Julia Seen
- Listed as
- architect
- Firm
- Nelson Architecture,Inc
- Based in
- Pleasanton
- On San Francisco permits
- Jun 2018 to Nov 2025
7 permits since 2000 (architect on 7 permits): 6 completed, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 25, 2025 | Completed final sign-off Dec 2025 | 222 02nd St | Cobe Construction Inc | 14th fl/ installation of ner unistrut grid suspended from the existing floor structure above. this project does not propose any chnages to size, use or occupancy of existing spaces, therefore, the egress is not affected by the installation of new equipment.Details
14th fl/ installation of ner unistrut grid suspended from the existing floor structure above. this project does not propose any chnages to size, use or occupancy of existing spaces, therefore, the egress is not affected by the installation of new equipment. | $7,000 |
| Sep 26, 2025 | Completed final sign-off Dec 2025 | 215 Fremont St | Cobe Construction Inc | 2nd, 3rd and 4th fl. install new bevi water dispensers at (e) break rooms. scope of work includes minor plumbing and casework modifications.Details
2nd, 3rd and 4th fl. install new bevi water dispensers at (e) break rooms. scope of work includes minor plumbing and casework modifications. | $28,526 |
| Sep 26, 2025 | Completed final sign-off Dec 2025 | 121 Spear St | Cobe Construction Inc | floors 2, 5, 6 offices: install new bevi water dispensing unit at existing breakroom, including minor plumbing and case work modification.Details
floors 2, 5, 6 offices: install new bevi water dispensing unit at existing breakroom, including minor plumbing and case work modification. | $28,526 |
| Aug 27, 2025 | Completed final sign-off Jan 2026 | 222 02nd St | Peacock Construction | new non-load bearing interior furred walls. ceiling modification and new floor finish. electrical modification to support new recording studio. ref pa 202404240675Details
new non-load bearing interior furred walls. ceiling modification and new floor finish. electrical modification to support new recording studio. ref pa 202404240675 | $50,000 |
| Dec 17, 2019 | Never finaled issued Jan 2020, no final | 188 Spear St | Skyline Construction | floor finishes (approx 400sf), power work in room 402 elec to be design /buildDetails
floor finishes (approx 400sf), power work in room 402 elec to be design /build | $7,800 |
| Oct 26, 2018 | Completed final sign-off Sep 2022 | 188 Spear St | Anderson Burton Construction Inc | floors 2-8. revision to pa #201806202382. relocation of 24hr comm intercoms (coord. w/201809079405) minor increase in demo, minor decrease in other scopes.Details
floors 2-8. revision to pa #201806202382. relocation of 24hr comm intercoms (coord. w/201809079405) minor increase in demo, minor decrease in other scopes. | |
| Jun 20, 2018 | Completed final sign-off May 2019 | 188 Spear St | Anderson Burton Construction Inc | remove security turnstiles in suites, replace w/door. flrs 2-8Details
remove security turnstiles in suites, replace w/door. flrs 2-8 | $313,000 |