using 2016cebc ch. 4d. engineering criteria appendeix a-4. maher n/a. | $150,000 | |
| Oct 4, 2017 | Completed final sign-off Aug 2018 | 385 Santa Clara Av | Upscale Construction Inc. | replace (e) property line retaining wall with concrete retaining wall.Details
replace (e) property line retaining wall with concrete retaining wall. | $25,000 |
| Sep 22, 2017 | Completed final sign-off May 2021 | 1359 Hayes St | Rei Build Up Construction Corp | soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4.Details
soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. | $120,000 |
| Sep 15, 2017 | Completed final sign-off Aug 2018 | 2687 Mcallister St | Kalix Inc Dbalara Construction | soft story retrofit mandatory per sfebc ch 4d and 2016 cebc app a4Details
soft story retrofit mandatory per sfebc ch 4d and 2016 cebc app a4 | $70,000 |
| Sep 15, 2017 | Completed final sign-off Jan 2020 | 1822 Mcallister St | Pellandini & Company | mandatory steismic retrofit, soft story retrofit per 2016 cebc appex a4, sfebc ch 4dDetails
mandatory steismic retrofit, soft story retrofit per 2016 cebc appex a4, sfebc ch 4d | $10,000 |
| Sep 12, 2017 | Completed final sign-off Jun 2019 | 1706 Steiner St | soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. commercialDetails
soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. commercial | $7,500 | |
| Sep 12, 2017 | Completed final sign-off Jun 2019 | 1706 Steiner St | soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. residentialDetails
soft story retrofit per sfebc chapter 4d per engineering criteria 2016 cebc appendix a-4. residential | $92,500 | |
| Aug 1, 2017 | Completed final sign-off Jan 2018 | 2134 Green St | Narrowback Construction Co. | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. n/a for maherDetails
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. n/a for maher | $120,000 |
| Jul 20, 2017 | Completed final sign-off Aug 2018 | 1200 Francisco St | Jari Construction Inc | soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4. all work in garage, adding plywood to (e) walls, install new shearwalls, foundation work includes adding a new grade beam at new shearwalls and install holdowns into existing foundation.Details
soft story retrofit per sfebc chapter 4d, 2016 cebc appendix a-4. all work in garage, adding plywood to (e) walls, install new shearwalls, foundation work includes adding a new grade beam at new shearwalls and install holdowns into existing foundation. | $150,000 |
| Jul 18, 2017 | Completed final sign-off Nov 2018 | 208 02nd Av | Graham Moore Construction Inc | revision to the original proposed deck permit #201411121329. reducing of the utility room & structural changes to lower deck guardrails will be changed from wire mesh to glass & a built in bench will be constructed by light wellDetails
revision to the original proposed deck permit #201411121329. reducing of the utility room & structural changes to lower deck guardrails will be changed from wire mesh to glass & a built in bench will be constructed by light well | $1,500 |
| Jun 15, 2017 | Completed final sign-off Jan 2018 | 2360 03rd St | Buck O'neill Builders Inc. | revision to pa #201612155028 - shear wall @ mid-wall.Details
revision to pa #201612155028 - shear wall @ mid-wall. | $3,500 |
| May 17, 2017 | Completed final sign-off Jun 2018 | 1846 Van Ness Av | Kalix Inc Dbalara Construction | revision to pa 2016-1222-5675 & 2016-1222-5676, soft story retrofit per sfbc chapter 34b engineering criteria 2012 iebc appendix a-4. revision to shear walls are being removed from original design as they are located in residential space and not in the target story portion of the level. n/a maherDetails
revision to pa 2016-1222-5675 & 2016-1222-5676, soft story retrofit per sfbc chapter 34b engineering criteria 2012 iebc appendix a-4. revision to shear walls are being removed from original design as they are located in residential space and not in the target story portion of the level. n/a maher | |
| Mar 8, 2017 | Completed final sign-off Nov 2018 | 1905 Laguna St | Alef Construction Corp | common area- soft story retrofit per sfebc chapter 4d, 2012 iebc appendix a-4. install hardy frames in garage, underpinning concrete pads are being installed at the hardy frames.Details
common area- soft story retrofit per sfebc chapter 4d, 2012 iebc appendix a-4. install hardy frames in garage, underpinning concrete pads are being installed at the hardy frames. | $80,000 |
| Jan 11, 2017 | Expired or cancelled cancelled Feb 2019 | 365 Upper Tr | Jeff King And Company Inc | addition of rear yard decks with step lighting and gas fire pit. no change to (e) building envelope or encroachment into rear yard area as defined by sf planning code sec. 136(c)(24)(b)Details
addition of rear yard decks with step lighting and gas fire pit. no change to (e) building envelope or encroachment into rear yard area as defined by sf planning code sec. 136(c)(24)(b) | $10,000 |
| Dec 22, 2016 | Completed final sign-off Jun 2018 | 1846 Van Ness Av | Kalix Inc Dbalara Construction | soft story retrofit per sfbc chapter 34b engineering criteria other rational design (commercial) this permit is related to 201612225675Details
soft story retrofit per sfbc chapter 34b engineering criteria other rational design (commercial) this permit is related to 201612225675 | $17,000 |
| Dec 22, 2016 | Completed final sign-off Jun 2018 | 1846 Van Ness Av | Kalix Inc Dbalara Construction | soft story retrofit per sfbc chapter 34b engineering criteria other rational design (residential)Details
soft story retrofit per sfbc chapter 34b engineering criteria other rational design (residential) | $68,000 |
| Oct 14, 2016 | Never finaled issued Oct 2016, no final | 63 Clarendon Av | Kalix Inc Dbalara Construction | revision to app#201212286964. revising support at inside garage.Details
revision to app#201212286964. revising support at inside garage. | |
| Sep 23, 2016 | Expired or cancelled expired Apr 2019 | 888 De Haro St | Kalix Inc Dbalara Construction | rear bldg. legalize an (e) 1st floor unit by remodeling/recreating kitchen, remodel (e) bathroom, add cabinet & living room & a closet @ new bedroom. all electrical & heating @ 1st floor only to be upgrade, two new property line windows.Details
rear bldg. legalize an (e) 1st floor unit by remodeling/recreating kitchen, remodel (e) bathroom, add cabinet & living room & a closet @ new bedroom. all electrical & heating @ 1st floor only to be upgrade, two new property line windows. | $45,000 |
| Aug 18, 2016 | Completed final sign-off Sep 2017 | 340 Baker St | Alef Construction Corp | seismic retrofit of first floor new shearwalls to be installed with shearwall holddowns installed with epoxy anchorage. new hardy frame shear panels to be installed with a new concrete pad foundation at eache hardy frame. appdx a4.Details
seismic retrofit of first floor new shearwalls to be installed with shearwall holddowns installed with epoxy anchorage. new hardy frame shear panels to be installed with a new concrete pad foundation at eache hardy frame. appdx a4. | $35,000 |
| Apr 15, 2016 | Completed final sign-off Jul 2019 | 538 Mississippi St | Twin Pinnacles Construction | add 1-story rear addition under (e) porch for 2nd unit. add stair and convert (e) attic to bedroom/bath with balcony.Details
add 1-story rear addition under (e) porch for 2nd unit. add stair and convert (e) attic to bedroom/bath with balcony. | $320,000 |
| Mar 18, 2016 | Expired or cancelled withdrawn Apr 2016 | 523 Guerrero St | soft story retrofit per sfbc chapter 34b engineering critaria per other rational design. voluntary seismic retrofit per ab-094Details
soft story retrofit per sfbc chapter 34b engineering critaria per other rational design. voluntary seismic retrofit per ab-094 | $15,000 | |
| Jan 22, 2016 | Completed final sign-off Apr 2019 | 365 Upper Tr | Jeff King And Company Inc | add a (n) playroom, wine room & powder room to existing crawl space of (e) bldg envelope. (n) glazed opening on west facing facade opens to a (n) exterior deck within the footprint of (e) decks above, (n) rear yard access stair, (n) fire sprinklers @ addition under seperate permit. n/a maherDetails
add a (n) playroom, wine room & powder room to existing crawl space of (e) bldg envelope. (n) glazed opening on west facing facade opens to a (n) exterior deck within the footprint of (e) decks above, (n) rear yard access stair, (n) fire sprinklers @ addition under seperate permit. n/a maher | $140,000 |
| May 21, 2015 | Expired or cancelled expired Jan 2022 | 2170 Hayes St | Kalix Inc Dbalara Construction | modify building support to allow removal of central post line & capture lightwell area for improved parking. infill lightwell @ garage only.Details
modify building support to allow removal of central post line & capture lightwell area for improved parking. infill lightwell @ garage only. | $100,000 |
| Jun 13, 2014 | Never finaled issued Oct 2016, no final | 1000 Fulton St | Magnolia Development Inc. | installation of roof maintenance walkway on north side of roof with minimum required safety height for railing, accessed by (e) fire escape on east facade, per coa case no. 2013.0490aDetails
installation of roof maintenance walkway on north side of roof with minimum required safety height for railing, accessed by (e) fire escape on east facade, per coa case no. 2013.0490a | $50,000 |
| May 2, 2014 | Expired or cancelled cancelled Dec 2015 | 523 Guerrero St | voluntary structural strengthening of lower story.Details
voluntary structural strengthening of lower story. | $6,000 | |
| May 1, 2014 | Completed final sign-off Apr 2015 | 449 Douglass St | Cal C A D E Construction Inc | add dormer, add windows, lower deck. remove interior walls, lower floor of studio apratment. remodel 2 kitchens and 2 bathrooms per plan. no fire wall required.Details
add dormer, add windows, lower deck. remove interior walls, lower floor of studio apratment. remodel 2 kitchens and 2 bathrooms per plan. no fire wall required. | $300,000 |
| Dec 30, 2013 | Completed final sign-off Dec 2018 | 3045 23rd St | (front bldg).compliance with ordinance no.155-13 not required. excavation <50 cu.yd. remodel lower, upper & expand upper unit into attic. new mechanical systems, new kitchens & applicance. new bath fixtures. replace (e) wood windows with new wood windows to match. add (2) dormers & deck at rear ofDetails
(front bldg).compliance with ordinance no.155-13 not required. excavation <50 cu.yd. remodel lower, upper & expand upper unit into attic. new mechanical systems, new kitchens & applicance. new bath fixtures. replace (e) wood windows with new wood windows to match. add (2) dormers & deck at rear of | $375,000 | |
| Jul 18, 2013 | Completed final sign-off Aug 2014 | 4379 23rd St | Douglas Gower Dba Mesa Construction | rotate (n) entry door by 27 degree so as to gain more access space & change method of foundation construction. rev. pa# 201306048576Details
rotate (n) entry door by 27 degree so as to gain more access space & change method of foundation construction. rev. pa# 201306048576 | |
| Oct 9, 2012 | Never finaled issued Oct 2012, no final | 549 Jersey St | expand an existing interior wall opening from 5'0 to 10'0. also an exhaust hood will be replaced over range. new lighting in living room.Details
expand an existing interior wall opening from 5'0 to 10'0. also an exhaust hood will be replaced over range. new lighting in living room. | $5,000 | |
| Oct 4, 2012 | Never finaled issued Oct 2012, no final | 51 Grattan St | Design Line Construction | revision to pa# 2011-0805-1856/s1/r1-revised shoring & retaining wall due to site conditions, revised rear s.w for z-wall, replace foundation & minor framing revisionsDetails
revision to pa# 2011-0805-1856/s1/r1-revised shoring & retaining wall due to site conditions, revised rear s.w for z-wall, replace foundation & minor framing revisions | $20,000 |
| Jul 6, 2012 | Completed final sign-off Aug 2014 | 4379 23rd St | Douglas Gower Dba Mesa Construction | rebuild (e) laundry shed on 1st fl. add 6'x17' deck at 2nd fl, rear. replace all windows of 2nd fl, rear gable end. reinsulate & sheet rock rear bedroom. convert (e) basement into an inlaw apartment.Details
rebuild (e) laundry shed on 1st fl. add 6'x17' deck at 2nd fl, rear. replace all windows of 2nd fl, rear gable end. reinsulate & sheet rock rear bedroom. convert (e) basement into an inlaw apartment. | $75,000 |
| Oct 3, 2011 | Completed final sign-off Jun 2012 | 307 Duncan St | remodel the (e) kitchen anon bearing wall will be partially removed between the kitchen & the dining room. lighting will be added to the dining room. all windows, skylights & doors to remain without change. no exterior work to be performed.Details
remodel the (e) kitchen anon bearing wall will be partially removed between the kitchen & the dining room. lighting will be added to the dining room. all windows, skylights & doors to remain without change. no exterior work to be performed. | $30,000 | |
| Sep 12, 2011 | Completed final sign-off Dec 2011 | 216 Eddy St | D.F.P.F Corp Dba Fine Line Construction | roof-upgrades to roof rafters for installing solar thermal panelsDetails
roof-upgrades to roof rafters for installing solar thermal panels | $15,000 |
| Sep 12, 2011 | Completed final sign-off Dec 2011 | 34 Turk St | D.F.P.F Corp Dba Fine Line Construction | roof-upgrades to roof rafters for installing solar thermal panelsDetails
roof-upgrades to roof rafters for installing solar thermal panels | $11,700 |
| Jul 20, 2011 | Completed final sign-off Jul 2012 | 963 Hampshire St | interior renovation on 2 levels including two storage rooms and full bathroom @ rear garage level. rebuilding of existing rear shed with new living space with existing bldg envelope, new stair & new windows at rear.Details
interior renovation on 2 levels including two storage rooms and full bathroom @ rear garage level. rebuilding of existing rear shed with new living space with existing bldg envelope, new stair & new windows at rear. | $65,000 | |
| May 12, 2011 | Completed final sign-off Nov 2011 | 1567 Shrader St | Altmann & Associates, Inc | revision to appl #201012086337: move laundry closet, delete wet bar, expand ground floor mud room, relocate garage door to original location at front of bldg. steam shower @ master bath (modify existing shower).Details
revision to appl #201012086337: move laundry closet, delete wet bar, expand ground floor mud room, relocate garage door to original location at front of bldg. steam shower @ master bath (modify existing shower). | $5,000 |
| Mar 23, 2011 | Expired or cancelled cancelled Jan 2026 | 552 Arlington St | removal & replacement of (e) retaining wall, replace of front foundation, repair of sewer line.Details
removal & replacement of (e) retaining wall, replace of front foundation, repair of sewer line. | $25,000 | |
| Feb 24, 2011 | Never finaled issued Aug 2011, no final | 226 27th St | High Tech Construction | improve structure,replace concrete slab @ grd flr unit,new moment frame,seismic upgrade entire bldg,relocate unit,improve interior. revise pa200808229885/201006033742 renov.kitchen+bath unit 1. install new storage in garage(correct prior pa200808229885 identify as (e) res unit as laudry rmDetails
improve structure,replace concrete slab @ grd flr unit,new moment frame,seismic upgrade entire bldg,relocate unit,improve interior. revise pa200808229885/201006033742 renov.kitchen+bath unit 1. install new storage in garage(correct prior pa200808229885 identify as (e) res unit as laudry rm | $20,000 |
| Dec 31, 2010 | Expired or cancelled expired Feb 2018 | 3973 19th St | Flaherty Brothers Construction Inc | removal of 2nd internal egress stair from lower unit. (3973) removal of non structural partition between garage and common stair. relocation of e post between garage doors, new garage door, enlarge curb cutDetails
removal of 2nd internal egress stair from lower unit. (3973) removal of non structural partition between garage and common stair. relocation of e post between garage doors, new garage door, enlarge curb cut | $16,500 |
| Oct 5, 2010 | Never finaled issued Jun 2012, no final | 27 Liberty St | replace rear existing, non-conforming, required egress stair with code-compliant stair.Details
replace rear existing, non-conforming, required egress stair with code-compliant stair. | $32,000 | |
| Jun 18, 2010 | Completed final sign-off Nov 2010 | 1142 De Haro St | Tom Ehline | add to top of basement foundation so as to aleviate existing earth to wood conditoin on the north wall. approx 32' from rear end of buildingDetails
add to top of basement foundation so as to aleviate existing earth to wood conditoin on the north wall. approx 32' from rear end of building | $30,000 |
| Oct 27, 2009 | Completed final sign-off May 2010 | 940 Union St | Matarozzi/Pelsinger Builders Inc. | revision to 200904216734. modify framing and foundations for basement apartmentDetails
revision to 200904216734. modify framing and foundations for basement apartment | |
| Jun 1, 2007 | Completed final sign-off Jan 2008 | 1983 15th St | Dore Const. Of Calif. Inc. | remodel of existing residential unit to include new kitchen, 2 new bathrooms & replacement of 12 (e) windows. upgrade electric service panel and install new rough plumbing & electric throughout unit. voluntary lateral strengthening in garage area. no calculation has been reviewed.Details
remodel of existing residential unit to include new kitchen, 2 new bathrooms & replacement of 12 (e) windows. upgrade electric service panel and install new rough plumbing & electric throughout unit. voluntary lateral strengthening in garage area. no calculation has been reviewed. | $85,000 |
| Oct 31, 2006 | Completed final sign-off Feb 2009 | 8 Kronquist Ct | Kalix Inc Dbalara Construction | new retaining walls at rear yard. max ht. 5'.Details
new retaining walls at rear yard. max ht. 5'. | $7,000 |
| Oct 31, 2005 | Expired or cancelled expired Apr 2006 | 45 Liberty St | Century Design & Construction | revision to app#200307149357 & 200507299017 to change foundation back to concr. clab from prev. apprved wood frame over crawl space.Details
revision to app#200307149357 & 200507299017 to change foundation back to concr. clab from prev. apprved wood frame over crawl space. | |
| Oct 26, 2005 | Completed final sign-off Jan 2011 | 700 Montgomery St | rev.to appl#200301286101 handicapped access issues to comply with adminstrative bulletin#ab-017 sfbc,2001Details
rev.to appl#200301286101 handicapped access issues to comply with adminstrative bulletin#ab-017 sfbc,2001 | $2,700 | |
| Mar 1, 2005 | Completed final sign-off Nov 2005 | 2542 03rd St | umb upgrade, nov corrections, accessibility work at bldg. entrance as per nov #200116433Details
umb upgrade, nov corrections, accessibility work at bldg. entrance as per nov #200116433 | $115,000 | |
| Jan 21, 2005 | Expired or cancelled withdrawn Sep 2007 | 45 Liberty St | Century Design & Construction | revision to 200307149360: to provide a shed dormer for attic stair, and interior floor plan alterDetails
revision to 200307149360: to provide a shed dormer for attic stair, and interior floor plan alter | $3,000 |
| Dec 24, 2004 | Completed final sign-off Feb 2009 | 580 Washington St | Narrowback Construction Co. | seismic retrofit to sfbc 3403.6 to comply w/umb ordinance.access improvements required for above.Details
seismic retrofit to sfbc 3403.6 to comply w/umb ordinance.access improvements required for above. | $250,000 |
| Jan 29, 2003 | Completed final sign-off Sep 2003 | 650 Alvarado St | comply nov 200233187. repair failing retaining wallDetails
comply nov 200233187. repair failing retaining wall | $15,000 |